CENTRIC JONES CO. v. CITY OF KEARNEY, 02-1964/5
A contractor's claims were time barred where it failed to comply with Nebraska Revised Statute section 16-276 concerning claims against a city of the "first class," and by its terms the contract at issue required compliance with the statute.