Charles McCOY, et al., Plaintiffs-Appellants, v. METROPOLITAN TRANSPORTATION AUTHORITY, et al., Defendants-Respondents.
Order, Supreme Court, New York County (Robert D. Lippmann, J.), entered on or about June 16, 2005, which granted summary judgment dismissing the claims against defendants Metropolitan Transit Authority and Metro North Commuter Railroad for common-law negligence and under Labor Law § 200, and denied in part plaintiffs' cross motion to amend their bill of particulars so as to allege specified Industrial Code violations for purposes of their Labor Law § 241(6) claim, modified, on the law, to the extent that plaintiffs' cross motion to amend their bill of particulars is granted in its entirety so as to permit the inclusion of allegations that defendants violated Industrial Code § 23-8.1(f)(1)(iv), § 23-8.1(f)(2)(i) and § 23-8.2(c)(3), and as so modified, affirmed, without costs.
The motion court correctly dismissed the claims against defendants Metropolitan Transit Authority and Metro North Commuter Railroad for common-law negligence and under Labor Law § 200, in view of the absence of evidence that their representatives exercised any supervisory control over the work in question (see O'Sullivan v. IDI Constr. Co., 7 N.Y.3d 805, 822 N.Y.S.2d 745, 855 N.E.2d 1159 [2006], affg. 28 A.D.3d 225, 813 N.Y.S.2d 373 [2006] ). However, it erred in limiting plaintiffs' amendment of their bill of particulars to the addition of claimed violations of Industrial Code (12 NYCRR) §§ 23-8.2(d)(1) and (2) to support their Labor Law § 241(6) claim; the claims of violations of Industrial Code § 23-8.1(f)(1)(iv), § 23-8.1(f)(2) (i) and § 23-8.2(c)(3) should have been permitted as well.
We disagree with the view that these other three proffered provisions of the Industrial Code are inapplicable to this claim as a matter of law. All three provisions in question apply to cranes hoisting loads: § 23-8.1(f)(1)(iv) requires that before a crane starts to hoist a load, the load must be “well secured and properly balanced ․ before it is lifted more than a few inches,” § 23-8.1(f)(2)(i) prohibits sudden acceleration or deceleration of a moving load during a hoisting operation, and § 23-8.2(c)(3) requires that tag or restraint lines be used when rotation or swinging of a load being hoisted by a mobile crane may create a hazard.
These provisions are not rendered inapplicable as a matter of law simply because the accident occurred while the beam was being propelled in a forward direction, having already been lifted a foot off the ground. When a crane is being used to move a large, heavy or unwieldy item from one spot to another, the term “hoisting” should not be read so narrowly as to apply only to the part of the process in which the item is being moved in an upward direction, and to preclude the part of the operation when the load, having been lifted upward, is being propelled horizontally. There is little logic to the idea that the Code would require a tag or restraint line to protect workers and others from the rotation or swinging of a load, but only when the load is being raised, and not when an already raised load is being moved horizontally.
Nor do the relied-upon cases support such a reading. In Biafora v. City of New York, 27 A.D.3d 506, 508, 811 N.Y.S.2d 764 [2006], the plaintiff was injured by a bucket that had been dragged along the ground until the cable connected to the bucket accidentally lifted it off the ground, whereupon it hit the plaintiff; the Court merely observed that under the alleged facts, any violations of the safe hoisting provisions were not a proximate cause of the accident. In Penta v. Related Cos., 286 A.D.2d 674, 675, 730 N.Y.S.2d 140 [2001], lv. denied 100 N.Y.2d 515, 769 N.Y.S.2d 201, 801 N.E.2d 422 [2003], the plaintiff was hit by a hook that swung free after a load of wood was unhooked from the crane; the Court held that Industrial Code § 23-8.1(i), which requires that moving parts of a crane have guards securely fastened in place, is inapplicable to hooks, and that § 23-8.2(c)(3), which it noted is designed to protect workers from hazards created by the horizontal movement of a load being hoisted by a crane, is inapplicable where there is no load. Neither case stands for the proposition that Code provisions that are designed to protect people from the uncontrolled movement of a load suspended from a crane only apply when the load is being moved upward.
The amendment of plaintiffs' bill of particulars therefore should have included each of the five claimed Industrial Code violations, any of which could provide a predicate for liability under Labor Law § 241(6).
Plaintiff, an employee of the general contractor, sustained serious injury when he was run over by a mobile hydraulic forklift, known as a Gradall. The machine was being used to transport a 3-foot-high, 20-foot-long steel beam from a construction area to a scrap heap. Plaintiff was walking in front of the machine steadying the right end of the beam, which was suspended about one foot off the ground, as a coworker steadied the opposite end. When the Gradall operator stopped for a traffic light, the beam rotated and plaintiff was pushed backward toward the machine. When the light turned green, the Gradall lurched forward, crushing plaintiff's legs under the front wheel.
Supreme Court correctly found that Industrial Code (12 NYCRR) § 23-8.1(f)(1)(iv) (providing that a load must be well secured and properly balanced before being hoisted more than a few inches in a sling), § 23-8.1(f)(2)(i) (prohibiting sudden acceleration or deceleration of a moving load during a hoisting operation except in an emergency) and § 23-8.2(c)(3) (requiring tag lines to be used when rotation or swinging of a load hoisted by a mobile crane may create a hazard) are inapplicable. The accident occurred when the beam was being transported, not at a time it was being hoisted (see Biafora v. City of New York, 27 A.D.3d 506, 508, 811 N.Y.S.2d 764 [2006] [violations of 12 NYCRR 23-8.1(f) and 23-8.2(c) were not proximate cause of injury resulting from cement bucket being dragged along ground by crane operator]; Penta v. Related Cos., 286 A.D.2d 674, 675, 730 N.Y.S.2d 140 [2001], lv. denied 100 N.Y.2d 515, 769 N.Y.S.2d 201, 801 N.E.2d 422 [2003] [“12 NYCRR 23-8.2(c)(3) ․ is designed to protect workers from hazards created by the horizontal movement of a load being hoisted by a Crane”] ).
I agree that Supreme Court properly declined to impose liability on the owners under Labor Law § 200. Plaintiff does not dispute that his work crew received direction concerning the manner in which work was to be performed from his employer's supervisor. “It is settled law that where the alleged defect or dangerous condition arises from the contractor's methods and the owner exercises no supervisory control over the operation, no liability attaches to the owner under the common law or under section 200 of the Labor Law” (Lombardi v. Stout, 80 N.Y.2d 290, 295, 590 N.Y.S.2d 55, 604 N.E.2d 117 [1992] ). There is no proof that representatives of the railroad site owners who monitored site safety, work progress and the impact of construction activity on railroad operations exercised any supervisory control over the methods used in transporting the beam so as to expose them to liability for plaintiff's injuries (see Comes v. New York State Elec. and Gas Corp., 82 N.Y.2d 876, 877, 609 N.Y.S.2d 168, 631 N.E.2d 110 [1993] [no evidence owner “had any input into how the steel beam was to be moved”]; Cahill v. Triborough Bridge & Tunnel Auth., 31 A.D.3d 347, 350, 819 N.Y.S.2d 732 [2006] [inspection and reporting of safety violations not supervision or control] ). Liability does not attach merely because an owner may have been aware that work was being performed in an unsafe manner (O'Sullivan v. IDI Constr. Co., 28 A.D.3d 225, 813 N.Y.S.2d 373 [2006], affd. 7 N.Y.3d 805, 822 N.Y.S.2d 745, 855 N.E.2d 1159 [2006] [presence of on-site safety manager not grounds for imposing liability]; Singh v. Black Diamonds LLC, 24 A.D.3d 138, 805 N.Y.S.2d 58 [2005] [project superintendent's conduct of regular walk-throughs, authority to stop work for unsafe conditions and inspection of plywood covering hole through which plaintiff fell insufficient to impose liability under Labor Law § 200]; see also Dennis v. City of New York, 304 A.D.2d 611, 612, 758 N.Y.S.2d 661 [2003]; Colon v. Lehrer, McGovern & Bovis, 259 A.D.2d 417, 419, 687 N.Y.S.2d 130 [1999] ). Here, the activities of the owners' representatives were confined to safety procedures, including on-site safety inspections and instruction on safe practices and methods.
Accordingly, the order should be affirmed.
All concur except TOM, J.P. and BUCKLEY, J. who dissent in part in a memorandum by TOM, J.P. as follows:
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: March 15, 2007
Court: Supreme Court, Appellate Division, First Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)