SEABOARD SUR. CO. v. TOWN OF GREENFIELD, 03-1453
Plaintiff is not liable on a construction performance bond because defendant failed to provide additional written notice that the period had begun after which they would be deemed in default. This failure resulted in a material breach discharging plaintiff from liability under the bond.