THE MID-CONTINENT AREA POWER POOL v. FERC, 01-3876
FERC's orders were broad enough to encompass a requirement that petitioner file transmission service agreements for short-term firm and non-firm service to members of its power pool, but court remands for determination whether an ordered refund should be waived because its prior orders did not clearly require the filing of the agreements.