ENGLAND v. THE SHERMAN R. SMOOT CORP., 03-1461

The award of compensation to defendant for a delay in the completion of a construction contract is reversed where Armed Services Board of Contract Appeals used the improper rebuttable presumption that plaintiff had caused the delay.