Sandro FARDUCHI, plaintiff, v. UNITED ARTISTS THEATRE CIRCUIT, INC., et al., appellants, Construction of New York, Inc., respondent, et al., defendants.
In an action to recover damages for personal injuries, the defendants United Artists Theatre Circuit, Inc., and Street Retail Forest Hills I, LLC, appeal from an order of the Supreme Court, Queens County (Golar, J.), dated April 14, 2004, which denied their motion for summary judgment on their cross claims for common-law and contractual indemnification, including insurance and defense costs, insofar as asserted against the defendant Pepco Construction of New York, Inc.
ORDERED that the order is affirmed, with costs.
The Supreme Court properly denied summary judgment to United Artists Theatre Circuit, Inc., and Street Retail Forest Hills I, LLC (hereinafter collectively the Owners), on their cross claims against the general contractor, Pepco Construction of New York, Inc. (hereinafter Pepco), because a triable issue of fact existed as to Pepco's alleged negligence and that of its subcontractors and sub-subcontractors, and as to whether Pepco exclusively supervised and controlled the work area where the accident occurred. Thus, even though the Owners' liability was purely statutory and vicarious, conditional summary judgment for common-law indemnification would have been premature (see Perri v. Gilbert Johnson Enters., Ltd., 14 A.D.3d 681, 685, 790 N.Y.S.2d 25; Hernandez v. Two E. End Ave. Apt. Corp., 303 A.D.2d 556, 558, 757 N.Y.S.2d 65). Moreover, because the subject contract required indemnification only where there was negligence on the part of the contractor or its agents, summary judgment for contractual indemnification would also have been premature (see Kader v. City of N.Y., Hous. Preserv. & Dev., 16 A.D.3d 461, 463, 791 N.Y.S.2d 634).
The plaintiff's contention that he is entitled to summary judgment on his cause of action alleging a violation of Labor Law § 241(6) is not properly before this court (see Dunham v. Hilco Constr. Co., 89 N.Y.2d 425, 654 N.Y.S.2d 335, 676 N.E.2d 1178).
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: November 28, 2005
Court: Supreme Court, Appellate Division, Second Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)