GALS, INC., Plaintiff-Appellant, v. GEMMA CONSTRUCTION COMPANY, INC., et al., Defendants, American Home Assurance Company, et al., Defendants-Respondents.
Order, Supreme Court, New York County (Karla Moskowitz, J.), entered August 18, 2003, which, in an action by a subcontractor to recover damages for delay, overhead and lost profits allegedly sustained on a public improvement project, insofar as appealed from as limited by the briefs, granted defendant surety's motion for summary judgment dismissing the complaint as against it, unanimously affirmed, without costs.
Plaintiff's claim for delay damages is based on the five-month period it was bound to remain on “standby,” furnishing materials, equipment and manpower to the site, while a stop work order issued by the prime contractor was in effect. This claim was properly dismissed as precluded by the release that plaintiff thereafter gave defendant “for labor, materials and/or equipment supplied to the Project prior to the date of this Assignment or Release, except for Releasor's claim for costs/overhead/profit on deleted work [and certain other claims not in issue]” (see Rocanova v. Equitable Life Assur. Socy., 83 N.Y.2d 603, 616, 612 N.Y.S.2d 339, 634 N.E.2d 940 [1994] ). If plaintiff intended to reserve its claim for delay damages, it should have included that claim in the release as another exception. We would add that plaintiff's subcontract also plainly precludes delay damages.
Plaintiff's claims for overhead and lost profits are based on the prime contractor's deletion of the major portion of plaintiff's subcontract at or about the time it lifted the stop work order. These claims were properly dismissed as precluded by defendant's payment bond, which covers “[m]aterials and supplies (whether incorporated in the permanent construction work or not), as well as reams, fuels, oils, implements or machinery furnished, used or consumed by said Principal or any Subcontractor [on the site].” Placement of a comma after, rather than before, the word “machinery” discloses a clear intent to cover only labor that plaintiff actually performed at the site, and materials and supplies that it actually “used” at the site, and not labor, materials and supplies that it merely “furnished” to the site. Such a result is in accord with well-established law that a labor and material bond does not generally cover lost profits (see QDR Consultants & Dev. Corp. v. Colonia Ins. Co., 251 A.D.2d 641, 643, 675 N.Y.S.2d 117 [1998], lv. denied 92 N.Y.2d 814, 681 N.Y.S.2d 475, 704 N.E.2d 228 [1998] ).
We have considered plaintiff's claim of bad faith and find it to be without merit.
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: October 28, 2004
Court: Supreme Court, Appellate Division, First Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)