— A Northeast Restoration Corp., Plaintiff–Respondent, v. T.A. Ahern Contractors Corp., et al., Defendants–Appellants, New York City School Construction Authority, et al., Defendants.
_
Judgment, Supreme Court, Bronx County (Barry Salman, J.), entered April 18, 2014, after a nonjury trial, awarding plaintiff damages as against defendants T.A. Ahern Contractors Corp. and Safeco Insurance Company of America, unanimously affirmed, with costs. Appeal from order, same court and Justice, entered on or about April 15, 2014, unanimously dismissed, without costs, as subsumed in the appeal from the aforesaid judgment.
There is no basis for disturbing the trial court's finding in favor of plaintiff on its claim for unpaid change orders and work completed but not billed before the termination date of its contract with defendant Ahern (see generally Nagel v. Nagel, 85 AD3d 559 [1st Dept 2011] ). Contrary to defendants' contention, plaintiff was justified in refusing to continue performing work that it deemed outside the scope of the contract, absent a Notice of Direction (NOD) from Ahern, which would have protected its right to claim additional compensation for that work (compare Kalisch–Jarcho, Inc. v. City of New York, 72 N.Y.2d 727 [1988] [contractor was permitted to file a written protest to preserve its right to claim compensation for disputed work] ). The testimony of defendants' witness that the contract did not require an NOD under the circumstances was contradicted by the language of the contract, and was effectively an improper expert opinion as to a legal conclusion (see Colon v. Rent–A–Center, 276 A.D.2d 58, 61 [1st Dept 2000] ).
Plaintiff's evidence of its damages, including the work it performed from the last billing cycle to the termination, was sufficient. Further, the calculation used to determine the value of that work, i.e., the percentage of completion of the total contract price, was proper (see e.g. Schultz Constr. v. Franbilt, Inc., 285 A.D.2d 936 [3d Dept 2001] ).
The dismissal of Ahern's counterclaims is supported by evidence that plaintiff neither caused the claimed damages nor was responsible for them under the contract.
We have considered defendants' remaining contentions and find them unavailing.
_
CLERK
Thank you for your feedback!
As the largest network of trusted legal brands, we help firms build authority across the platforms consumers and AI systems rely on most. Our network helps attorneys strengthen visibility, credibility, and preference where legal decisions begin.
Docket No: 1592 6 1592 6
Decided: October 22, 2015
Court: Supreme Court, Appellate Division, First Department.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)