SNC, LTD., Plaintiff-Respondent-Appellant, v. KAMINE ENGINEERING AND MECHANICAL CONTRACTING CO., INC., et al., Defendants-Appellants-Respondents.
Order, Supreme Court, New York County (Walter Schackman, J.), entered August 9, 1996, which, inter alia, granted defendants' motions for summary judgment to the extent of dismissing plaintiff bidder's causes of action for breach of contract against the Owner defendants, except to the extent based on the Owner's duty to negotiate with plaintiff in good faith, and dismissing plaintiff's cause of action for tortious interference with contract against the Contractor defendants, except to the extent based on the Owner's duty to negotiate with plaintiff in good faith, unanimously affirmed, without costs.
There are issues of fact as to whether plaintiff and the Owner defendants reached a binding preliminary contract giving rise to a duty to negotiate in good faith, and, if so, whether the Owner defendants breached it (see, Goodstein Constr. Corp. v. City of New York, 67 N.Y.2d 990, 502 N.Y.S.2d 994, 494 N.E.2d 99, aff'g 111 A.D.2d 49, 52, 489 N.Y.S.2d 175; Teachers Ins. & Annuity Assn. v. Tribune Co., 670 F.Supp. 491, 498-499 [S.D.N.Y.] ). However, because of the preliminary nature of any agreement, plaintiff was required to demonstrate that its competitor, the Contractor defendants, used wrongful or unlawful means, or acted without competitive motive, in persuading the Owner defendants to abandon their negotiations with plaintiff (see, Guard-Life Corp. v. Parker Hardware Mfg. Corp., 50 N.Y.2d 183, 193-194, 428 N.Y.S.2d 628, 406 N.E.2d 445; Nassau Diagnostic Imaging & Radiation Oncology Assocs. v. Winthrop-University Hosp., 197 A.D.2d 563, 602 N.Y.S.2d 650, lv. denied 83 N.Y.2d 756, 614 N.Y.S.2d 386, 637 N.E.2d 277). While plaintiff's proof in that regard was lacking, the Contractor defendants failed to meet their initial burden of going forward on the motion for summary judgment, which, on that basis, was properly denied (see, Winegrad v. New York Univ. Med. Center, 64 N.Y.2d 851, 853, 487 N.Y.S.2d 316, 476 N.E.2d 642). The motion by the Ansaldo defendants may be renewed upon completion of discovery, should they be so advised. We are in accord with the balance of the IAS court's determination and find the parties' other arguments for affirmative relief to be without merit.
MEMORANDUM DECISION.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: April 03, 1997
Court: Supreme Court, Appellate Division, First Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)