[235 U.S. 164, 165] Messrs. R. E. Milling and Mr. M. J. Foster for plaintiff in error.
Mr. I. D. Moore for defendant in error.
Mr. Justice Hughes delivered the opinion of the court:
The plaintiff in error seeks to review the judgment of the state court upon the ground that it denied a Federal right [235 U.S. 164, 166] asserted under the contract clause of the Constitution. Art. 1, 10.
The suit was brought by the mayor of the city of New Orleans, in his official capacity, to restrain the Louisiana Railway & Navigation Company from proceeding under a municipal ordinance-No. 1997, New Council Series, dated September 4, 1903-to construct and operate tracks over a public belt railroad reservation, and from operating cars, etc., over public belt railroad tracks, and to have the ordinance, so far as it granted to that company such privileges of construction and operation, declared null and void. The facts, so far as it is necessary to state them, are these:
The authorities of the city of New Orleans devised the plan of establishing a public belt railroad along the river front. On March 1, 1899, the city adopted an ordinance (No. 15,080, C. S.) under which, in consideration of certain concessions, the Illinois Central Railroad Company built about 2 miles of the projected system, that is, from the upper limit of the city to the upper boundary of Audubon park. This was followed by ordinance No. 147, N. C. S., adopted August 7, 1900, which created a belt railroad board, composed of the mayor and certain city officials, to construct, control, and operate the belt railroad for the benefit of the city; and on August 12, 1902, the board of commissioners of the port of New Orleans, called the 'dock board,'-a body exercising state authority over a part of the area to be traversed by the proposed road,- approved the dedication for the purpose stated. This approval was to remain in force only so long as the belt railroad was 'operated and controlled by a public commission' in accordance with the provisions of ordinance No. 147.
On February 10, 1903, a further ordinance was adopted-No. 1615, N. C. S.-which, among other things, granted to the New Orleans & San Francisco Railroad Company [235 U.S. 164, 167] a right of way over the belt line and reservation from the upper limit of the city to Henderson street. The condition was that the company, at its own expense, should construct and dedicate to perpetual public use the tracks as projected from the end of the line already built, on the upper side of Audubon park, to Henderson street ( a distance of about 5 miles), the construction to be completed before July 1, 1904. Other provisions looked to still further construction through contributions from other railroads. The validity of this ordinance was at once challenged in a suit brought by the mayor, on behalf of the city, which resulted in favor of the railroad company. Capdevielle v. New Orleans & S. F. R. Co. 110 La. 904, 34 So. 868. The terms of the ordinance, however, did not conform to the conditions upon which the dock board had consented to the building of the belt road, and, in a suit brought by that board against the railroad company, the carrying out of ordinance No. 1615 was restrained so far as it authorized the construction of the railroad upon the property subject to the board's jurisdiction. New Orleans v. New Orleans & S. F. R. Co. 112 La. 1011, 36 So. 837. Following this decision, it appears that the New Orleans & San Francisco Railroad Company abandoned the building of the belt line contemplated by the ordinance; no part of it was constructed thereunder.
On September 4, 1903, while the suit of the dock board was pending, and after the final decision in the Capdevielle suit, the city adopted ordinance No. 1997, N. C. S.,-the ordinance here in question (127 La. pp. 784-792, 54 So. 25). Without passing now upon points in controversy, it may be said that this ordinance, reciting that under ordinance No. 1615 there had already been granted to the New Orleans & San Francisco Railroad Company the right to construct the belt line over the reservation from the place at which the rails then terminated to Henderson street, [235 U.S. 164, 168] granted to the Louisiana Railway & Navigation Company-the plaintiff in error-a right of way over 'the double track belt line and reservation' to that point, upon stated terms and conditions, among which may be noted the following: That when the plaintiff in error had operated its equipment over the described belt tracks for thirty days, it should pay to the city the sum of $50,000; that in case the New Orleans & San Francisco Railroad company failed 'without legal excuse' to build the described line to Henderson street, as provided in ordinance No. 1615, the plaintiff in error should build that line in place of the first-mentioned company-this construction to be in lieu of the payment of $50,000, and the belt tracks so built, as soon as completed to Henderson street, to be 'turned over to the immediate ownership of the city of New Orleans,' and to be under 'the control and management of the public belt authority;' and, further, that in case the New Orleans & San Francisco Railroad Company should, from any cause, complete only a portion of the described tracks, the plaintiff in error should have the right to use so much of the described belt line as had been built, on payment of a proportionate part of the specified sum. This ordinance the plaintiff in error formally accepted on September 17, 1903
The suit brought by the dock board against the New Orleans & San Francisco Railroad Company was decided by the supreme court of the state in May, 1904, and, in the October following, the city adopted ordinance No. 2683, N. C. S., which made comprehensive provision for municipal construction and operation of the belt line system. All conflicting ordinances were repealed, and it cannot be doubted that this ordinance, if enforced, would make it impossible for the plaintiff in error to exercise the rights it might otherwise have under ordinance No. 1997. The belt board was reorganized by the establishment of a new public belt railroad commission, com- [235 U.S. 164, 169] posed of the mayor and sixteen 'citizen taxpayers,' to whom was confided the necessary administrative authority for carrying out the municipal scheme. This ordinance received the approval of the dock board on stated conditions, and, on July 1, 1905, the new undertaking was formally inaugurated. On November 10, 1905, the plaintiff in error deposited with a trust company, which was one of the fiscal agents of the city, $50,000 in securities in alleged compliance with its contract under ordinance No. 1997. The city, however, went on with its own plan, arranging for bank credits to enable it to carry on the work under ordinance No. 2683, and when, in May, 1906, the plaintiff in error attempted to begin construction under the earlier ordinance, it was stopped by the city authorities. Soon after, the present suit was instituted.
The petition of the mayor, alleging upon various grounds the invalidity of ordinance No. 1997, also averred the adoption of ordinance No. 2683, the irrevocable dedication thereby for the reservation of the public belt railroad, and the undertaking by the city, under that ordinance, of the work of construction. The plaintiff in error, in its answer, set up the unconstitutionality of the later ordinance as one impairing contractual obligations. At the beginning of the suit a preliminary injunction was granted, in accordance with the city's prayer, and the city proceeded with the construction of the public belt railroad, which has since been put in operation. In the court of first instance, judgment went 'in favor of the plaintiff, Martin Behrman, in his official capacity of mayor of the city of New Orleans, and as ex-officio president of the public belt railroad commission of the city,' declaring ordinance No. 1997, so far as it purported to grant the privileges in dispute, to be 'illegal, void, and of no effect,' and making the injunction permanent. This judgment was affirmed by the supreme court of the state upon the ground that the contract was 'subject to a suspensive [235 U.S. 164, 170] CONDITION, AND THAT THIS CONDITION HAD BEcome impossible of realization, and the contract had, in consequence, fallen through, when plaintiff made its attempt to begin work and the injunction was taken.' 127 La. 775, 795, 796.
The defendant in error moves to dismiss, invoking the established rule that, where the state court gives no effect to the subsequent enactment, the jurisdiction of this court does not attach. Knox v. Exchange Bank, 12 Wall. 379, 383, 20 L. ed. 414, 415; Lehigh Water Co. v. Easton,
It is the contention of the plaintiff in error that, although the proposed belt road to Henderson street was not built by the New Orleans & San Francisco Railroad Company, and although it be assumed that the failure of that company to build was legally excusable, and hence, that the obligation of the plaintiff in error to build in its stead did not arise, still there was an effective grant under ordinance No. 1997, and the plaintiff in error is entitled to [235 U.S. 164, 172] the use of the belt in the manner therein described upon the payment of $ 50,000.
We agree with the state court that this is not a proper interpretation of the ordinance.
1
Provision had already
[235 U.S. 164, 173]
been made for construction to the designated point by the New Orleans & San Francisco Railroad Company. Ordinance No. 1997 prefaced its grant by a recital of the right of construction which had been given to that com-
[235 U.S. 164, 174]
pany, and it was expressly stated that the grant to the plaintiff in error was made 'under the belt provisions of said ordinance No. 1615.' It had been provided in the last-mentioned ordinance that the public authorities might give to other railroad companies the right to use the road thus to be constructed, on their making contributions which should go into a special fund for the further extension of the belt line system. It is manifest that the intent was to give to the plaintiff in error the described right to use the tracks thus to be laid. But it was also contem-
[235 U.S. 164, 175]
plated that the New Orleans & San Francisco Railroad Company might fail to build, and that this failure might be 'without legal excuse.' In that event, it was agreed that the plaintiff in error should step into the place of the other company and assume the burden of construction 'under the terms and conditions' of ordinance No. 1615, such construction to take the place of the pecuniary consideration for the use of the tracks. It was further apparent that the fulfilment of the plan of ordinance No. 1615 might be legally impossible, and hence that the failure of the New Orleans & San Francisco Railroad Company might be legally excused. In this event, the plaintiff in error did not undertake to build, and no right of construction was given to it. We cannot imply such a right. While we are to give to public grants a fair and reasonable interpretation (United States v. Denver & R. G. R. Co.
It is urged that the provisions of ordinance No. 1997 ( 3, par. (c) that the belt tracks to be constructed by the plaintiff in error, as soon as they were completed to Henderson street, should be turned over to the 'immediate ownership of the city,' and should be under the 'control and management' of the public belt authority, obviated the objection raised by the dock board with respect to ordinance No. 1615. But an examination of other provisions of the ordinance shows that this 'control and management' was intended to be subject to certain limitations. Thus, it was provided in paragraph (f) that all controversies between the plaintiff in error and the public belt authority, or any other company or companies to which the use of the tracks might be granted, relating to the movement and handling of cars, trains, and traffic thereon, should be submitted to three arbitrators, one to be selected by the plaintiff in error, the second by the public belt authority, or by such other company or companies, as the case might be, and the third by the two thus chosen, and that the decision of any two of these arbitrators was to have the effect of an 'amicable composition.' We find no reason to doubt the correctness of the conclusion that the conditions, subject to which the dock board approved the dedication for belt road purposes of [235 U.S. 164, 177] the portion of the proposed route under its jurisdiction, would have been violated under the plan of ordinance No. 1997, as well as under that of ordinance No. 1615. And, further, it is clear that the proviso in paragraph (c) which related to tracks to be constructed by the plaintiff in error did not change the event in which alone the plaintiff in error was entitled to construct them, and this was in case the New Orleans & San Francisco Railroad Company should fail to build 'without legal excuse.'
Thus far we have assumed that the New Orleans & San Francisco Railroad Company was legally excused from building. But it is insisted by the plaintiff in error that this is not the case. That is, it is said that the grant of the right to construct was divisible, and that, so far as the city was competent to provide for such construction, the New Orleans & San Francisco Railroad Company was bound to build the belt road, and, therefore, that its failure to build to this extent was 'without legal excuse' within the meaning of the paragraph (c). But ordinance No. 1615 negatives this view. It explicitly provided for construction 'from the end of the rails on the upper side of Audubon park to Henderson street,' and that the city should furnish 'a clear legal right of way for the construction of said tracks.' We think that there is no basis whatever for the contention that the New Orleans & San Francisco Railroad Company was bound to construct a part of the belt road specified if, by reason of the successful opposition of the dock board, it was without power to build the remainder. And when the dock board prevailed in its suit, that company was entitled to abandon, as it did abandon, the undertaking. This was the event which was carefully excluded by ordinance No. 1997 in defining the contingency in which the plaintiff in error should build. The provision in paragraph (c) for the return of the securities which were to be deposited by the plaintiff in error as security for the performance of its obligation, in case [235 U.S. 164, 178] it should be prevented 'from building said belt tracks or any portion of the same on account of the city not furnishing the right of way,' or 'by causes beyond its control,' tends to support, rather than to oppose, the view that the undertaking was regarded as an entirety; for all the securities were to be returned although the prevention related to a portion of the route only. We are also referred to the provision ( 3, par . (d) that, in the event that the New Orleans & San Francisco Railroad Company should, from any cause, complete 'only a portion of the tracks' described, the plaintiff in error should have the right 'to operate its own locomotives, cars,' etc, 'over such portion of the tracks' as had already been built, and as might be built by the first-mentioned company, for a proportionate part of the agreed payment. This clause, in view of the existing situation of the parties, was held by the state court to have reference to a contingency in which, the opposition of the dock board not having been successful, the railroad company had proceeded with its undertaking, and, having built a part of the tracks, had failed to complete them; and this construction is in harmony with the other provisions of the ordinance. But, in fact, the event described in paragraph (d) did not happen, as no part of the road was built; and this clause in no way aids the contention that the New Orleans & San Francisco Railroad Company was under legal obligation to undertake a partial construction if it became legally impossible to carry out its undertaking as a whole.
We conclude that the contract upon which the plaintiff in error relies was subject, in any aspect, to a supensive condition (Civil Code [ La.] art. 2021), that the event in which the obligation was to arise did not happen, and hence, that the subsequent enactment was not open to the objection raised.
Judgment affirmed.
[ Footnote 1 ] 'This ordinance, so far as it is material with respect to this question, is as follows:
build said belt tracks from the upper side of Audubon park to Henderson street, on or before July 1, 1904, the Louisiana Railway & Navigation Company shall build the same from the upper side of Audubon park to Henderson street, under the terms and conditions of paragraph 10 of 2 of ordinance No. 1615, N. C. S.; and, in case said Louisiana Railway & Navigaition Company shall build said tracks, it is hereby granted the right and privilege to operate its trains, cars, and traffic over said tracks under all the provisions and terms of said paragraph 10 of 2 of ordinance No. 1615, N. C. S., said Louisiana Railway & Navigation Company assuming the obligation of the New Orleans & San Francisco Railroad Company under said paragraph of said ordinance, and being hereby granted all the rights and privileges of said New Orleans & San Francisco Railroad Company, its successors or assigns, under said paragraph 10 of 2 of said ordinance, except as hereinafter provided, such construction of said tracks from the upper side of Audubon park to Henderson street to be in lieu of the payment of $50,000, referred to in paragraph (a) of this section; provided, that said Louisiana Railway & Navigation Company shall complete the said tracks to Henderson street within one year from the time the city shall furnish the clear and undisputed right of way, it being always understood that said Louisiana Railway & Navigation Company assumes all the obligations of the New Orleans & San Francisco Railroad Company under paragraph 10 of 2 of said ordinance No. 1615, N. C. S.; and provided that, as soon as said belt tracks shall be completed to Henderson street, the same shall be turned over to the immediate ownership of the city of New Orleans, and to be under the control and management of the public belt authority; and provided, further, that said Louisiana Railway & Navigation Company shall, on July 1, 1904, deposit with the fiscal agent of the city of New Orleans, bonds or other securities satisfactory to said fiscal agent, of the value of $50,000, the same to be held in escrow as security for compliance by said company with the foregoing obligations, and to be returned to said company when said company shall have built and completed said belt tracks from the upper side of Audubon park to Henderson street; and provided, further, that in case said company shall be prevented from building said belt tracks, or any portion of the same, on account of the city
not furnishing the right of way under the terms of ordinance No. 1615, N. C. S., or by causes beyond its control, then the securities deposited shall be returned to it by said fiscal agent. . . .
...
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Citation: 235 U.S. 164
No. 49
Decided: November 30, 1914
Court: United States Supreme Court
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)