PRIMARY ELECTRICAL EQUIPMENT, INC., doing business as Primary Electrical Supply, respondent, v. ALDONA FIRE PROTECTION, INC., doing business as A. Electric Electrical Construction, appellant.
In an action, inter alia, to recover damages for breach of contract, the defendant appeals from a judgment of the Supreme Court, Queens County (Florio, Ct.Atty.Ref.), entered June 27, 2012, which, after a nonjury trial, is in favor of the plaintiff and against it in the sum of $61,230.30.
ORDERED that the judgment is affirmed, with costs.
In reviewing a determination made after a nonjury trial, the power of this Court is as broad as that of the trial court, and this Court may render the judgment it finds warranted by the facts, bearing in mind that the trial judge had the advantage of seeing the witnesses and hearing the testimony (see Baba–Ali v. State of New York, 19 NY3d 627, 640; Northern Westchester Professional Park Assoc. v. Town of Bedford, 60 N.Y.2d 492, 499; Kozar v. Christie's, Inc., 109 AD3d 967).
The evidence adduced at trial in this case demonstrated that the defendant contracted for the purchase and delivery of certain electrical equipment from the plaintiff, that the defendant accepted the delayed delivery of the equipment, and that the defendant installed and used the equipment without objection and without paying the balance of the purchase price due and owing under the contract. Contrary to the defendant's contention, the evidence did not establish either that the delay in delivering the equipment was unreasonable under the circumstances, or that any portion of the delay was attributable to the plaintiff. In any event, the defendant's acceptance of the delayed delivery without further objection, and without the assertion of any claim for a setoff or for damages due to the delay, supports the conclusion that it acquiesced in the delay and so cannot now avoid its contractual payment obligation (see Ring 57 Corp. v. Litt, 28 A.D.2d 548, 548–549; see generally Burgess Steel Prods. Corp. v. Modern Telecom., 205 A.D.2d 344, 346). Accordingly, we decline to disturb the Supreme Court's determination awarding judgment in favor of the plaintiff.
Thank you for your feedback!
As the largest network of trusted legal brands, we help firms build authority across the platforms consumers and AI systems rely on most. Our network helps attorneys strengthen visibility, credibility, and preference where legal decisions begin.
Decided: January 15, 2014
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)