IN RE: MARSON CONSTRUCTION CORPORATION, et al., appellants, v. MTA NEW YORK CITY TRANSIT, etc., respondent.
In a proceeding pursuant to CPLR article 78 to review a determination of the Chief Engineer of the respondent, MTA New York City Transit, dated January 16, 1997, which determined that the respondent was entitled to deduct the profit, overhead, and bond costs associated with a negotiated credit on work that the respondent deleted from a construction contract with the petitioner Marson Construction Corporation, the petitioners appeal from so much of an order and judgment (one paper) of the Supreme Court, Kings County (Dowd, J.), dated June 17, 1998, as granted the respondent's cross motion for reargument of a judgment of the same court, dated October 30, 1997, which granted the petition and, upon reargument, vacated the judgment, denied the petition, and dismissed the proceeding.
ORDERED that the order and judgment is affirmed insofar as appealed from, with costs.
The petitioners seek to review a determination of the Chief Engineer of the respondent, MTA New York City Transit (hereinafter the TA), as arbitrator under a construction contract. The determination permitted the TA to deduct $125,560.50 in profit, overhead, and bond costs associated with work deleted from the contract. That determination was based on Article 4.04(a) of the contract. As the parties agree, under the terms of the contract, the Chief Engineer's determination may be annulled only if it is “arbitrary, capricious or lacks rational basis”.
The determination of the Chief Engineer that the TA was entitled to deduct profit, overhead, and bond costs when deleting work from the contract was not irrational (see, Matter of Pell v. Board of Educ., 34 N.Y.2d 222, 231, 356 N.Y.S.2d 833, 313 N.E.2d 321). Additionally, this court is precluded from reviewing the reasonableness of the amount deducted for profit, overhead, and bond costs because the petitioners never challenged it before the Chief Engineer (see, Matter of Sudarsky v. State Div. of Hous. & Community Renewal, 258 A.D.2d 405, 685 N.Y.S.2d 704; Matter of Willets Point Contr. Corp. v. Department of Motor Vehicles of State of N.Y., 227 A.D.2d 411, 642 N.Y.S.2d 63). Finally, the petitioners' contention that the arbitration process was procedurally improper is without merit, since the contract did not mandate either that the Chief Engineer hold a hearing or that the petitioner Marson Construction Corporation be given the opportunity to submit reply papers (see, Westinghouse Elec. Corp. v. New York City Tr. Auth., 82 N.Y.2d 47, 603 N.Y.S.2d 404, 623 N.E.2d 531).
MEMORANDUM BY THE COURT.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: August 09, 1999
Court: Supreme Court, Appellate Division, Second Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)