104 CONTRACTORS, INC., Plaintiff-Respondent, v. R.T. GOLF ASSOCIATES, L.P., R.T. Golf, Inc., Defendants-Appellants, et al., Defendants. (Appeal No. 2.)
R.T. Golf Associates, L.P. and R.T. Golf, Inc. (defendants) appeal from an amended judgment after a bench trial awarding plaintiff $92,920.88 on a mechanics' lien filed against property owned by defendants. Plaintiff subcontractor filed the mechanics' lien after defendants terminated the general contractor and required both plaintiff and the general contractor to cease all work on the job site. The lien was for site work for a golf driving range and included 9,816 cubic yards of fill dirt and 480 tons of stone for a road and building pad. Defendants contend that the amended judgment must be reversed because, at the time the lien was filed, there was nothing owed by defendants to the general contractor to which the lien could attach. We disagree.
It is well settled that the rights of a subcontractor are derivative of the rights of the general contractor and that a subcontractor's lien “must be satisfied out of funds due and owing from the owner to the general contractor” at the time the lien is filed (DiVeronica Bros. v. Basset, 213 A.D.2d 936, 937, 624 N.Y.S.2d 296; see also, Lien Law § 4[1]; Strain & Son v. Baranello & Sons, 90 A.D.2d 924, 925, 457 N.Y.S.2d 925; Bunce v. Fahey, 73 A.D.2d 632, 423 N.Y.S.2d 58).
The general contractor, defendant Michael Valle, had no formal contract with defendants but their informal arrangement provided for payments based on a cost plus percentage basis. A mechanics' lien may be based on such a cost plus percentage price (see, e.g., Fyfe v. Sound Dev. Co., 235 N.Y. 266, 269, 139 N.E. 263). Revised cost estimates were made as the project plans were revised but no ceiling price was established. Some progress payments were made during the course of the work. Supreme Court determined that, based on that informal arrangement, money became due and owing to Valle when he presented a bill for $78,528 to defendants shortly before he was discharged. We conclude that money became due and owing under this cost plus agreement when plaintiff established that defendants owed Valle for the work performed by plaintiff while Valle was the general contractor (see generally, DiVeronica Bros. v. Basset, supra, at 938, 624 N.Y.S.2d 296). The record supports the court's finding that the parties understood that cost could not be determined until the work had been performed by Valle or his subcontractors. Although defendants may not have been aware of the cost of the work being performed by plaintiff, the court found that they requested changes in the grade that required the quantity of fill used and they were aware that the work was being performed. Those findings should not be disturbed (see generally, Thoreson v. Penthouse Intl., 80 N.Y.2d 490, 495, 591 N.Y.S.2d 978, 606 N.E.2d 1369, rearg. denied 81 N.Y.2d 835, 595 N.Y.S.2d 397, 611 N.E.2d 298).
We also reject defendants' contention that the termination of Valle after completion of the work and the proposed settlement negotiated between Valle and defendants after the lien was filed precluded plaintiff's recovery on the lien. A lien becomes vested upon filing and subsequent failure to perform does not preclude or reduce recovery (see, Rukeyser v. Fountain & Choate, 185 App.Div. 263, 267-268, 173 N.Y.S. 21; see also, Upton Co. v. Flynn, 169 App.Div. 79, 81-82, 154 N.Y.S. 725, affd. 218 N.Y. 674, 113 N.E. 1067; Foshay v. Robinson, 137 N.Y. 134, 136-137, 32 N.E. 1041). We need not consider the effect of settlement because the record does not indicate that a settlement agreement was actually reached.
The amended judgment of foreclosure, entered November 3, 1998, cannot be affected by an order granting a default judgment to defendants against Valle dated December 17, 1998. “It is settled law that a trial court cannot modify or amend an error in substance affecting a judgment. Those errors may be corrected only by appeal or by vacating the judgment” (Szabo v. Szabo, 71 A.D.2d 32, 35, 421 N.Y.S.2d 500), and here the court did not vacate the judgment.
Amended judgment unanimously affirmed with costs.
MEMORANDUM:
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: March 29, 2000
Court: Supreme Court, Appellate Division, Fourth Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)