Neil TERK, Respondent, v. 40059 OWNERS CORP., Appellant.
Order entered September 25, 2000 (Debra A. James, J.) modified by denying plaintiff's cross-motion for summary judgment on the fifth cause of action; as modified, order affirmed, without costs.
Plaintiff seeks to recoup amounts previously assessed by defendant cooperative representing construction costs incurred by defendant on plaintiff's behalf for repairs to the penthouse apartment and a separate “tool room” space owned by plaintiff. Plaintiff asserts that these costs were actually attributable to repair of the building's roof and water tower, and were not properly assessed solely against him. Civil Court granted summary judgment in plaintiff's favor on the ground that defendant had forfeited its right to charge the repair expenses to plaintiff because it did not provide 30 days written notice before making the repairs. We disagree. The standard provision in the proprietary lease(s) entitled “Lessor's Right to Remedy Lessee's Defaults” (paragraph 19) does not operate as a condition precedent foreclosing recovery by the cooperative since there is no express language that “failure to provide [the] 30-day notice will result in the Lessor's inability to make repairs that it ․ deems necessary for the good of the building and its tenants” (Mariaux v. Turtle Bay Towers Corp., NYLJ, May 1, 2002, at 20, col 3 [Sup Ct., N.Y. Co.] ). Moreover, there would at least be a factual issue as to whether plaintiff, by his conduct, waived any notice requirement by failing to object until after the repairs were performed.
The itemization of repairs and expenses annexed to the opposing affidavit of defendant's counsel, even if inadmissible, sufficed to place in issue plaintiff's naked claim that the repairs in question related only to the roof and not to his premises (see generally, Zuckerman v. City of New York, 49 N.Y.2d 557, 562, 427 N.Y.S.2d 595, 404 N.E.2d 718). In this connection, we note that the delay in prosecuting the action (now 15 years old) impeded defendant's ability to oppose the summary judgment motion because of changes in the cooperative's management and board.
That part of the order which granted leave to plaintiff to serve and file a notice of trial is affirmed. Plaintiff's noncompliance with the prior order of June 29, 1999, directing that a notice of trial be filed within 30 days, did not excuse defendant from serving plaintiff with the 90-day demand required by CPLR 3216 (see, Chase v. Scavuzzo, 87 N.Y.2d 228, 638 N.Y.S.2d 587, 661 N.E.2d 1368; Boricua College v. L & T Construction Co., Inc., 294 A.D.2d 170, 742 N.Y.S.2d 228). Courts do not possess the power to dismiss an action for general delay (see, Chase v. Scavuzzo, supra, at 233, 638 N.Y.S.2d 587, 661 N.E.2d 1368). The matter should proceed to trial forthwith.
PER CURIAM.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: December 27, 2002
Court: Supreme Court, Appellate Term, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)