URBANA AT THE RESIDENCES CONDOMINIUM NO. 3 ASSOCIATION, INC., Petitioner, v. WHITE COURSE LENNAR, LLC, Lennar Homes, LLC, Raisa Krause, Carmen Orozco, Vanessa Perez, Capri Construction Corp., Crown Roofing, Horizon Windows Corp., Miami Architectural Studio, LLC, Jennifer Mallon Salman, Nodal Structures, Inc., Carlos A. Nodal, Pascual Perez & Associates, Inc., Edgardo Perez, Sunshine Windows Manufacturing, Inc., Universal World Construction, Inc., Witkin Design Group, Inc., Andrew Michael Witkins, Empire Electric Maintenance and Service, Inc., Ortega Grading, Inc., Shamrock Engineering Corp., Eric A. Shea, Southwest Plumbing Services, Inc., Dixie Landscape, LLC, South Florida Stucco & Exteriors, LLC, and Oscar Air Conditioning, Inc., Respondents.
This case arises from the construction of a residential condominium. White Course Lennar, LLC developed the condominium, and Lennar Homes, LLC served as the general contractor. Petitioner Urbana at the Residences Condominium No. 3 Association, Inc. filed suits against the developer, general contractor, designers, subcontractors, and suppliers, alleging construction defects. The developer moved to compel arbitration of the Association's claims against it. The Association agreed to arbitrate, and the trial court stayed the litigation between those parties pending resolution of the arbitration.
The Association filed an arbitration claim against the developer with the American Arbitration Association. The developer, in turn, invoked the subcontract agreements with the general contractor to demand arbitration against most of the subcontractors.
Meanwhile, litigation proceeded against the other parties. Respondents Sunshine Windows Manufacturing, Inc. and Oscar Air Conditioning, Inc. moved to stay the entire action pending the outcome of the arbitration. They contended that allowing the litigation to continue would risk splitting causes of action, produce inconsistent verdicts, duplicate discovery, and create competing deadlines. Several other defendants joined the motions. The Association opposed the requested stay. It maintained that there was no arbitration agreement between it and the subcontractors, a stay would not promote the efficient resolution of litigation, and a stay would violate its right to access of courts and due process.
After hearing argument, the trial court stayed the case pending arbitration—except as to a few parties.1 Citing Hessen v. Schimmel, 182 So. 3d 1 (Fla. 3d DCA 2015), the trial court reasoned that a temporary stay was warranted because the claims are “based on the same operative facts and are inextricably inseparable from the claims subject to arbitration.” Upon conclusion of the arbitration, the parties were to seek to return the case to active status. One order required a status conference in six months to advise the trial court as to the status of the arbitration and whether the stay should remain in place. Meanwhile, the cases were consolidated.
The Association moved for reconsideration and challenged the exclusion of a few defendants. The trial court granted reconsideration and extended the stay to those parties as well. Again, the trial court ordered a status conference in six months at which the parties will advise as to the status of the arbitration and whether a stay should remain in effect. As before, the court directed the parties to seek return of the case to active status upon the conclusion of the arbitration proceedings.
The Association seeks a writ of certiorari to quash the stay orders. It characterizes the stays as indefinite in nature, thereby denying it access to the courts, among other things. The Respondents counter that the stays are temporary, and therefore, do not inflict the irreparable harm necessary for certiorari review. Although the orders do not establish a date certain for lifting the stays, they argue that the orders require the parties to report on the arbitration's progress and whether the stays should remain in effect. They argue that the orders also contemplate the resumption of the litigation upon the arbitration's conclusion.
To obtain a writ of certiorari, a party must demonstrate a departure from the essential requirements of the law that results in material injury that cannot be corrected on plenary appeal. Reeves v. Fleetwood Homes of Fla., Inc., 889 So. 2d 812, 822 (Fla. 2004); Kilgore v. Bird, 6 So. 2d 541, 545 (Fla. 1942). “Unless the petitioner establishes irreparable harm, the court must dismiss the petition for lack of jurisdiction.” Damsky v. Univ. of Miami, 152 So. 3d 789, 792 (Fla. 3d DCA 2014). It is a condition precedent for this Court to provide relief. Jaye v. Royal Saxon, Inc., 720 So. 2d 214, 215 (Fla. 1998).
Because the challenged orders simply postpone the litigation pending arbitration rather than foreclose its resumption, the Association has failed to establish the irreparable harm necessary for certiorari review. We therefore dismiss the petition for lack of jurisdiction. See Alt. Glob. One, LLC v. Feingold, 426 So. 3d 655, 656 (Fla. 3d DCA 2026) (dismissing petition for lack of irreparable harm where the trial court only stayed proceeding pending disposition of an earlier-filed action pending in the United States District Court for the Southern District of Florida); Kazakov v. Bourlakova, 425 So. 3d 1176, 1176–77 (Fla. 3d DCA 2025) (dismissing petition for lack of irreparable harm where the trial court's order allowed the parties to lift the stay and try any remaining issues left after resolution of the international litigation); Baute v. Crenshaw, 405 So. 3d 388, 390 (Fla. 6th DCA 2023) (“Not every stay causes a party irreparable harm.”); Flaig ex rel. Palmcrest Homes of Tampa Bay, LLC v. Sullivan, 141 So. 3d 1274, 1276 (Fla. 2d DCA 2014) (“The order staying the proceedings properly provides that the ․ suit may go forward if the issues raised therein are not decided in other litigation. Any resulting delay or inconvenience to the parties would not suffice as the irreparable harm that would permit us to issue a writ of certiorari.”); Cruz v. Cooperativa De Seguros Multiples De Puerto Rico, Inc., 76 So. 3d 394, 398 (Fla. 2d DCA 2011) (“At most, the [arbitration] process delays litigation to promote an alternative method of resolution. Delay or inconvenience is insufficient to invoke certiorari review.”); Perry v. Fireman's Fund Ins. Co., 379 So. 2d 429, 430 (Fla. 2d DCA 1980) (“[A] stay simply postpones the action until the happening of some contingency.”).
Petition dismissed.
FOOTNOTES
1. After the developer filed its third-party demand for arbitration, Witkins Design Groups, Inc. and Universal World Construction successfully opposed the arbitration demand. As a result, the developers’ claims against them must be filed in civil court. They were initially excluded from the stay.
GOODEN, J.
Thank you for your feedback!
As the largest network of trusted legal brands, we help firms build authority across the platforms consumers and AI systems rely on most. Our network helps attorneys strengthen visibility, credibility, and preference where legal decisions begin.
Docket No: Nos. 3D26-1461, 3D26-1462
Decided: November 12, 2026
Court: District Court of Appeal of Florida, Third District.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Make It a Preferred Google Search Source
Add to GoogleGet help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)