WEST ORANGE MANAGEMENT, INC., respondent, v. Vincent ALAIMO, et al., appellants.
In an action, inter alia, to recover damages for breach of contract, the defendants appeal from a judgment of the Supreme Court, Orange County (Alfieri, J.), dated June 28, 2007, which, after a nonjury trial, is in favor of the plaintiff and against them in the principal sum of $5,500, and dismissed their counterclaims.
ORDERED that the judgment is affirmed, with costs.
The plaintiff commenced this action to recover a balance owed on a written agreement with the defendants to demolish and remove a building, and to recover additional costs allegedly incurred as a result of misrepresentations made by the defendants concerning the project. The defendants counterclaimed, inter alia, to recover damages for alleged breaches of the contract and for negligence in the performance of the same, including damage to a boiler during its removal and relocation to another property. After a nonjury trial, the court found, inter alia, in favor of the plaintiff on its cause of action to recover the balance of the contract price, and dismissed the counterclaims. The defendants appeal. We affirm.
Upon review of a determination rendered after a nonjury trial, this Court's authority is as broad as that of the trial court, and this Court may render the judgment it finds warranted by the facts, taking into account in a close case the fact that the trial judge had the advantage of seeing the witnesses (see Candela v. Byron Chem. Co., Inc., 54 A.D.3d 306, 863 N.Y.S.2d 230). Here, we find no basis to disturb the Supreme Court's determination on appeal, including its findings as to credibility. The plaintiff proved substantial performance of the contract and entitlement to the balance of the contract price (see Spence v. Ham, 163 N.Y. 220, 57 N.E. 412; cf. Trataros Constr., Inc. v. New York City School Constr. Auth., 46 A.D.3d 871, 849 N.Y.S.2d 437). In opposition, the defendants failed to prove that they sustained damages as a result of a breach or the negligent performance of the contract, other than the damages to the boiler. Further, contrary to the defendants' contention on appeal, the Supreme Court did not deny their request for an adjournment in order to produce the owner of the plaintiff as a witness. Rather, the request was abandoned.
The defendants' remaining contentions are without merit.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: December 02, 2008
Court: Supreme Court, Appellate Division, Second Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)