Learn About the Law
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
UNIVERSAL CONSTRUCTION RESOURCES, INC., Plaintiff–Respondent, v. NEW YORK CITY HOUSING AUTHORITY, Defendant–Appellant.
Three of the purported notices of claim were not facially compliant with Section 23 of the contract. Neither the July 19, 2015 letter nor the April 11, 2016 letter was designated a notice of claim, a defect this Court has found to warrant the dismissal of a contractor's action against the Housing Authority (see Matter of Intercontinental Constr. Contr., Inc. v. New York City Hous. Auth., 173 A.D.3d 453, 454, 102 N.Y.S.3d 576 [1st Dept. 2019]). The failure to state the “nature and amount of the extra costs or damages” sought in the July 19, 2015, February 12, 2016, and April 11, 2016 letters also required dismissal (see Hi–Tech Constr. & Mgt. Servs. Inc. v. Housing Auth. of the City of N.Y., 125 A.D.3d 542, 542, 4 N.Y.S.3d 189 [1st Dept. 2015], lv denied 26 N.Y.3d 908, 18 N.Y.S.3d 599, 40 N.E.3d 577 [2015]), since Section 23 makes notice an express condition precedent to suit or recovery (see Schindler El. Corp. v. Tully Constr. Co., Inc., 139 A.D.3d 930, 931, 30 N.Y.S.3d 707 [1st Dept. 2016]).
The March 1, 2017 notice of claim was untimely, as the project was substantially completed on March 23, 2016, and the certificate of final acceptance was dated May 9, 2016. Therefore, plaintiff's claims or damages could have been ascertained well before the March 1, 2017 notice of claim was sent (see C.S.A. Contr. Corp. v. New York City School Constr. Auth., 5 N.Y.3d 189, 192, 800 N.Y.S.2d 123, 833 N.E.2d 266 [2005]; D & L Assoc., Inc. v. New York City School Constr. Auth., 69 A.D.3d 435, 435, 894 N.Y.S.2d 14 [1st Dept. 2010]).
Additional discovery is not necessary, as plaintiff was required to maintain weekly payroll records, rented or acquired materials and equipment before it began work, and based its subcontractor costs on pre-negotiated rates. Based on this data, plaintiff could have, by March 23, 2016 when the work was substantially complete, or upon final acceptance of the work on May 9, 2016, calculated costs and damages (see D & L Assoc., Inc., 69 A.D.3d at 435, 894 N.Y.S.2d 14). Plaintiff has made no showing how defendant's alleged misconduct impaired its ability to fulfill Section 23 of the contract (A.H.A. Gen. Constr. v. New York City Hous. Auth., 92 N.Y.2d 20, 33–34, 677 N.Y.S.2d 9, 699 N.E.2d 368 [1998]).
Thank you for your feedback!
As the largest network of trusted legal brands, we help firms build authority across the platforms consumers and AI systems rely on most. Our network helps attorneys strengthen visibility, credibility, and preference where legal decisions begin.
Docket No: 10247
Decided: October 31, 2019
Court: Supreme Court, Appellate Division, First Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)