Erald TROJA, Appellant, v. YORK ELECTRICAL OF WESTCHESTER, Respondent.
ORDERED that the judgment is affirmed, without costs.
Plaintiff commenced this small claims action seeking $5,000 for breach of contract. Plaintiff alleged that defendant failed to complete electrical services it was contracted to perform. At a nonjury trial, plaintiff testified that defendant failed to complete the project and he had to hire others to do so. Plaintiff did not present any expert testimony regarding the condition of defendant's work. Defendant's owner, Peter York, testified that 75 percent of the electrical work was completed, that plaintiff paid defendant $7,000 of the $9,877 of the contracted price (approximately 71 percent), that defendant offered to complete the project and that plaintiff never asked defendant to return. The City Court found in favor of defendant and dismissed the action.
In a small claims action, our review is limited to a determination of whether “substantial justice has ․ been done between the parties according to the rules and principles of substantive law” (UCCA 1807; see UCCA 1804; Ross v Friedman, 269 AD2d 584 [2000]; Williams v Roper, 269 AD2d 125 [2000]). The determination of a trier of fact as to issues of credibility is given substantial deference, as a trial court's opportunity to observe and evaluate the testimony and demeanor of the witnesses affords it a better perspective from which to assess their credibility (see Vizzari v State of New York, 184 AD2d 564 [1992]; Kincade v Kincade, 178 AD2d 510 [1991]). This deference applies with greater force to judgments rendered in the Small Claims Part of the court (see Williams v Roper, 269 AD2d at 126).
Although plaintiff claimed that defendant did not fulfill its contractual obligations under the contract, the credible evidence established that defendant's failure to perform was due to plaintiff's actions when he failed to advise defendant to return after Peter York said that he was willing and able to complete the job. The law looks with disfavor when one party, by its own unilateral act, prevents or hinders the other party from fulfilling a contract (see Arc Elec. Constr. Co. v Fuller Co., 24 NY2d 99 [1969]). Insofar as the evidence established that defendant completed 75 percent of the contracted work, it was entitled to be compensated for that work, which it was. Consequently, the judgment dismissing the action provided the parties with substantial justice (see UCCA 1804,1807).
Accordingly, the judgment is affirmed.
DRISCOLL, J.P., VOUTSINAS and WARHIT, JJ., concur.
Thank you for your feedback!
As the largest network of trusted legal brands, we help firms build authority across the platforms consumers and AI systems rely on most. Our network helps attorneys strengthen visibility, credibility, and preference where legal decisions begin.
Docket No: 2021-189 W C
Decided: April 28, 2022
Court: Supreme Court, Appellate Term, New York,
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)