Learn About the Law
Get help with your legal needs
FindLawâs Learn About the Law features thousands of informational articles to help you understand your options. And if youâre ready to hire an attorney, find one in your area who can help.
CENTRIC GULF COAST, INC. v. BULLSEYE MASONRY, LLC
Defendant/Appellant, Bullseye Masonry, LLC, appeals the trial court's judgment that sustained a peremptory exception of prescription in favor of Third-Party Defendant/Appellee, Oldcastle APG, Inc., and dismissed its third-party demand with prejudice, which had been filed in the 24th Judicial District Court, Division âJâ. For the following reasons, we affirm the trial court's judgment.
FACTS AND PROCEDURAL HISTORY
The facts pertinent to this appeal are as follows.
On August 26, 2022, Centric Gulf Coast, Inc. (hereinafter referred to as âCentricâ) filed a petition for damages and breach of contract against Bullseye Masonry, LLC (hereinafter referred to as âBullseyeâ).1 In its petition, Centric alleged that it entered into Master Subcontract Agreement No. 2016-003 with Bullseye on August 2, 2016, whereby Bullseye agreed to perform work specified in a separate work authorization contract. On December 16, 2019, Centric and Bullseye executed Work Authorization No. 1186-006 for all of the labor and materials to complete the masonry scope for the Marrero Waste Water Treatment Plant Safe Room and Administration (hereinafter referred to as âthe Projectâ) for $407,000. Centric alleged that, as early as February 18, 2021, the masonry was found to have been leaking. In April 2021, samples of the masonry were sent for testing at ACM Chemistries in Grapevine, Texas, and the product used for the masonry failed water testing.
Centric then alleged that Bullseye and its product supplier, Oldcastle APG, Inc. (hereinafter referred to as âOldcastleâ) acknowledged the masonry products for the Project were defective. It stated that, on June 3, 2021, a notice of default was issued to Bullseye, informing Bullseye that it was in default of its obligations per the master subcontract agreement and the work authorization. Centric sought damages from Bullseye for contractual default and breach of contract.
On February 16, 2023, Bullseye filed a third-party demand against Oldcastle. In its complaint, Bullseye alleged that it and Centric entered into a master subcontract agreement for the Project, with the work to be completed to be specified in a separate work authorization. It stated the Project required an integral water repellant to be included in the concrete masonry units (hereinafter referred to as âCMUsâ), and it contracted with Oldcastle to provide the CMUs for the Project. Bullseye asserted it informed Oldcastle that the CMUs required the integral water repellant, and Oldcastle represented that the CMUs it provided included the water repellant specified in the agreement. It alleged that the CMUs were found to have been leaking as early as February 2021; and when the CMUs were sent for testing in April 2021, the products failed the water testing. Bullseye stated that Oldcastle acknowledged the CMUs Oldcastle supplied were defective and did not contain the water repellant. Bullseye sought damages from Oldcastle for breach of contract for failing to provide the specified product and negligence for any damages it would incur as a result of the defective work or product.
In opposition to Bullseye's third-party demand, Oldcastle filed a peremptory exception of prescription. In its exception, Oldcastle contended that the distribution of the CMUs to Bullseye constituted a contract of sale pursuant to La. C.C. art. 2439, rather than a contract for construction or work. Oldcastle averred that Bullseye's cause of action in tort or contract/redhibition was prescribed on its face because it was filed over a year after Bullseye had knowledge of any claims it may have had against Oldcastle.
Conversely, in its opposition brief to Oldcastle's exception of prescription, Bullseye argued that it and Oldcastle were joint tortfeasors, and prescription was interrupted when Centric filed suit against Bullseye in August 2022. Bullseye further argued that the prescriptive period against Oldcastle did not begin to run until July 1, 2022 because Oldcastle had previously made continuous affirmative representations that it would remedy the Project's defect. In the alternative, Bullseye contended it did not sustain an injury until July 1, 2022âwhen Oldcastle refused to remedy the issueâand it filed its demand well-within the date of injury. To support its position, Bullseye attached the Project's bid documents; an affidavit of its member and manager, Melisa Hedrick; Work Authorization No. 1186-006; the ACM Chemistries Water Repellency Testing Results; and various correspondence between Centric, Bullseye, and Oldcastle to its opposition brief.
The exception of prescription was heard before the trial court on November 7, 2023. No evidence was offered by either party at the hearing. At the conclusion of the hearing, the trial court orally sustained Oldcastle's exception of prescription. A written judgment was rendered on April 3, 2024, sustaining Oldcastle's exception and dismissing Bullseye's third-party demand with prejudice. The instant appeal followed.
ASSIGNMENTS OF ERROR
Bullseye alleges the trial court manifestly erred in applying the one-year prescriptive period to its third-party claims because: 1) Oldcastle and Bullseye are joint tortfeasors, and prescription was interrupted; and 2) Oldcastle made continuous affirmative representations that it would remedy the defect.
LAW AND ANALYSIS
General Exception of Prescription Law
An exception of prescription is a type of peremptory exception. The function of the peremptory exception is to have the plaintiff's action declared legally nonexistent or barred by the effect of law, and hence this exception tends to dismiss or defeat the action. Ruffins v. HAZA Foods of Louisiana, LLC, 21-619 (La. App. 5 Cir. 5/25/22), 341 So.3d 1259, 1262, citing Farber v. Bobear, 10-985 (La. App. 4 Cir. 1/19/11), 56 So.3d 1061, 1069. Prescriptive statutes are strictly construed against prescription and in favor of the claim. Henry v. Southwest Airlines, 23-522 (La. App. 5 Cir. 7/31/24), 392 So.3d 1176, 1179, writ denied, 24-1081 (La. 11/20/24), 396 So.3d 68. Of the possible constructions of a prescriptive statute, the one that maintains enforcement of the claim, instead of the one that bars enforcement, should be adopted. Id.
The burden of proof in an exception of prescription lies with the party asserting it; however, where the petition shows on its face that it has prescribed, the burden shifts to the plaintiff to prove the prescriptive period has been interrupted or suspended. McClellan v. Premier Nissan, L.L.C., 14-726 (La. App. 5 Cir. 2/11/15), 167 So.3d 934, 935. If evidence is introduced at the hearing on the peremptory exception of prescription, the trial court's findings of fact are reviewed under the manifest error/clearly wrong standard of review. Id. If the findings are reasonable in light of the record reviewed in its entirety, an appellate court may not reverse, even though convinced that had it been sitting as the trier of fact, it would have weighed the evidence differently. Id. In the absence of evidence, the exception of prescription must be decided on the well-pleaded allegations of material facts set forth in the petition, which are accepted as true. Ruffins, supra.
At the hearing on Oldcastle's exception of prescription, neither party introduced any evidence for the trial court to consider. Because no evidence was introduced, we must decide this matter on the well-pleaded allegations of material facts set forth in Bullseye's third-party demand.
Joint Tortfeasors
Bullseye alleges the trial court erroneously sustained Oldcastle's exception of prescription by applying the one-year prescriptive period, pursuant to La. C.C. art. 3492. It argues that the trial court failed to acknowledge the joint tortfeasor relationship between Oldcastle and Bullseye, as both companies could be deemed as contributors to Centric's damages. As such, Bullseye contends that its claims against Oldcastle were interrupted by the filing of Centric's petition for damages against Bullseye in September 2022. It avers that, if its claims against Oldcastle are prescribed, Centric's claims against Bullseye must also be prescribed.
Oldcastle maintains the trial court properly sustained its exception of prescription. It asserts that Centric sued Bullseye for breach of contract and default of the contract to build, neither of the actions sued upon being a tort action; thus, Oldcastle and Bullseye cannot be joint tortfeasors because their obligations arose out of conventional obligations. Oldcastle avers it was solely a supplier of movables to Bullseye, and an action against a seller for an alleged defect or vice in the thing purchased is one of redhibition. Because Bullseye discovered the alleged defect or vice in the CMUs more than a year prior to filing the third-party demand, Oldcastle submits that Bullseye's demand is prescribed on its face.
In order to ascertain the viability of Bullseye's third-party demand, we must determine the prescriptive period applicable to this matter. The nature of an obligation in Louisiana, for the purpose of determining the applicable prescriptive period, is either contractual, quasi-contractual, delictual, quasi-delictual or legal. We Sell Used Cars, Inc. v. United Nat. Ins. Co., 30,671 (La. App. 2 Cir. 6/24/98), 715 So.2d 656, 658. The prescriptive period applicable to an action is determined by the character of the action as disclosed in the pleadings. Succession of Theobald, 20-68 (La. App. 5 Cir. 12/23/20), 309 So.3d 878, 883, citing Born v. City of Slidell, 15-136 (La. 10/14/15), 180 So.3d 1227, 1232.
Bullseye's demand alleged that it contracted with Oldcastle to provide the CMUs for the Project, and the Project required that the CMUs contain an integral water repellant. It further alleged Oldcastle represented that the CMUs contained the water repellant specified, and the CMUs supplied by Oldcastle were installed by Bullseye at the Project's site. The CMUs, however, leaked in February 2021 and, subsequently, failed the water testing in April 2021. Bullseye then alleged that Oldcastle was liable for breach of contract for failing to provide the specified product for the Project and, in the event Centric proved that any work performed on the Project by Bullseye was defective, for negligently providing the product that caused the damages.
It is well-settled that the same acts or omissions may constitute breaches of both general duties and contractual duties and may give rise to both actions in tort and actions in contract. Lahare v. Valentine Mech. Servs. LLC, 17-289 (La. App. 5 Cir. 6/29/17), 223 So.3d 773, 776, citing In re St. Louis Encephalitis Outbreak, 41,250 (La. App. 2 Cir. 9/1/06), 939 So.2d 563, 566-67. A plaintiff may assert both actions and is not required to plead the theory of his case. Id. The classical distinction between âdamages ex contractuâ and âdamages ex delictoâ is that the former flow from the breach of a special obligation contractually assumed by the obligor, whereas the latter flow from the violation of a general duty owed to all persons. Id., citing Dubin v. Dubin, 25,996 (La. App. 2 Cir. 8/17/94), 641 So.2d 1036, 1040.
Generally, where a person neglects to do what he is obligated to do under a contract, he has committed a passive breach of the contract. Lahare, supra. If he negligently performs a contractual obligation, he has committed active negligence and, thus, an active breach of contract. Id. at 777. A passive breach of contract warrants only an action for breach of contract; an active breach of contract, on the other hand, may also support an action in tort under La. C.C. art. 2315. Id.
Upon review of Bullseye's third-party demand, we find that it fails to allege Bullseye's injuries were caused by Oldcastle's negligent performance of the contract. Instead, the demand alleges that the injuries were caused by Oldcastle's non-performance of the contract, namely Oldcastle's failure to provide CMUs that contained an integral water repellant. Consequently, we conclude that Bullseye alleged a passive breach of contract, which does not support a claim in tort. While the filing of a petition against one joint tortfeasor does interrupt prescription against the other joint tortfeasors,2 we find that Bullseye's demand is not a tort action. Instead, we hold that the allegations in Bullseye's demand arise from contractual obligations.3
Pursuant to La. C.C. art. 3499, â[u]nless otherwise provided by legislation, a personal action is subject to a liberative prescription of ten years.â The prescriptive period applicable to an action alleging a breach of contract is ten years. McClellan v. Premier Nissan, L.L.C., 14-726 (La. App. 5 Cir. 2/11/15), 167 So.3d 934, 935. However, an action for redhibition prescribes one year from the date the defect is discovered by the buyer. La. C.C. art. 2534; Gaspard v. Camping World RV Sales, L.L.C., 20-125 (La. App. 3 Cir. 9/30/20), 304 So.3d 1050, 1054. A âbreach of contract claim based upon the sale of an allegedly defective product would be founded in redhibition and subject to the one year prescriptive period.â Bottinelli Real Estate, L.L.C. v. Johns Manville, Inc., 19-619 (La. App. 4 Cir. 12/27/19), 288 So.3d 179, 185, quoting Stewart Interior Contractors, L.L.C. v. MetalPro Industries, L.L.C., 13-922 (La. App. 4 Cir. 1/8/14), 130 So.3d 485, 489.
According to Bullseye's third-party demand, the CMUs supplied by Oldcastle were found to have been leaking as early as February 2021. When the CMUs were sent for testing in April 2021, the products failed the water testing. Bullseye knew in 2021 that the CMUs did not contain the integral water repellant, which is the basis of its claims for damages. However, Bullseye did not file its demand against Oldcastle until February 16, 2023, well over a year after Bullseye had notice of the allegedly defective CMUs. Therefore, accepting Bullseye's well-pleaded allegations as true, we find that Bullseye's third-party demand is prescribed on its face. Because Bullseye failed to introduce any evidence at the hearing on the exception of prescription, we also find that Bullseye failed to prove the prescriptive period had been interrupted or suspended.4
Affirmative Representations
Alternatively, Bullseye alleges the trial court erroneously determined the date on which it sustained damages to trigger the one-year prescriptive period. It argues that, since the defect was initially detected, Oldcastle made continuous affirmative representations that it would remedy said defect on the Project; however, it was not until July 1, 2022 that Oldcastle refused to remedy the issue by paying liquidated damages. Bullseye contends that its third-party demand against Oldcastle in February 2023 was well-within one year of the date of its injury, which was July 1, 2022âthe date Oldcastle reneged on its representations and left Bullseye with the costs to cure the defect.
Oldcastle argues that Bullseye's third-party demand was prescribed on its face. As such, Bullseye was burdened with proving prescription was suspended or interrupted, and Bullseye failed to introduce any evidence at the hearing on the exception of prescription. Thus, it avers there was insufficient evidence presented by Bullseye to prove prescription was interrupted in this matter. Oldcastle also argues that settlement negotiations are inadmissible and objects to the reference to any such negotiations.
As previously mentioned, neither party introduced any evidence at the hearing on the exception of prescription. Bullseye asserts that Oldcastle made continuous affirmative representations that it would remedy said defect on the Project. However, there is no evidence before us to consider in support of that argument. Although Bullseye attached exhibits to its opposition brief to the exception of prescription, â[e]vidence not properly and officially offered and introduced cannot be considered, even if it is physically placed in the record. Documents attached to memoranda do not constitute evidence and cannot be considered as such on appeal.â Ford Motor Credit Co., LLC v. Davis, 20-271 (La. App. 5 Cir. 10/13/21), 329 So.3d 1047, 1056, writ not considered, 21-1739 (La. 1/26/22), 331 So.3d 926, quoting Denoux v. Vessel Management Servs., 07-2143 (La. 5/21/08), 983 So.2d 84, 88. Therefore, we find that Bullseye failed to prove that its third-party demand against Oldcastle is not prescribed.
DECREE
For the foregoing reasons, we affirm the trial court's judgment that sustained Oldcastle APG, Inc.âs peremptory exception of prescription and dismissed Bullseye Masonry, LLC's third-party demand. Bullseye Masonry, LLC is assessed the costs of this appeal.
AFFIRMED
FOOTNOTES
1.  âCentric Gulf Coast, Inc. v. Bullseye Masonry, LLC was filed in the 24th Judicial District Court under case number 832-152.
2.  âSee, La. C.C. art. 2324(C) that states, â[i]nterruption of prescription against one joint tortfeasor is effective against all joint tortfeasors.â
3.  âAlthough Bullseye argues the trial court incorrectly applied the one-year prescriptive period for delictual actions pursuant La. C.C. art. 3492, the record does not reflect that the trial court considered that particular codal article. The judgment does not mention La. C.C. art. 3492, or any other codal article, as the basis for the trial court's ruling. Furthermore, a review of the transcript of the hearing does not reveal the trial court's consideration of La. C.C. art. 3492. There is nothing in the record to support Bullseye's contention that the trial court based its ruling upon La. C.C. art. 3492.
4.  âWe express no opinion as to matters that are not currently before this Court, in particular, whether Centric's claims against Bullseye are prescribed.
JOHNSON, J.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Docket No: NO. 24-CA-319
Decided: April 02, 2025
Court: Court of Appeal of Louisiana, Fifth Circuit.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLawâs newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLawâs Learn About the Law features thousands of informational articles to help you understand your options. And if youâre ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)