GREYSTONE BUILDING & DEVELOPMENT CORP., Plaintiff–Appellant, v. MAKRO GENERAL CONTRACTORS, INC., et al., Defendants–Respondents, The New York City Transit Authority, Defendant.
Order, Supreme Court, New York County (David Benjamin Cohen, J.), entered on or about December 10, 2018, which denied plaintiff's motion for summary judgment, and granted defendants Makro General Contractors, Inc. and Hercules Argyriou's motion to dismiss the complaint as against them, unanimously modified, on the law, to deny defendants' motion, and otherwise affirmed, without costs.
Summary judgment in plaintiff's favor on its claim for payment for work performed is precluded by issues of fact as to the portion of the contract that was performed and the portion that was deleted (see e.g. F. Garofalo Elec. Co. v. New York Univ., 300 A.D.2d 186, 189, 754 N.Y.S.2d 227 [1st Dept. 2002]; Sea Crest Constr. Corp. v. City of New York, 286 A.D.2d 652, 730 N.Y.S.2d 332 [1st Dept. 2001]).
Defendants are not entitled to dismissal of the complaint on the ground that the action was commenced outside the one-year period of limitations contained in the subcontract between defendant Makro and plaintiff for claims arising out of the subcontract. While there is nothing inherently unreasonable about the one-year limitations period, it is unenforceable under the circumstances of this case (see AWI Sec. & Investigations, Inc. v. Whitestone Constr. Corp., 164 A.D.3d 43, 47, 82 N.Y.S.3d 14 [1st Dept. 2018]; D & S Restoration, Inc. v. Wenger Constr. Co., Inc., 160 A.D.3d 924, 75 N.Y.S.3d 505 [2d Dept. 2018]). After work commenced, a certain portion of the subcontracted work became impracticable, and deletions and change orders were made to Makro's prime contract with defendant New York City Transit Authority (NYCTA) and, by extension, the subcontract. Although, according to plaintiff's principal (additional defendant on counterclaim Theodore Melittas), plaintiff's work was substantially completed in September of 2013, negotiations among NYCTA, Makro and plaintiff over the value of the credit for the deleted work proceeded until September of 2015. However, under the subcontract, plaintiff was not entitled to final payment until NYCTA paid Makro. Thus, the one-year limitation period had run before the final negotiations were complete, i.e., before NYCTA would have paid Makro (see Executive Plaza, LLC v. Peerless Ins. Co., 22 N.Y.3d 511, 518, 982 N.Y.S.2d 826, 5 N.E.3d 989 [2014] [“A ‘limitation period’ that expires before suit can be brought is not really a limitation period at all, but simply a nullification of the claim”] ).
Thank you for your feedback!
As the largest network of trusted legal brands, we help firms build authority across the platforms consumers and AI systems rely on most. Our network helps attorneys strengthen visibility, credibility, and preference where legal decisions begin.
Docket No: 11235
Decided: March 10, 2020
Court: Supreme Court, Appellate Division, First Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)