STATE OF CALIFORNIA v. NEVILLE CHEM. CO., 02-56506

The limitations period for bringing an initial suit for recovery of remedial action costs under CERCLA cannot accrue until after the final adoption of the remedial action plan required by the statute.

Appellate Information

  • Argued 11/03/2003
  • Decided 02/10/2004
  • Published 02/10/2004

Judges

  • BERZON, Circuit Judge:, Before PREGERSON, FERNANDEZ, and BERZON, Circuit Judges.

Court

  • United States Ninth Circuit

Counsel

  • For Appellees:
  • Terry Anastassiou,Ropers, Majeski, Kohn & Bentley, San Francisco, CA, for the defendant-appellant., Bill Lockyer, Atty. Gen. of State of California, Richard Frank, Chief Asst. Atty. Gen., Theodora Berger, Senior Asst. Atty. Gen., Donald Robinson, Supervising Deputy Atty. Gen., Laurie A. Oearlmanm, Deputy Atty. Gen., Harrison M. Pollak, Deputy Attorney General, Oakland, CA, for the plaintiff-appellee.