Jacobs Eng'g Group, Inc. v. US, 05-5052
Summary judgment requiring the government to reimburse plaintiff-contractor for 80 percent of its costs of performance in a dispute over a development and construction contract is reversed where termination under the contract's termination-for-the-convenience-of-the-government clause required payment of all the costs.