CLAUDE STATEN, Plaintiff–Appellant, v.
THE CITY OF NEW YORK, Defendant–Respondent.THE CITY OF NEW YORK, Third–Party Plaintiff–Respondent, v. ZHL GROUP, INC. et al., Third–Party Defendants.
/18
Order, Supreme Court, Bronx County (Wilma Guzman, J.), entered January 21, 2025, which granted defendant's motion to dismiss the complaint, denied defendant's motion for a protective order as moot, and, in effect, denied plaintiff's cross-motion to compel, unanimously affirmed, without costs.
In this action for injuries related to the latent effect of exposure to construction dust and debris, the statute of limitations began to run when plaintiff discovered the primary conditions on which his claim is based, and not when he subsequently suffered worsened symptoms that necessitated transport to the hospital and time off from work (see Matter of New York County DES Litig., 89 N.Y.2d 506, 509 [1997] ).
Plaintiff testified that he experienced progressively worsening physical symptoms over the course of June and July 2017, which he attributed, at the time, to construction dust and debris, before the July 26, 2017 incident that resulted in his transport to the hospital. These symptoms included chest pains, shortness of breath and nausea. He complained to an NYPD plant manager about the construction dust and debris making him sick before the July 26, 2017 incident, and defendant put forth unrebutted evidence demonstrating that plaintiff's conversation with the NYPD plant manager necessarily occurred, at the latest, by July 22, 2017. In addition, the documentary evidence, including his medical record and notice of claim, established that prior to his hospitalization, plaintiff was aware of a change in his physical condition and attributed it to the construction debris. Thus, his symptoms were not “too isolated or inconsequential” to start the limitations period running before July 26, 2017 (see Ward v. Lincoln Elec. Co., 116 AD3d 558, 559 [1st Dept 2014] [internal quotation marks omitted] ). Nonetheless, plaintiff did not file his notice of claim, required by General Municipal Law § 50–e (1), until October 23, 2017, more than 90 days after he complained of the construction dust and debris causing him sickness. Thereafter, plaintiff never sought leave to file the untimely notice of claim before the expiration of the applicable 1 year and 90–day statute of limitations period. Thus, the court correctly dismissed plaintiff's complaint.
We have considered plaintiff's remaining arguments, including those related to the branch of the appeal concerning discovery issues, and find them unavailing.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Docket No: Index No. 30997 /18
Decided: May 21, 2026
Court: Supreme Court, Appellate Division, First Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)