Washington Gas Light Co. v. FERC, 09-1100
In a petition for review of the Federal Energy Regulatory Commission's (FERC) approval of a construction project that would allow a natural gas importer to import greater quantities of liquefied natural gas and distribute it in gaseous form, the petition is denied where, by imposing a post-expansion limit on the project that matched the pre-expansion limit, FERC satisfactorily ensured that the expansion would not result in an increased risk of unsafe natural gas leakage.