Learn About the Law
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
IN RE: PROPERTIES OF NEW YORK, INC., Appellant, v. PLANNING BOARD OF the TOWN OF STUYVESANT et al., Respondents.
Appeal from a judgment of the Supreme Court (Connor, J.), entered August 16, 2005 in Columbia County, which, inter alia, dismissed petitioner's application, in a proceeding pursuant to CPLR article 78, to direct the Town of Stuyvesant to reimburse it for certain consultant fees.
Petitioner applied to respondents for approval of a real property subdivision and was informed that it must pay all fees incurred by respondents for the services of engineers and attorneys to review and assess the application. Petitioner paid the fees initially, but soon began to withhold payment and question the amounts charged. After being advised that the application would not proceed without payment in full, petitioner made the remaining payments under protest. Payments were completed on April 20, 2004, and the final plat was endorsed eight days later. Petitioner then wrote respondents on June 24, 2004 demanding an audit and return of most of the amounts previously paid on the ground that respondents had exceeded their authority by requiring such payments. When respondents declined to do so, petitioner commenced this CPLR article 78 proceeding on August 27, 2004 to challenge imposition of the fees. Supreme Court dismissed the petition as time barred, finding that the four-month statute of limitations accrued on April 20, 2004, the date of the last payment, and not-as argued by petitioner-eight days later on the date of the endorsement of the final plat. Petitioner appeals.
While we agree that the proceeding is time barred, we cannot agree with Supreme Court that petitioner's last payment commenced the limitations period. The question of when the four months began to run is answered by identifying the administrative action or determination to be reviewed and deciding when it became final and binding (see CPLR 217[1] ). It is well settled that an administrative action becomes final and binding when it has an impact upon a party and the party is clearly aggrieved by it (see Matter of Edmead v. McGuire, 67 N.Y.2d 714, 716, 499 N.Y.S.2d 934, 490 N.E.2d 853 [1986]; Matter of Hunt Bros. Contrs. v. Glennon, 214 A.D.2d 817, 819, 625 N.Y.S.2d 319 [1995]; New York City Off Track Betting Corp. v. State of New York Racing & Wagering Bd., 196 A.D.2d 15, 18, 608 N.Y.S.2d 328 [1994], lv. denied 84 N.Y.2d 804, 617 N.Y.S.2d 138, 641 N.E.2d 159 [1994] ). The Court of Appeals has articulated a two-part test for identifying when an administrative action is final and binding upon a petitioner. “First, the agency must have reached a definitive position on the issue that inflicts actual, concrete injury and second, the injury inflicted may not be prevented or significantly ameliorated either by further administrative action or by steps available to the complaining party” (Matter of Best Payphones v. Department of Info. Tech. & Telecom. of City of N.Y., 5 N.Y.3d 30, 34, 799 N.Y.S.2d 182, 832 N.E.2d 38 [2005] [citations omitted]; see Matter of City of New York [Grand Lafayette Props.], 6 N.Y.3d 540, 547-548, 814 N.Y.S.2d 592, 847 N.E.2d 1166 [2006] ).
In our view, the action to be reviewed here was respondents' unambiguous notification to petitioner that each payment was required and the application would not proceed without it. Respondents' letters and e-mails, all communicated well before petitioner's last payment, left no doubt that respondents had reached a definitive position regarding payment that inflicted actual, concrete injury on petitioner and offered no alternative or opportunity for amelioration. Accordingly, the cause of action accrued well before the date fixed by Supreme Court.
Petitioner's contention that respondents charged these fees to petitioner as part of the subdivision approval process, which was not complete until the final plat was endorsed, is unavailing because endorsement of the plat in no way altered petitioner's obligation to pay. Unlike the petitioners in Matter of Eadie v. Town Bd. of Town of N. Greenbush, 7 N.Y.3d 306, 821 N.Y.S.2d 142, 854 N.E.2d 464 [2006], who challenged a State Environmental Quality Review Act determination favoring rezoning only after enactment of the rezoning, petitioner here suffered “concrete injury” when the fees were imposed rather than when final approval was granted (id. at 316, 821 N.Y.S.2d 142, 854 N.E.2d 464). Finally, petitioner's subsequent demand for an audit and return of certain fees paid was plainly a request for reconsideration and did not operate to extend the statute of limitations (see Matter of Lubin v. Board of Educ. of City of N.Y., 60 N.Y.2d 974, 976, 471 N.Y.S.2d 256, 459 N.E.2d 481 [1983], cert. denied 469 U.S. 823, 105 S.Ct. 99, 83 L.Ed.2d 44 [1984]; Matter of Reynoso v. McGinnis, 32 A.D.3d 1147, 1148, 821 N.Y.S.2d 476 [2006] ).
ORDERED that the judgment is affirmed, without costs.
ROSE, J.
CARDONA, P.J., MUGGLIN and LAHTINEN, JJ., concur.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: December 07, 2006
Court: Supreme Court, Appellate Division, Third Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)