SIRIUS AMERICA INSURANCE COMPANY, et al., plaintiffs-respondents-appellants, v. VIGO CONSTRUCTION CORP., defendant-respondent-appellant, Martin C. Gonzalez, appellant-respondent, East Wind Contracting, Inc., et al., defendants.
In an action for a judgment declaring that the plaintiff Sirius America Insurance Company is not obligated to defend and indemnify the defendant Vigo Construction Corp. in an underlying action entitled Gonzalez v. Vigo Construction Corp., pending in the Supreme Court, Queens County, under Index No. 04/10349, the defendant Martin C. Gonzalez appeals, as limited by his brief, from so much of an order of the Supreme Court, Queens County (Dorsa, J.), dated June 27, 2006, as denied his cross motion for summary judgment, the plaintiffs cross-appeal from so much of the same order as denied their motion for summary judgment declaring that the plaintiff Sirius America Insurance Company is not obligated to defend and indemnify the defendant Vigo Construction Corp. in the underlying action, and the defendant Vigo Construction Corp. cross-appeals from the same order.
ORDERED that the cross appeal of the defendant Vigo Construction Corp., is dismissed, as that defendant is not aggrieved by the order (see CPLR 5511); and it is further,
ORDERED that the order is reversed insofar as appealed from, on the law, and the cross motion of the defendant Martin C. Gonzalez for summary judgment is granted; and it is further,
ORDERED that the order is affirmed insofar as cross-appealed from by the plaintiffs; and it is further,
ORDERED that one bill of costs is awarded to the defendant Martin C. Gonzalez payable by the respondents-appellants appearing separately and filing separate briefs; and it is further,
ORDERED that the matter is remitted to the Supreme Court, Queens County for the entry of a judgment declaring that the plaintiff Sirius America Insurance Company is obligated to defend and indemnify the defendant Vigo Construction Corp., in an underlying action entitled Gonzalez v. Vigo Construction Corp., pending in the Supreme Court, Queens County, under Index No. 04/10349.
Preliminarily, we note that the cross appeal of the defendant Vigo Construction Corp. (hereinafter Vigo), must be dismissed, because only an “aggrieved party” has standing to appeal (CPLR 5511). Vigo did not seek any relief in the Supreme Court, and the plaintiffs' motion for summary judgment, which Vigo opposed, was denied (see Anspach v. Miller Bluff's Constr. Corp., 280 A.D.2d 564, 720 N.Y.S.2d 536). Additionally, merely because the order appealed from contains language or reasoning that a party deems adverse to its interests does not furnish “a basis for standing to take an appeal” (Castaldi v. 39 Winfield Assoc., LLC, 22 A.D.3d 780, 803 N.Y.S.2d 716; quoting Pennsylvania Gen. Ins. Co. v. Austin Powder Co., 68 N.Y.2d 465, 472-473, 510 N.Y.S.2d 67, 502 N.E.2d 982).
Insurance Law § 3420(d) requires an insurer to provide a written disclaimer “as soon as is reasonably possible.” The reasonableness of any delay in providing such written disclaimer is measured from the time when the insurer “has sufficient knowledge of facts entitling it to disclaim, or knows that it will disclaim coverage” (First Fin. Ins. Co. v. Jetco Contr. Corp., 1 N.Y.3d 64, 66, 769 N.Y.S.2d 459, 801 N.E.2d 835). The insurer bears the burden of justifying any delay (id. at 69, 769 N.Y.S.2d 459, 801 N.E.2d 835). In the instant case, Sirius relied upon a disclaimer dated November 3, 2004, and sent 34 days after it knew or should have known of the basis for denying coverage. Since there was no explanation for that delay, the 34-day delay in disclaiming coverage was unreasonable as a matter of law and thus ineffective (see Matter of Allstate Ins. Co. v. Swinton, 27 A.D.3d 462, 811 N.Y.S.2d 108; Pawley Interior Contr., Inc. v. Harleysville Ins. Cos., 11 A.D.3d 595, 782 N.Y.S.2d 660; Moore v. Ewing, 9 A.D.3d 484, 781 N.Y.S.2d 51; cf. Farmbrew Realty Corp. v. Tower Ins. Co. of N.Y., 289 A.D.2d 284, 734 N.Y.S.2d 592; Brooklyn Hosp. Ctr. v. Centennial Ins. Co., 258 A.D.2d 491, 685 N.Y.S.2d 267). Under these circumstances, the defendant Martin C. Gonzalez was entitled to judgment as a matter of law on the issue of whether Sirius was required to defend and indemnify Vigo in an underlying action entitled Gonzalez v. Vigo Construction Corp., pending in the Supreme Court, Queens County, under Index No. 04/10349. Since this is a declaratory judgment action, the matter must be remitted to the Supreme Court, Queens County for the entry of a judgment declaring that Sirius is obligated to defend and indemnify Vigo Construction Corp. in that action (see Lanza v. Wagner, 11 N.Y.2d 317, 334, 229 N.Y.S.2d 380, 183 N.E.2d 670, appeal dismissed 371 U.S. 74, 83 S.Ct. 177, 9 L.Ed.2d 163, cert. denied, 371 U.S. 901, 83 S.Ct. 205, 9 L.Ed.2d 164).
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: February 05, 2008
Court: Supreme Court, Appellate Division, Second Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)