SHAW CONSTR. v. ICF KAISER ENG'RS, 02-30183
A subcontractor has the right to regard a subcontract dissolved, and the parties restored to their pre-contract positions, when it becomes evident that the general contractor will not perform and has materially breached the subcontract.
Appellate Information
- Decided 12/30/2004
- Published 12/31/2004
Judges
- DENNIS, Circuit Judge:, Before HIGGINBOTHAM, GARZA and DENNIS, Circuit Judges.
Court
- United States Fifth Circuit
Counsel
- For Appellant:
- Eric A. Kracht (argued), Kracht & Associates, Baton Rouge, LA, for Shaw Constructors., Eugene R. Preaus (argued), Edward C. Gleason, Preaus, Roddy & Associates, New Orleans, LA, for PCS Nitrogen Fertilizer L.P.