PORTLAND NATURAL GAS TRANSMISSION SYS. v. 19.2 ACRES OF LAND, 02-1369

The district court properly calculated the amount of compensation due under Massachusetts law after plaintiff took, by eminent domain, temporary and permanent easements on land to construct and operate a pipeline under the Natural Gas Act.

Appellate Information

  • Decided 01/31/2003
  • Published 01/31/2003

Judges

  • TORRUELLA, Circuit Judge., Before BOUDIN, Chief Judge, TORRUELLA, Circuit Judge, and CYR, Senior Circuit Judge.

Court

  • United States First Circuit

Counsel

  • For Appellant:
  • James T. Finnigan, with whom Rich May, PC was on brief, for appellants.

  • For Appellees:
  • James D. Masterman, with whom Richard D. Vetstein and Masterman, Culbert & Tully, LLP were on brief, for appellee WBC Extrusion Products, Inc.