HILTI, INC., Respondent, v. SOVEREIGN BUILDING CORP., Defendant, Trataros Construction, Inc., et al., Appellants.
Order unanimously modified by vacating the finding that the “invoices were part of a continuing order on the contract” and the conclusion that the written notice of claim and the institution of the action regarding all the invoices were timely as a matter of law; as so modified, affirmed without costs.
The State Finance Law provides that the prime contractor of construction work on a public improvement project shall furnish a “bond guaranteeing prompt payment of moneys due to all persons furnishing labor or materials to the contractor or his subcontractors in the prosecution of the work provided for in such contract” (State Finance Law 137[1] ).
Section 137(3) provides, as a prerequisite to action on a payment bond, a written notice to the prime contractor. In pertinent part, that section reads:
“a person having a direct contractual relationship with a subcontractor of the contractor furnishing the payment bond but no contractual relationship express or implied with such contractor shall not have a right of action upon the bond unless he shall have given written notice to such contractor within one hundred twenty days from the date on which the last of the labor was performed or the last of the material was furnished, for which his claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or for whom the labor was performed.”
A “claim” made under the State Finance Law or the Miller Act upon which it was based (40 USC 270a et seq.) must be made pursuant to an underlying contract. As noted above, where claims are based upon a single contract for materials furnished, written notice of the claim must be made within 120 days from the date on which the supplier furnished or supplied the last of the material for the underlying contract (see, United States ex rel. Robert DeFilippis Crane Serv., Inc. v. William L. Crow Const. Co., 826 F.Supp. 647). However, where claims are based on a series of contracts, a written notice of the claim must be made within 120 days from the date on which the supplier furnished or supplied the last of the material for each of the underlying contracts (see e.g., United States v. National Union Fire Insurance Co. of Pittsburgh, Pa., 1999 WL 294730; United States ex rel. Robert DeFilippis Crane Serv., Inc. v. William L. Crow Const. Co., supra ). The question, therefore, becomes whether the contract at issue is a single contract or a series of contracts. “Whether a contract is a single contract or a series of contracts is determined by the intent of the parties, viewed in light of the surrounding circumstances” (United States v. National Union Fire Insurance Co. of Pittsburgh, Pa., supra ).
Here, in opposition to the defendants-appellants' motion for summary judgment in which they contended that there were a series of contracts and plaintiff failed to give timely written notices of claim for each, the plaintiff submitted proof which suggested that the parties intended to have the transactions serve as a single contract and, thus, the one notice of claim, which was filed within 120 days of the date the last of the material was furnished, was sufficient. The existence of a material issue of fact in this regard renders summary judgment inappropriate (see e.g., United States ex rel. Robert DeFilippis Crane Serv., Inc. v. William L. Crow Const. Co., supra ). Accordingly, we disagree with the lower court insofar as it summarily determined that “the invoices were part of a continuing order on the contract”, and concluded that the written notice of claim and the institution of the action were timely as a matter of law.
The defendants-appellants' remaining contentions are without merit.
MEMORANDUM.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: January 29, 2001
Court: Supreme Court, Appellate Term, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)