METROPOLITAN STEEL INDUSTRIES, INC., Plaintiff-Appellant, v. TULLY CONSTRUCTION CO., INC., Defendant-Respondent,
Seaboard Surety Company, et al., Respondents. Tully Construction Co., Inc., Third-Party Plaintiff-Respondent, v. The City of New York, Third-Party Defendant-Respondent.
Order, Supreme Court, New York County (Herman Cahn, J.), entered March 20, 2008, which, in an action for delay damages by a subcontractor against the project's general contractor, and a third-party action by the general contractor against the site owner for its own delay damages and for indemnification of plaintiff's claims as well of the claims of “other subcontractors ․ [which] have demanded or will demand damages by reason of delays,” denied plaintiff's motion to vacate a prior order staying the action pending completion of the project, unanimously reversed, on the facts, without costs, the motion granted and the stay vacated.
The stay was imposed because, in the view of Supreme Court, significant judicial economies, including, in particular, the prospect of “mediation,” would be served by awaiting completion of the project and receipt of any and all claims by the other subcontractors, and then hearing and considering all of the claims together. While the general contractor and owner argue that completion of the project is necessary to determine the impact of all of the delays, neither show how the alleged errors and oversights in the foundation work, which allegedly caused the delay in plaintiff's steel erection work, in turn caused, in domino-like fashion, the cumulative delays in the project that have continually pushed its anticipated completion date back. Absent a showing that any delay damages likely to be claimed by the other subcontractors will be based on the same foundation problems alleged by plaintiff as the cause of its delay damages, it does not appear sufficiently likely that any significant judicial economies will be served by considering all of the subcontractors' claims for delay damages together (cf. Schneider v. Lazard Freres & Co., 159 A.D.2d 291, 293-294, 552 N.Y.S.2d 571 [1990] [stay imposed pending final determination of another action because other action “raises numerous possibilities for the application of collateral estoppel”]; Belopolsky v. Renew Data Corp., 41 A.D.3d 322, 837 N.Y.S.2d 154 [2007] ). The owner's request for a severance of the third-party action and stay of all proceedings therein, in the event this Court vacates the stay of the main action, is improperly made for the first time on appeal, and we decline to consider it.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: October 14, 2008
Court: Supreme Court, Appellate Division, First Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)