Twin Oaks at Southwood, LLC v. Summit Constructors, Inc., 1D06-3913
In a lawsuit arising out of a construction contract, an order granting plaintiff-contractor's motion to dismiss defendant-owner's counterclaims and determining that plaintiff was entitled to arbitration of the counterclaims is reversed where the trial court erred as a matter of law in finding that the trial court erred as a matter of law in ruling that a "Project Completion Agreement" was a separate agreement from the original construction contract, and that plaintiff did not waive its right to demand arbitration when it instituted the litigation.
Appellate Information
- Decided 11/22/2006
- Published 11/27/2006
Judges
- BARFIELD, J.
Court
- District Court of Appeal of Florida
Counsel
- For Appellant:
- M. Stephen Turner, P.A., and J. Nels Bjorkquist, of Broad and Cassel, Tallahassee, for Appellant.
- For Appellees:
- Hugh M. Davenport, Jacksonville, for Appellee.