Cyclonaire Corp. v. ISG Riverdale, 1070421

Order finding that plaintiff's subcontractor's mechanic's lien was invalid for failure to strictly comply with the 90-day written notice period mandated by section 24(a) of the Mechanics Lien Act is affirmed over claims that: 1) the trial court's judgment was against the manifest weight of the evidence; and 2) the trial court erred by excluding from evidence internal shipping and invoicing documents, which plaintiff claims would have proved that plaintiff's last date of performance fell within the applicable 90-day period.