J & GS Restoration, Inc., Appellant, v. Metro Contractors, LLC, Respondent.
ORDERED that the judgment is modified by increasing the award in favor of plaintiff to the principal sum of $2,850; as so modified, the judgment is affirmed, without costs.
Plaintiff commenced this commercial claims action to recover the principal sum of $5,800, which, plaintiff alleged, was the outstanding sum due for subcontracting work it had provided defendant, a general contractor. At a nonjury trial, the parties agreed that plaintiff had completed a project for defendant with a price of $4,050, toward which defendant had paid $4,000. Plaintiff presented testimony that it had also completed a second project for defendant with a price of $3,800, toward which defendant had paid $1,000, and a third project with a price of $2,950, which defendant had not paid. Defendant denied that it had engaged plaintiff to complete anything except the $4,050 project and asserted that the $1,000 payment applied to the $3,800 project was an "accident." After a nonjury trial, the Civil Court (Mark M. Kagan, J.) awarded plaintiff a judgment in the principal sum of $2,800, representing the balance due on the $3,800 project. Plaintiff appeals from the May 27, 2025 judgment on the ground of inadequacy.
In a commercial claims action, this court's review is limited to a determination of whether "substantial justice has . . . been done between the parties according to the rules and principles of substantive law" (CCA 1807-A [a]; see CCA 1804-A; Ross v Friedman, 269 AD2d 584 [2000]; Williams v Roper, 269 AD2d 125 [2000]). Furthermore, the determination of a trier of fact as to issues of credibility is given substantial deference, as a trial court's opportunity to observe and evaluate the testimony and demeanor of the witnesses affords it a better perspective from which to assess their credibility (see Vizzari v State of New York, 184 AD2d 564 [1992]; Kincade v Kincade, 178 AD2d 510 [1991]). This deference applies with greater force to judgments rendered in the Commercial Claims Part of the court, (see Williams v Roper, 269 AD2d at 126).
Here, the court implicitly resolved issues of credibility as to the $2,950 project in defendant's favor, and we find no basis to disturb that determination. In light of the parties' agreement that defendant had paid only $4,000 toward the $4,050 project, however, substantial justice will be rendered (see CCA 1804-A, 1807-A [a]) by increasing the award in favor of plaintiff by $50, to the principal sum of $2,850.
Accordingly, the judgment is modified by increasing the award in favor of plaintiff to the principal sum of $2,850.
BUGGS, J.P., MUNDY and LIN, JJ., concur.
ENTER:
Jennifer Chan
Chief Clerk
Decision Date: September 18, 2026
Thank you for your feedback!
As the largest network of trusted legal brands, we help firms build authority across the platforms consumers and AI systems rely on most. Our network helps attorneys strengthen visibility, credibility, and preference where legal decisions begin.
Docket No: 2025-1104 Q C
Decided: September 18, 2026
Court: Supreme Court, Appellate Term, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Make It a Preferred Google Search Source
Add to GoogleGet help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)
Answer a few questions and get helpful next steps for your legal issue.