ONRC ACTION v. COLUMBIA PLYWOOD, INC., 98-36233, 99-35019

Where plaintiff's request for renewal of pollutant discharge permit was tardy but nonetheless accepted by state environmental agency, timing requirement for renewal was waived by agency; district court lacked jursdiction to hear claims not properly raised in 60-day citizen suit notice under the Clean Water Act.

Appellate Information

  • Argued 02/17/2000
  • Decided 04/16/2002
  • Published 04/16/2002

Judges

  • DAVID R. THOMPSON, Circuit Judge., Before: REINHARDT, THOMPSON, and T.G. NELSON, Circuit Judges.

Court

  • United States Ninth Circuit

Counsel

  • For Appellees:
  • William Carpenter, Jr., Eugene, OR, for the appellants-cross-appellees., Karen O'Casey, Portland, OR, for the appellee-cross-appellant.