Town of Norwood, MA v. Fed. Energy Regulatory Comm'n, 06-1658

FERC order sustaining a contract termination charge contained in a tariff previously filed by an intervening party is affirmed insofar as it determines the amount of principal due and requires interest payments based on at least the prime rate, but remanded to determine whether more interest is properly due.

Appellate Information

  • Decided 02/02/2007
  • Published 02/02/2007

Judges

  • BOUDIN, Chief Judge., Before BOUDIN, Chief Judge, CYR, Senior Circuit Judge, and LIPEZ, Circuit Judge.

Court

  • United States First Circuit

Counsel

  • For Appellant:
  • Robert A. Jablon with whom Elaine C. Lippmann, Spiegel & McDiarmid, Charles F. Wheatley, Jr., Wheatley & Ranquist, P.A., J. Owen Todd, Juliet A. Davison, Heidi A. Nadel and Todd & Weld LLP were on consolidated brief for petitioner., Kenneth G. Jaffe with whom Alston & Bird LLP, and John F. Sherman III, Deputy General Counsel, National Grid USA Services Company, Inc., were on brief for intervenor.

  • For Appellees:
  • Michael E. Kaufmann with whom John S. Moot, General Counsel, and Robert H. Solomon, Solicitor, Federal Energy Regulatory Commission, were on consolidated brief for respondent.