HERR v. PEQUEA TOWNSHIP, 00-2473
Where a township participates in proceedings before other governmental agencies authorized to resolve land use issues, the township and its supervisors are not subject to liability for delay from those proceedings solely because their participation was motivated by a desire to delay or prevent the project.