PHELPS GUIDE RAIL, Plaintiff-Appellant, v. UNITED STATES FIDELITY & GUARANTY COMPANY and Midstate Construction Services, Inc., Defendants-Respondents. (Appeal No. 2.)
Supreme Court properly granted the motion of defendant United States Fidelity & Guaranty Company (Fidelity) seeking dismissal of the complaint against it as time-barred. The record establishes that plaintiff entered into a subcontract with defendant Midstate Construction Services, Inc. (Midstate) in September 2001 pursuant to which plaintiff was to provide guardrails in connection with Midstate's contract with the New York State Office of General Services (State) for the repair and replacement of underground heating lines at a correctional facility. In accordance with State Finance Law § 137, Midstate had obtained a labor and material bond (payment bond) from Fidelity. On July 2, 2002, plaintiff filed a notice of lien for public improvement (mechanic's lien) setting forth that payment under its subcontract with Midstate was due on December 6, 2001. On November 18, 2002, the State approved the work performed by plaintiff, and plaintiff commenced this breach of contract action on November 4, 2003 alleging that it had complied with all terms and conditions of the payment bond and that Midstate, as principal, and Fidelity, as surety, are liable for plaintiff's claim on the payment bond.
We agree with the court that plaintiff's action is time-barred. State Finance Law § 137(4)(b) provides in relevant part that “no action on a payment bond furnished pursuant to this section shall be commenced after the expiration of one year from the date on which final payment under the claimant's subcontract became due.” Here, final payment was due under the subcontract on December 6, 2001 in accordance with the terms of the mechanic's lien, and plaintiff failed to commence this action within one year thereafter. Pursuant to the decision of the Court of Appeals in Windsor Metal Fabrications v. General Acc. Ins. Co. of Am., 94 N.Y.2d 124, 128, 700 N.Y.S.2d 90, 722 N.E.2d 58, the statutory “time frame may not be extended or overridden by any provisions of the subcontract.” Thus, contrary to plaintiff's contention, the 5% retainage provision of the subcontract did not extend the date on which final payment was due until November 18, 2002, when the State approved plaintiff's work.
It is hereby ORDERED that the amended order so appealed from be and the same hereby is unanimously affirmed without costs.
MEMORANDUM:
Thank you for your feedback!
As the largest network of trusted legal brands, we help firms build authority across the platforms consumers and AI systems rely on most. Our network helps attorneys strengthen visibility, credibility, and preference where legal decisions begin.
Decided: February 03, 2006
Court: Supreme Court, Appellate Division, Fourth Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)