United States Ninth Circuit
Sierra Club v. Bureau of Land Management, 13-1583
In a dispute involving the Wind Project, the decision of the United States Bureau of Land Management (BLM) to grant a right-of-way over federal land for a wind energy project developed on private land by intervenor, is affirmed where: 1) the Wind Project did not trigger BLM's duty to initiate consultation with the US Fish and Wildlife Service under the Endangered Species Act; and 2) the Wind Project did not trigger BLM's duty to prepare an Environmental Impact Statement under National Environmental Policy Act because the Wind Project was not a federal action or connected to the Road Project.
Appellate Information
- Decided 05/27/2015
- Published 05/27/2015
Judges
- Rawlinson
Court
- United States Ninth Circuit