BLUE HERON CONSTRUCTION COMPANY, LLC, Plaintiff-Respondent, v. VILLAGE OF NUNDA, Defendant-Appellant.
Plaintiff commenced this action seeking damages for the alleged breach by defendant of its construction contract with plaintiff and for unjust enrichment. According to plaintiff, it fully and adequately performed the work of the contract, and defendant thus owed plaintiff the sum of $69,205. 23, representing $54,500 in liquidated damages based on plaintiff's failure to comply with the contract insofar as it required substantial completion of the work by the contractual deadline, and a retainage amount of $14,705.23 based on the termination of the contract prior to final completion of the work. Defendant contends on appeal that Supreme Court should have granted its motion for summary judgment dismissing the complaint in its entirety, rather than only granting that part of the motion dismissing the claim for lost profits. We agree.
We note at the outset our agreement with defendant that the court erred in denying its motion in part, inasmuch as plaintiff failed to seek the requisite extension of the deadline for substantial completion. “It is well settled that, where parties have set forth their agreement in an unambiguous and complete document, that agreement should be enforced according to its terms” (Westfield Family Physicians, P.C. v. HealthNow N.Y., Inc., 59 A.D.3d 1014, 1015, 873 N.Y.S.2d 793; see W.W.W. Assoc. v. Giancontieri, 77 N.Y.2d 157, 162, 565 N.Y.S.2d 440, 566 N.E.2d 639). The dates by which substantial completion and final completion of the project were required were set forth in section 12.02(A) of the contract, which refers to “Contract Times.” Any adjustment with respect to those dates could be made only by a written “Change Order” or a “Claim” for an adjustment, pursuant to section 12.02(B) of the contract. Article 12 of the contract sets forth a metric by which any “Claim” for an adjustment of the “Contract Times” was to be covered, but it did not relieve plaintiff of its obligation to seek such an extension in the event that defendant was responsible for the delay. It is undisputed that plaintiff did not request an extension of the “Contract Times,” nor did it achieve substantial completion or final completion of the work of the contract by the contractual deadline.
We further agree with defendant that the liquidated damages provision of the contract was enforceable. “As a general rule, where the delays are caused by the mutual fault of the parties, a liquidated damage clause is abrogated and each party must resort to an action to recover its actual damages” (J.R. Stevenson Corp. v. County of Westchester, 113 A.D.2d 918, 921, 493 N.Y.S.2d 819; see Mosler Safe Co. v. Maiden Lane Safe Deposit Co., 199 N.Y. 479, 486, 93 N.E. 81). Where, however, the contract includes a provision allowing it to be extended for causes beyond the contractor's control, the obligation to pay liquidated damages is preserved (see X.L.O. Concrete Corp. v. Brady & Co., 104 A.D.2d 181, 186, 482 N.Y.S.2d 476, affd. 66 N.Y.2d 970, 498 N.Y.S.2d 799, 489 N.E.2d 768; Mosler Safe Co., 199 N.Y. at 486-487, 93 N.E. 81; Mars Assoc. v. Facilities Dev. Corp., 124 A.D.2d 291, 292-293, 508 N.Y.S.2d 87; J.R. Stevenson Corp., 113 A.D.2d at 921-922, 493 N.Y.S.2d 819). We reject the contentions of plaintiff that the assessment of liquidated damages is inequitable based on the dispute with respect to the cause of its delay in substantially completing the work and that defendant waived the provision of the contract requiring timely completion of the work (see generally Gilbert Frank Corp. v. Federal Ins. Co., 70 N.Y.2d 966, 968, 525 N.Y.S.2d 793, 520 N.E.2d 512; Deep v. Clinton Cent. School Dist., 48 A.D.3d 1125, 1126, 850 N.Y.S.2d 792). Plaintiff's contention that defendant may not impose liquidated damages because such damages were substantially higher than any actual damage sustained by defendant is raised for the first time on appeal and thus is not properly before us (see Ciesinski v. Town of Aurora, 202 A.D.2d 984, 985, 609 N.Y.S.2d 745).
It is hereby ORDERED that the order insofar as appealed from is unanimously reversed on the law without costs, the motion is granted in its entirety and the complaint is dismissed.
MEMORANDUM:
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: June 12, 2009
Court: Supreme Court, Appellate Division, Fourth Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)