N. STATES POWER CO. v. MINNESOTA DEP'T OF TRANSP.United States Eighth Circuit
Government Contracts, Property Law & Real Estate, Public Utilities, TransportationDefendant had the authority to order plaintiff-utility to relocate its underground facilities in order to make way for the Hiawatha Light Rail Transit... |
02/20/2004 | 03-1517 |
ORFF v. USUnited States Ninth Circuit
Agriculture, Civil Procedure, Contracts, Government Contracts, Government Law, Property Law & Real Estate, Water LawSovereign immunity bars plaintiffs--individual landowners and water users of the Westlands Water District--from suing for alleged violations of a... |
02/18/2004 | 00-16922 |
US v. REITMEYERUnited States Tenth Circuit
Construction, Criminal Law & Procedure, Government ContractsBecause the government failed to commence this action within the seven year limitations period prescribed by the Major Fraud Act, the indictments were... |
02/04/2004 | 02-5151 |
HI-SHEAR TECH. CORP. v. USUnited States Federal Circuit
Contracts, Government Contracts, RemediesCourt of Federal Claims employed a reasonable method of calculating damages arising from the Army's negligent overestimation of its spare parts... |
02/02/2004 | 03-5077 |
WICKWIRE GAVIN, P.C. v. USPSUnited States Fourth Circuit
Government Contracts, Government LawIn response to an information request regarding its contract with Hallmark Cards, Inc., defendant properly invoked FOIA Exemption 3 in withholding... |
01/30/2004 | 02-2310 |
PENNSYLVANIA NAT'L MUT. CAS. INS. CO. v. CITY OF PINE BLUFFUnited States Eighth Circuit
Government Contracts, Insurance LawCity must reimburse its surety for losses the surety suffered after the city released funds to a general contractor despite notice of the contractor's... |
01/15/2004 | 02-3600, 02-3646, 02-3735 |
LIGHTING & POWER SERV., INC. v. ROBERTSUnited States Eighth Circuit
Construction, Government ContractsDistrict court erroneously instructed the jury on the total cost method of recovery by requiring a showing that defendant general contractor had some... |
01/13/2004 | 02-3697 |
ENGLAND v. THE SWANSON GROUP, INC.United States Federal Circuit
Administrative Law, Government ContractsDefendant failed to present to the contracting officer, prior to the contracting officer's settlement determination, a "claim" within the meaning of... |
01/09/2004 | 03-1051 |
PASADENA LIVE, LLC v. CITY OF PASADENACalifornia Court of Appeal
Government Contracts, Property Law & Real EstateParties entered an agreement whereby plaintiff funded improvements to city property in exchange for credit against license fees. Trial court erred in... |
01/07/2004 | B164361 |
EMMA CORP. v. INGLEWOOD UNIFIED SCH. DIST.California Court of Appeal
Construction, Government ContractsTrial court properly found defendant estopped from enforcing plaintiff's original bid on a construction contract. Although plaintiff did not... |
01/06/2004 | B163469 |