The Utility Reform Network v. Public Utilities Commission, A138701
The California Public Utilities Commission's approval of PG&E's application for a new gas-fired power plant is annulled, where: 1) the Commission's finding of need for the plant is unsupported by substantial evidence, because it relies on uncorroborated hearsay materials the truth of which is disputed and which do not come within any exception to the hearsay rule; and 2) the remaining evidence in the record fails to support the Commission's finding of need.
Appellate Information
- Decided 02/05/2014
- Published 02/05/2014
Judges
- JONES
Court
- California Court of Appeal