Jennifer J. SUCRE, etc., Appellant, v. CONSOLIDATED EDISON COMPANY OF NEW YORK, INC., et al., Respondents, et al., Defendant.
DECISION & ORDER
In a consolidated action to recover damages for wrongful death, the plaintiff appeals from an order of the Supreme Court, Queens County (Janice A. Taylor, J.), entered January 6, 2017. The order, insofar as appealed from, granted that branch of the motion of the defendants Consolidated Edison Company of New York, Inc., and Consolidated Edison, Inc., which was pursuant to CPLR 3211(a)(7) to dismiss the complaint insofar as asserted against them, and denied, as academic, the plaintiff's cross motion for summary judgment on the issue of liability insofar as asserted against those defendants.
ORDERED that the order is reversed insofar as appealed from, on the law, with costs, that branch of the motion of the defendants Consolidated Edison Company of New York, Inc., and Consolidated Edison, Inc., which was pursuant to CPLR 3211(a)(7) to dismiss the complaint insofar as asserted against them is denied, and the plaintiff's cross motion for summary judgment on the issue of liability insofar as asserted against the defendants Consolidated Edison Company of New York, Inc., and Consolidated Edison, Inc., is denied on the merits.
The plaintiff, the administratrix of the estate of the decedent, commenced this wrongful death action against, among others, the defendants Consolidated Edison Company of New York, Inc., and Consolidated Edison, Inc. (hereinafter together Con Edison), alleging, inter alia, that Con Edison negligently caused the decedent's death. According to the plaintiff, the decedent was electrocuted to death while working as a self-employed roofing contractor. The plaintiff alleged that the decedent had been repairing the roof of the home of a client when he came into contact with an uninsulated, exposed electrical wire leading from his client's home to Con Edison's electrical lines. According to the plaintiff, Con Edison negligently caused the decedent's death by allowing and permitting the installation and connection of its electrical lines to the homeowner's electrical wires in a manner that was improper and not in compliance with applicable code standards. The plaintiff contends that, as a result, the wires became unsafe, defective, and dangerous to individuals such as the decedent who reasonably could be foreseen to be working near those wires.
Con Edison moved pursuant to CPLR 3211(a)(7) to dismiss the complaint insofar as asserted against it, on the ground that it did not owe a duty to the decedent or, in the alternative, for summary judgment dismissing the complaint insofar as asserted against it. The plaintiff cross-moved for summary judgment on the issue of liability insofar as asserted against Con Edison. The Supreme Court, inter alia, granted that branch of Con Edison's motion which was pursuant to CPLR 3211(a)(7) to dismiss the complaint insofar as asserted against it and denied, as academic, the plaintiff's cross motion.
The Supreme Court should have denied that branch of Con Edison's motion which was pursuant to CPLR 3211(a)(7). “In determining a motion for failure to state a cause of action, the court must ‘accept the facts as alleged in the complaint as true, accord plaintiffs the benefit of every possible favorable inference, and determine only whether the facts as alleged fit within any cognizable legal theory’ ” (Miglino v. Bally Total Fitness of Greater N.Y., Inc., 92 A.D.3d 148, 158, 937 N.Y.S.2d 63, affd 20 N.Y.3d 342, 961 N.Y.S.2d 364, 985 N.E.2d 128, quoting Leon v. Martinez, 84 N.Y.2d 83, 87–88, 614 N.Y.S.2d 972, 638 N.E.2d 511). In order to succeed on its motion to dismiss, Con Edison had to establish that the complaint fails to state a viable cause of action (see Leon v. Martinez, 84 N.Y.2d at 88, 614 N.Y.S.2d 972, 638 N.E.2d 511). Here, Con Edison contended, inter alia, that it owed no duty to the decedent.
“[T]he existence and scope of a duty is a question of law requiring courts to balance sometimes competing public policy considerations” (Espinal v. Melville Snow Contrs., 98 N.Y.2d 136, 138, 746 N.Y.S.2d 120, 773 N.E.2d 485; see Palka v. Servicemaster Mgt. Servs. Corp., 83 N.Y.2d 579, 584–585, 611 N.Y.S.2d 817, 634 N.E.2d 189). Contrary to Con Edison's contention, it failed to establish that it owed no duty to the decedent (see Garda v. Paramount Theatre, LLC, 145 A.D.3d 964, 966, 44 N.Y.S.3d 163). Viewing the allegations in the light most favorable to the plaintiff, since the plaintiff alleged that Con Edison authorized the installation of an improper and non code-compliant connection between its electrical lines and the homeowner's electrical system, such actions gave rise to Con Edison's duty to the decedent who reasonably could be expected to come into contact with the property's electrical wires (see Espinal v. Melville Snow Contrs., 98 N.Y.2d at 140, 746 N.Y.S.2d 120, 773 N.E.2d 485; see also Miner v. Long Is. Light. Co., 40 N.Y.2d 372, 378, 386 N.Y.S.2d 842, 353 N.E.2d 805). Thus, Con Edison did not establish that the plaintiff failed to state a cause of action to recover damages for negligence.
However, we agree with the Supreme Court's denial of the plaintiff's cross motion for summary judgment on the issue of liability insofar as asserted against Con Edison, albeit on different grounds. “Summary judgment is a drastic remedy that deprives a litigant of his or her day in court, and it ‘should only be employed when there is no doubt as to the absence of triable issues’ ” (Kolivas v. Kirchoff, 14 A.D.3d 493, 493, 787 N.Y.S.2d 392, quoting Andre v. Pomeroy, 35 N.Y.2d 361, 364, 362 N.Y.S.2d 131, 320 N.E.2d 853). Here, the conflicting expert opinions regarding the applicable code and standards at the time of the electric service installation and whether Con Edison breached its duty by authorizing an unsafe installation and hookup of its electrical lines to the homeowner's premises create material and triable issues of fact that preclude summary judgment (see Urias v. Daniel P. Buttafuoco & Assoc., PLLC, 173 A.D.3d 1244, 1246, 104 N.Y.S.3d 712; Mangano v. Town of Babylon, 111 A.D.3d 801, 802, 975 N.Y.S.2d 130).
Con Edison's remaining contentions are without merit.
BALKIN, J.P., COHEN, MILLER and DUFFY, JJ., concur.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Docket No: 2017–01673
Decided: June 17, 2020
Court: Supreme Court, Appellate Division, Second Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)