FPL Energy Marcus Hook, L.P. v. Fed. Energy Regulatory Comm'n, 04-1341
Petitions for review of agency defendant's order denying a request for a reallocation and redetermination of plaintiff's cost responsibility for construction upgrades required to interconnect with an electricity transmission grid is granted where defendant did not adequately explain its decision on the upgrades' system benefit.