Peter BROWN, Plaintiff-Appellant, v. BRUCKNER PLAZA ASSOCIATES, Defendant, Toys R Us Inc., Defendant-Respondent.
[And a Third Party Action]. Toys “R” Us-NY, LLC, Second Third-Party Plaintiff-Respondent, v. CBI Drywall Corp., Second Third-Party Defendant-Respondent.
Order, Supreme Court, Bronx County (Kenneth Thompson, Jr., J.), entered January 15, 2002, which, insofar as appealed from, dismissed the complaint as against defendant Toys R Us upon motions for summary judgment, unanimously affirmed, without costs.
Acting as its own general contractor on a construction project, defendant Toys R Us employed Marc Norotsky as construction supervisor, and entered into purchase orders with third-party defendant C. Bros., Inc. (“C. Bros.”) to provide labor “as required by job superintendent” or “for clean up as directed by site management.” Toys R Us also contracted with CBI Drywall Corp. (“CBI”) to perform the drywall work on the project. C. Bros. and CBI shared common ownership and management. Plaintiff was injured while leveling off a dumpster pursuant to Norotsky's direction. Norotsky hired plaintiff who reported any problem he had to Norotsky. He considered Norotsky to be his supervisor, and was directed, controlled and supervised by Norotsky with respect to his clean-up work outside the building, including the specific work he was doing when he was injured. These facts establish as a matter of law that Toys R Us was plaintiff's special employer, notwithstanding that plaintiff was paid by C. Bros., and that a CBI foreman may have on occasion directed plaintiff to do some interior work. C. Bros., not CBI, was plaintiff's general employer, and the labor provided by the former and subject to Norotsky's control was distinct from the work provided by the latter. There is no showing that C. Bros. retained any authority over the work of its laborers once they were assigned to Toys R Us in accordance with the purchase orders, or that C. Bros. or CBI had any on-the-job authority over plaintiff that superseded Norotsky's authority (see, Gannon v. JWP Forest Elec. Corp., 275 A.D.2d 231, 712 N.Y.S.2d 494; see, Kramer v. NAB Constr. Corp., 282 A.D.2d 714, 715, 724 N.Y.S.2d 187, lv. denied 97 N.Y.2d 606, 738 N.Y.S.2d 290, 764 N.E.2d 394). We have considered plaintiff's other arguments and find them unavailing.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: June 18, 2002
Court: Supreme Court, Appellate Division, First Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)