TOWN OF AMHERST, Town of Clarence and Town of Lancaster, Respondents, v. COUNTY OF ERIE, Erie County Legislature and Nancy Naples, Erie County Comptroller, Appellants.
In March 1989 the parties entered into a real property information system consortium agreement. That agreement was terminated on December 3, 1992. In November 1994 each plaintiff commenced an action against defendants, and the actions were consolidated in February 1995. The fourth cause of action in each action asserted that defendant County of Erie breached the consortium agreement and sought monetary damages arising from that breach. In their amended answers, defendants asserted that each plaintiff had breached the consortium agreement by failing to pay amounts due under it. Defendants asserted a counterclaim against each plaintiff based on equitable recoupment. Plaintiff Town of Amherst moved, inter alia, for an order dismissing the counterclaim against it on the ground that defendants failed to comply with Town Law § 65(3) by filing a written verified claim within six months after the contract cause of action accrued. It appears from the record that the other plaintiffs joined in the motion. Supreme Court agreed with plaintiffs and dismissed the counterclaims. That was error.
Where a counterclaim “arose from the transactions, occurrences, or series of transactions or occurrences, upon which a claim asserted in the complaint depends”, CPLR 203(d) authorizes a defendant to interpose that counterclaim to the extent of the demand in the complaint notwithstanding that the counterclaim was barred at the time the complaint was interposed. Thus, a party may assert a claim for equitable recoupment even though a timely counterclaim has not or cannot be filed (see, Bendat v. Premier Broadcast Group, 175 A.D.2d 536, 538-539, 572 N.Y.S.2d 796).
Here, defendants assert counterclaims based on equitable recoupment arising from the same contract from which plaintiffs seek damages for breach of contract. Defendants concede that their counterclaims were time-barred by Town Law § 65(3) at the time the complaints were interposed and that they therefore may seek only equitable relief to mitigate any damages recovered by plaintiffs. Under those circumstances, defendants' failure to file a timely notice of claim pursuant to Town Law § 65(3) does not bar the counterclaims for equitable recoupment (see, CPLR 203[d]; Hart v. East Plaza, 62 A.D.2d 113, 117, 403 N.Y.S.2d 928, lv. dismissed 45 N.Y.2d 706, 408 N.Y.S.2d 1025, 380 N.E.2d 338; see also, Bendat v. Premier Broadcast Group, supra, at 538-539, 572 N.Y.S.2d 796). Consequently, we modify the order by denying that part of plaintiffs' motion seeking dismissal of defendants' counterclaims.
Order unanimously modified on the law and as modified affirmed without costs.
MEMORANDUM:
Thank you for your feedback!
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes visit FindLaw's Learn About the Law.
Decided: February 04, 1998
Court: Supreme Court, Appellate Division, Fourth Department, New York.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)