In an action to recover damages for personal injuries, the defendant McNulty Development Corp. appeals from an order of the Supreme Court, Nassau County (R. Bruce Cozzens, Jr., J.), entered September 22, 2023. The order, insofar as appealed from, denied those branches of that defendant's motion which were for summary judgment dismissing the causes of action alleging violations of Labor Law §§ 240(1) and 241(6) insofar as asserted against it.
ORDERED that the order is reversed insofar as appealed from, on the law, with costs, and those branches of the motion of the defendant McNulty Development Corp. which were for summary judgment dismissing the causes of action alleging violations of Labor Law §§ 240(1) and 241(6) insofar as asserted against it are granted.
The defendant McNulty Development Corp. (hereinafter MDC) was retained by Shore Oaks, LLC (hereinafter Shore Oaks), as a construction manager to manage the construction and to arrange for the coordination and scheduling of construction of a single-family residence on a lot located on Shore Drive in Plandome (hereinafter the project). Shore Oaks hired and paid the contractors on the project, including Castro Carpentry Corp. (hereinafter Castro). On January 7, 2021, the plaintiff was employed as a carpenter by Castro when he fell 18 feet to the ground from the roof of the house while putting up windows and molding using an air gun. The plaintiff subsequently commenced this action against the defendants. MDC moved, inter alia, for summary judgment dismissing the causes of action alleging violations of Labor Law §§ 240(1) and 241(6) insofar as asserted against it, contending that it was not authorized to supervise or control the plaintiff's work. The Supreme Court denied those branches of the motion, and MDC appeals.
Labor Law §§ 240(1) and 241(6) provide that “the nondelegable duties imposed by those statutes apply only to contractors and owners and their agents” (Bonkoski v. Condos Bros. Constr. Corp., 216 A.D.3d 612, 614, 188 N.Y.S.3d 137 [internal quotation marks omitted]). “Although a construction manager of a work site is generally not responsible for injuries under Labor Law §§ 200, 240(1), or 241(6), when it functions as an agent of the property owner or general contractor in circumstances where it has the ability to control the activity which brought about the plaintiff's injury, responsibility will attach” (Jin Gak Kim v. Kirchoff–Consigli Constr. Mgt., LLC, 197 A.D.3d 1289, 1290–1291, 152 N.Y.S.3d 324; see Maurisaca v. Bowery at Spring Partners, L.P., 168 A.D.3d 711, 712, 91 N.Y.S.3d 454). In this regard, a party is deemed to be an agent of an owner or general contractor under the Labor Law when it has supervisory control and authority over the work being done where a plaintiff is injured (see Lamar v. Hill Intl., Inc., 153 A.D.3d 685, 686, 59 N.Y.S.3d 756). “An agent's liability is limited to those areas and activities within the scope of the work delegated or, in other words, to the particular agency created” (id. [internal quotation marks omitted]).
Here, MDC established its prima facie entitlement to judgment as a matter of law through, among other things, the deposition testimony of the plaintiff and the contractual agreement between itself and Shore Oaks, which demonstrated that MDC did not have the authority to control or supervise the plaintiff's work (see Giannas v. 100 3rd Ave. Corp., 166 A.D.3d 853, 856, 88 N.Y.S.3d 442; Lamar v. Hill Intl., Inc., 153 A.D.3d at 686, 59 N.Y.S.3d 756). In opposition, the plaintiff failed to raise a triable issue of fact. The plaintiff's contentions that MDC was contractually responsible for reviewing and coordinating the safety programs of the contractors on the project site, yet failed to ensure compliance, and was required to coordinate the activities of all the contractors and report any deficiencies to Shore Oaks were insufficient to raise a triable issue of fact (see Lamar v. Hill Intl., Inc., 153 A.D.3d at 686, 59 N.Y.S.3d 756; Rodriguez v. JMB Architecture, LLC, 82 A.D.3d 949, 951, 919 N.Y.S.2d 40; Armentano v. Broadway Mall Props., Inc., 30 A.D.3d 450, 451, 817 N.Y.S.2d 132; Loiacono v. Lehrer McGovern Bovis, Inc., 270 A.D.2d 464, 464, 704 N.Y.S.2d 658).
Accordingly, the Supreme Court should have granted those branches of MDC's motion which were for summary judgment dismissing the causes of action alleging violations of Labor Law §§ 240(1) and 241(6) insofar as asserted against it.
IANNACCI, J.P., GENOVESI, WAN and LANDICINO, JJ., concur.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Docket No: 2023-10090
Decided: February 26, 2025
Court: Supreme Court, Appellate Division, Second Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)