GATEWAY DEMOLITION CORP., Plaintiff-Appellant, v. LUMBERMAN'S MUTUAL CASUALTY COMPANY, etc., Defendant-Respondent.
Order, Supreme Court, New York County (Emily Jane Goodman, J.), entered April 20, 2009, which, in an action to, inter alia, recover an unpaid contract balance and payment for extras, denied plaintiff's motion for partial summary judgment and granted defendant's cross motion for summary judgment to the extent of dismissing plaintiff's demand for extra payment for losses it sustained by being compelled to work on weekends, unanimously affirmed, without costs.
The New York City Department of Sanitation entered into a contract with nonparty Rapid Demolition Company, Inc. to demolish several structures. Defendant acted as surety on the project, assuring the project's completion. Rapid subsequently defaulted on the contract and defendant entered into a contract with plaintiff to complete the demolition work, which included the demolition of a large concrete overpass. Requests were made to the New York City Department of Transportation (DOT) to close the subject street for a period of three weeks. DOT did not grant the closure of the street for the three weeks requested, but instead allowed the street to be closed only on weekends. The motion court properly found that plaintiff was not entitled to payment for extra costs it incurred as a result of the DOT's denial of its request to completely close the subject street for three weeks. The contract made no mention of the street closure, nor was plaintiff's timely completion of the demolition made conditional upon such closure. Furthermore, the grant of such closure was not implicit in the agreement (cf. Anders v. State of New York, 42 Misc.2d 276, 282-284, 248 N.Y.S.2d 4 [1964] ), and the denial of same, with the resulting limitation on the hours in which work could take place, cannot be considered an unforeseeable circumstance (see Peckham Rd. Co. v. State of New York, 32 A.D.2d 139, 300 N.Y.S.2d 174 [1969], affd. 28 N.Y.2d 734, 321 N.Y.S.2d 117, 269 N.E.2d 826 [1971] ).
Finally, the contract balance retained in escrow is subject to disputed claims of backcharges that cannot be resolved on this appeal.
We have considered plaintiff's remaining arguments and find them unavailing.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: October 29, 2009
Court: Supreme Court, Appellate Division, First Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)