Steven K. DAVIS, Plaintiff and Appellant, v. FRESNO UNIFIED SCHOOL DISTRICT et al., Defendants and Respondents.
OPINION
Plaintiff Stephen K. Davis sued defendants Fresno Unified School District (Fresno Unified or District) and Harris Construction Co., Inc. (Contractor), alleging defendants' 2012 lease-leaseback agreements for the construction of a $36 million middle school violated California's competitive bidding statutes and conflict of interest laws. Defendants argued the competitive bidding requirements did not apply because the project qualified for the exception in Education Code section 17406 (section 17406). In an earlier 2015 appeal, we concluded section 17406's exception applied to lease-leaseback agreements only if the agreements (1) were genuine leases, (2) included “a financing component for the construction of the project,” and (3) provided for the school district's “use of the newly built facilities ‘during the term of the lease.’ ” (Davis v. Fresno Unified School Dist. (2015) 237 Cal.App.4th 261, 271, review denied, Aug. 26, 2015, S227786 (Davis I).) Applying this interpretation, we concluded Davis had adequately alleged section 17406's exception did not apply and, thus, he had stated a claim for a violation of the competitive bidding statutes. (Davis I, supra, at p. 271.)
A court trial was held in 2024 on Davis's competitive bidding and conflict of interest claims. In its statement of decision, the trial court applied the interpretation of section 17406 set forth in Davis I 1 and determined the lease-leaseback agreement fell within the exception because the leases were genuine, the construction costs carried by Contractor provided Fresno Unified with a form of financing, and the new facilities were used during the term of the lease. Thus, the court concluded Davis had failed to prove a violation of the competitive bidding statutes. The court also determined Davis had failed to prove that, as a result of entering into preconstruction services agreements with Fresno Unified, Contractor was a “officer” or “employee” of Fresno Unified subject to the conflict of interest prohibition in Government Code section 1090 (section 1090). Consequently, the court denied the conflict of interest claim. Davis filed this appeal.
First, we conclude the conflict of interest claim was properly rejected. Davis has not demonstrated the trial court misapplied the legal standards used to determine when an outside advisor like Contractor is an “officer” or “employee” for purposes of section 1090. Second, we find as a matter of law that the lease-leaseback arrangement did not qualify for the exception to competitive bidding in section 17406 because the project was financed by the issuance of bonds, not by Contractor-financing. Third, the remedy for the competitive bidding violation is set forth in subdivision (d)(1) of section 17406, which was enacted in 2016 after the decision in Davis I was final. That provision states a contractor may be paid its reasonable cost of construction, excluding profit, under agreements that failed to qualify for section 17406's exception. We conclude the allowance of the contractor's reasonable cost of construction is not an unconstitutional gift. (Cal. Const., art. XVI, § 16.) We also conclude Davis has not shown the trial court abused its discretion or committed legal or factual error when it included overhead costs as part of the reasonable cost of the services provided. Based on the court's finding that Contractor's net profit on the project was $236,129, that is the amount Contractor must refund to Fresno Unified.
We therefore reverse the judgment and direct the trial court to enter a modified judgment requiring Contractor to disgorge its profit.
FACTS
Sometime around 2006 through 2008, Fresno Unified initiated preparation of a facilities master plan—that is, a long-range plan for its facilities that included a needs assessment evaluating the suitability of its schools for student's educational needs. The plan was created by an outside firm. It identified major deficiencies throughout the district and the kinds of projects needed to correct the deficiencies. The Board of Education of Fresno Unified (board) approved the facilities master plan in 2009. The facilities master plan also identified areas where new construction was needed.
A major need was a middle school in southwest Fresno. Since 1978, southwest Fresno had no middle school and students from that neighborhood were transported by bus to four middle schools in other parts of Fresno. The construction of the southwest middle school—later named the Rutherford B. Gaston Sr. Middle School (Gaston Project)—was an important part of the facilities master plan.
Bonds
In March 2001, voters within the school district approved General Obligations Bond Measure K authorizing Fresno Unified to sell $199 million in bonds to fund the acquisition, construction, maintenance, and renovation of school facilities. In November 2010, after the board approved the facilities master plan, voters approved General Obligation Bond Measure Q authorizing Fresno Unified to sell $280 million in bonds to fund the acquisition, construction, maintenance, and renovation of school facilities. Both measures authorized an ad valorem tax on taxable property within the school district to fund Fresno Unified's payment obligations under the bonds.
Board Communications—Project Delivery Methods
In December 2010 and January 2011, after the approval of Measure Q, Fresno Unified's Deputy Superintendent Ruth F. Quinto prepared, and Superintendent Michael H. Hanson approved and signed, a series of “board communications” to the members of Fresno Unified's Board of Education (board) providing information about the methods for completing facilities projects. Quinto testified that, as soon as the bond measure passed, the superintendent wanted to begin educating board members about how Fresno Unified could most effectively provide for the construction of its school projects and, thus, avoid surprises as Fresno Unified moved forward with different construction delivery methods.
The first of these board communications, “BC No. A.1,” included as attachments two chapters from the Association of California Construction Managers (ACCM) Project Delivery Handbook titled “What is Construction Management?” and “What is Agency Construction Management?” The board communication described future topics as “Project Delivery Overview” and the three basic project delivery methods or models: (1) traditional design-bid-build, (2) construction manager at risk, and (3) lease-leaseback.
Subsequent board communications addressed the three delivery methods and provided chapters from the ACCM handbook describing each method. The three-page chapter addressing the lease-leaseback method stated it involved the selection of a developer-contractor to develop a new building or improvements on property the district owned, followed by the simultaneous execution of “a Site Lease of the property giving the [developer-contractor] the right to develop the project and a Facilities Lease giving it the obligation to develop the project and to lease the improvements and the site back to the District, with the District owning the improvements when the lease expires.” The description also stated that different school districts and their attorneys had taken different approaches to financing (if any), selection of the developer-contractor, lease terms, and the methods for selecting trade contractors. It asserted this flexibility was a primary attraction of the lease-leaseback method. Next, the description stated:
“Preconstruction work by the Developer-Contractor up to the time of signing of leases is sometimes conducted under a Preliminary Services Agreement, although some attorneys draft leases that are signed immediately and then amended as design and pricing are developed.
“Some attorneys draft leases providing for pre-construction services, even design responsibility, with language that calls for an amendment to give approval for construction to proceed including setting the date of completion and the Guaranteed Maximum Price.”
The ACCM handbook's description stated that “close coordination with a law firm is critical” due to political sensitivities, the preparation of two additional contracts (i.e., the lease and leaseback), and the “decisions about the extent or terms of any financing required.” In addition, it stated: “An attorney's advice is also necessary to decide whether a Validation process is advisable. This is a legal proceeding recommended by some attorneys to obtain court approval of the terms of the lease.”2
Request for Qualifications
After informing the board about the lease-leaseback delivery method, Fresno Unified's next step was to identify construction firms capable of completing school facilities projects using that delivery method. In March 2011, Fresno Unified published a request for qualifications 3 titled “RFQ No. 110327, Lease Leaseback Services” in the Fresno Bee newspaper and sent fax transmissions to various third parties. RFQ No. 110327's introduction stated Fresno Unified was “requesting ‘statements of qualifications’ from business entities experienced in the Lease Leaseback (LLB) public project delivery method, or business entities that can demonstrate their competence and ability to complete a public works project using the lease-leaseback delivery method.” The request stated Fresno Unified would evaluate and qualify the firms that best met the District's needs for future projects based on 16 listed factors and other considerations it deemed relevant. The factors included “expertise in finance and funding issues” and experience, expertise, and knowledge of the lease-leaseback process.
RFQ No. 110327 split the description of the anticipated scope of services into two categories: (1) assisting with project planning services and (2) construction and post-construction services. The planning services included cost estimating and value review; expedited design reviews that would generate proposed modifications; preparing a report to Fresno Unified with recommendation for maintaining project budget; development of a guaranteed maximum price acceptable to Fresno Unified; negotiating lease-leaseback contracts with Fresno Unified; bidding the work with a minimum of three bids for each trade and with input from Fresno Unified; identifying and obtaining will-serve letters from all utilities serving the site; and preparing a critical path method schedule on Primavera or other approved software. The request also stated:
“A selected LLB entity for a Project may also perform design/constructability review and value engineering. If the District proceeds with the Construction Phase of a Project, the selected LLB entity will enter into appropriate Site and Facilities Lease Agreements and related Construction Provisions, and may contract with separate trade contractors to perform the various trades comprising the entire Scope of Work.”
On March 18, 2011, after the newspaper notices had been published, Superintendent Hanson approved and signed a board communication “to inform the Board that the district is requesting qualification statements for lease-leaseback (LLB) services for future district facilities projects.” The board communication stated the deadline to respond was April 6, 2011, and, in accordance with best business practices, a pre-RFQ conference for interested firms would be held two weeks before the deadline. On March 31, 2011, after the conference, Fresno Unified issued an addendum to RFQ No. 110327 explaining that the statement of qualifications should be limited to 30 pages and advising that firms approved would remain qualified for a three-year period
Twenty-four contractors responded to the request. FUSD created a five-person committee to individually score the contractors based on nine criteria. After the scores were tabulated, Contractor Harris was ranked first, David A. Bush, Inc. was ranked second, and plaintiff's firm, Davis Moreno Construction, Inc., was ranked 14th.
On May 17, 2011, Fresno Unified staff sent all firms that had responded to RFQ No. 110327 an alphabetical list of the 14 contractors that staff would recommend the board approve at its May 25, 2011 meeting. Contractor was on the list and Davis Moreno Construction, Inc. was not. The agenda item prepared for the board meeting stated “staff recommends approval of the following fourteen (14) respondents to provide lease-leaseback services, on an as-needed basis, for a three (3) year period.” The agenda item also stated the recommended approval would have no financial impact on Fresno Unified because funding would be established on a project-by-project basis. Fresno Unified's board communication for that agenda item explained that approval of the recommendation would establish a pool of “qualified contractors to provide lease-leaseback services to the district for new construction and modernization projects when it is determined that this method is appropriate for the particular project”; the list would allow staff to negotiate a project with any qualified contractor; and all agreements for lease-leaseback services would require board approval. A readily apparent implication of the board communication was that any board member who disagreed with Fresno Unified's use of the lease-leaseback delivery method should vote against establishing a pool of contractors qualified to provide construction services under that method.
At the May 25, 2011 meeting, the board approved the recommended list and, thus, qualified those contractors pursuant to RFQ No. 110327. No contractor challenged the scoring process used or the board's approval of the 14 firms. The trial court stated it received no evidence suggesting the “selection process was infirm or conflicted in any manner.” The court specifically found that Contractor was not involved in the issuance of RFQ No. 110327.
Lease-Leaseback Projects
Before setting forth details about the Gaston Project, we describe Fresno Unified's use of the lease-leaseback delivery method for other projects. The first lease-leaseback project was approved by the board on August 10, 2011. The documents used were titled “Site Lease,” “Facilities Lease,” and “Construction Provisions.” The contractor was Lewis C. Nelson and Sons; the project was the construction of Vang Pao Elementary School; the contract amount was almost $16 million; and the source of funds was Measure K. In total, the board voted 25 times to award lease-leaseback projects to contractors that had been qualified under RFQ No. 110327. The last lease-leaseback project was the $5,550,000 Hoover High School Aquatic Center approved by the board on October 15, 2014. The contract was awarded to Bush Construction, Inc. and funded by Measure Q. Nine of Fresno Unified's 25 lease-leaseback projects were awarded to Contractor.
To design and prepare the plans and specifications for the 25 lease-leaseback projects, Fresno Unified used architectural firms that had been prequalified. A majority of the lease-leaseback projects involved the use of preconstruction services agreements, which Fresno Unified awarded with the intent that the contractor performing those services would build the project. That intent was implemented in all Fresno Unified's projects that used a preconstruction services agreement.
On October 13, 2011, Fresno Unified sold approximately $55.5 million in “Series G” general obligations bonds pursuant to Measure K and approximately $50.4 million in “Series B” general obligation bonds pursuant to Measure Q. Fresno Unified secured the indebtedness by pledging receipts from certain levies of ad valorem taxes on real property within the district.
Gaston Project
Fresno Unified retained Darden Architects to draft the Gaston Project's plans and specifications and to act as the architect of record. Next, Fresno Unified and Contractor entered into a “PRE CONSTRUCTION SERVICES AGREEMENT” for the Gaston Project stating the agreement was effective as of February 10, 2012.4 Deputy Superintendent Quinto's signature on the agreement was dated February 28, 2012. The preconstruction services included plan and design review, value engineering, schedule preparation, and other services. In a recital titled “Compensation,” the agreement stated: “In return for District's selection of Contractor to construct the Project, the services rendered [under this preconstruction services agreement] shall be performed at no cost to the District. However, should the District utilize another contractor to construct the Project, the District shall pay and Contractor shall receive as full compensation for all Services contemplated ․ the total sum of Five Thousand Dollars.” (Italics added.) That amount was below the threshold requiring the approval of Fresno Unified's board and, as a result, the board did not vote on the award of the preconstruction services agreement to Contractor. Before entering into the preconstruction services agreement, Fresno Unified's staff considered whether to ask other contractors to construct the entirety of the Gaston Project. When Fresno Unified selected Contractor from among the 14 contractors qualified under RFQ No. 110327, the mutual expectation and intent was that Contractor would bring the Gaston Project to completion, provided the board approved the lease-leaseback agreements.
On March 2, 2012, three days after Quinto signed the preconstruction services agreement, Contractor received the construction plans and specifications for the Gaston Project prepared by Darden Architects. Contractor began its review and the scheduling of meetings with specific trades to discuss ideas on enhancing the schedule, constructability, estimate and value engineering.5
During the preconstruction review, Fresno Unified, with input from Darden Architects and Contractor, decided to divide the Gaston Project into two phases to allow separate submissions of construction drawings to the Division of State Architect (DSA). The phase 1 site work included demolition of Carver Academy, construction of a flood control basin, off-site landscaping and soil remediation, below ground electrical and plumbing work, and sidewalks. The DSA could review and approve the plans for the first phase more quickly than plans for the entire project and, thus, the work on the first phase could begin before DSA completed its review of the plans for the second phase—construction of the buildings. Doug Reitz managed the preconstruction part of the Gaston Project for Contractor. He testified that splitting the project into phases instead of waiting for DSA approval of the entire project reduced the project's timeline by three to five months.
In April 2012, Contractor issued a bid package soliciting bids from subcontractors for the site work (demolition, abatement, grading, underground utilities) and off-site work (concrete, landscaping). On May 17, 2012, DSA approved Darden Architects' plans and specifications for the first phase of the Gaston Project, which included the site improvements, outdoor athletic fields and courts, and marquee sign.
Phase 1 Lease-Leaseback
The agenda for the May 23, 2012 board meeting included items A-9 and A-10, which were labeled “ADOPT Resolution 11-21, Authorizing the Execution of Lease-leaseback Agreements (Site Lease and Facilities Lease with Construction Provisions) for Construction of Rutherford B. Gaston, Sr. Middle School, Phase I (On-Site /Off-Site Work)” and “APPROVE Pre-Construction Services Agreement for Structural Steel Detailing Professional Services for Rutherford B. Gaston, Sr. Middle School,” respectively. (Boldface omitted.) Item A-9 described the work included in phase 1, stated approval of the resolution would allow that work to begin, identified the maximum guaranteed price ($5,277,469), and stated the superintendent recommended approval. It also stated: “Fiscal Impact: Sufficient funds of $5,277,469 are available in the 2011/2012 Measure K budget.” Item A-10 stated approval of the preconstruction services agreement relating to structural steel was “recommended at this time due to the anticipated long lead time to procure and fabricate the structural steel.” It also stated: “Fiscal Impact: Sufficient funds of $375,300 are available in the 2011/2012 Measure K budget.”
On May 20, 2012, Superintendent Hanson signed a board communication numbered “AS.1” to provide the board additional information on the Gaston Project and agenda items A-9 and A-10. The board communication stated that phase 1 covered only on-site and off-site work for the Gaston Project, not construction of the buildings, and explained the reasons for dividing the project into two phases. It stated that approvals were being sought for individual components of the overall project, rather than just one construction agreement, to “accelerate construction of this challenging project.” It stated the actual procurement and fabrication of steel would be included in the scope of work for phase 2 of the Gaston Project and the lease-leaseback agreements for phase 2 would “be recommended to the Board in the next few months.”
At its May 23, 2012 meeting, the board adopted a resolution authorizing the lease-leaseback agreements for phase 1 of the Gaston Project with a guaranteed maximum price of $5,277,469. The vote was 8-0 with one member absent. A clause in the resolution addressed financing by stating: “WHEREAS, in order to ensure that moneys sufficient to pay all costs will be available for the Project, the District desires to appropriate funds for the Project from its current fiscal year as provided in the Facilities Lease.” The board also approved Fresno Unified entering into the preconstruction service agreement with Contractor for structural steel detailing. The proposed preconstruction services agreement for structural steel detailing stated Contractor would “provide detailed plans, drawings and other documents for the ultimate fabrication and erection of steel members to be used in the construction of the [Gaston] Project” in exchange for $375,300.
The day after the board meeting, Fresno Unified issued a notice of award letter to Contractor stating the board had approved the phase 1 agreements for a final guaranteed maximum price of $5,277,469, which included contingencies of $435,753. The site lease and facilities lease (with incorporated construction provisions) executed by Fresno Unified and Contractor were dated as of May 24, 2012.
Phase 2 Lease-Leaseback
On August 8, 2012, DSA approved the plans for construction of phase 2 of the Gaston Project consisting of an administrative/classroom/library/music/science/kitchen building, a gymnasium and shower-locker building, and a mechanical building.
On September 24, 2012, Fresno Unified sent a notice of intent letter to Contractor requesting it to execute and return the proposed site lease and facilities lease for phase 2 of the Gaston Project in advance of the board's anticipated approval of the agreements at its September 26, 2012 meeting. The agenda for the board meeting included item B-11 describing Resolution 12-01, which would authorize the execution of the lease-leaseback agreements for phase 2 of the Gaston Project at a guaranteed maximum price of $36,702,876. Item B-11 stated the superintendent recommended adoption and also addressed the fiscal impact by stating: “Sufficient funds of $36,702,876 are available in the 2012/2013 Measure K and Measure Q budgets.”
At the September 26, 2012 meeting, the board adopted Resolution 12-01 by a vote of 6-0, with two members absent. The next day, Fresno Unified sent Contractor a notice of award letter and a notice to proceed letter. The notice of award stated the board had approved the phase 2 agreements for a final guaranteed maximum price of $36,702,876 that included owner-controlled contingencies of $1,938,292. It also stated Contractor was required to provide certain documents within 10 days, including executed performance and payment bonds, a certificate of insurance, certificate of workers' compensation, a completed emergency contact information form, a designation of subcontractors form listing agreed subcontractors, and executed escrow agreements if Contractor desired to use an escrow account.
The eight-page site lease for phase 2 of the Gaston Project was dated as of September 27, 2012 (Site Lease). Under its terms, Fresno Unified leased the project site to Contractor for $1 in rent for a term coinciding with the term of the facilities lease. Section 6.1 of the Site Lease stated: “Title to all improvements made on the Site during the term hereof shall vest subject to the terms of the Facilities Lease.”
The 15-page facilities lease for phase 2 of the Gaston Project also was dated as of September 27, 2012 (Facilities Lease). Under its terms, Contractor agreed to cause the project to be constructed in accordance with the DSA approved plans and specification and the “Construction Provisions for the Project” attached to the Facilities Lease (Construction Provisions). Contractor, as sublessor, subleased the project and the site to Fresno Unified, as sublessee, for a term ending “on the completion of the Project and payment of the last Lease Payment, as provided in the Lease Payment Schedule.”6 That schedule, Exhibit C to the Facilities Lease, stated Fresno Unified “shall make Lease Payments ․ in conformance with and subject to the terms and conditions for payments for the Project as set forth in the Construction Provisions – Exhibit D.” The Construction Provisions required monthly progress payments for the construction services rendered, with a five percent retention pending the acceptance of the project and recordation of a notice of completion. The Construction Provisions also stated that the guaranteed maximum price included $1,000 rental/lease payments that could be prepaid or paid monthly by Fresno Unified during the course of construction. The Construction Provisions allowed Contractor until May 15, 2014, to complete the project, which was 595 days after the notice to proceed.
The Facilities Lease stated the parties understood and intended that Fresno Unified's payment obligations constituted a current expense and “shall not in any way be construed to be a debt of [Fresno Unified] in contravention of any applicable constitutional or statutory limitation or requirement concerning the creation of indebtedness.” It also stated Fresno Unified “has appropriated that portion of the Guaranteed Maximum Price to be earned during the current fiscal year from [Fresno Unified's] current fiscal year and/or State funds to be received during the [Fresno Unified's] current fiscal year, and has segregated or will segregate such funds in a separate account to be utilized solely for Lease Payments. [Fresno Unified] will do so for each fiscal year during which the Project is to be constructed or Lease Payments are to be made.”
To receive monthly payments for construction services rendered, Contractor submitted an “APPLICATION AND CERTIFICATION FOR PAYMENT” that included the total sum of the work completed to date and the amount of the current payment due. The applications include an architect's certificate for payment in which the architect certified the quality of work and stated Contractor was entitled to payment of the amount requested. Each monthly application was accompanied by a certificate for retention payment and two invoices.
For example, application No. 4 was signed by Contractor on February 7, 2013. It covered the period from January 1, 2013, through January 31, 2013, and stated the current payment due was $2,130,889.14. Certificate for retention payment No. 4R requested a payment of $112,152.06 be made into the escrow account at United Security Bank. Contractor's invoice Nos. 3773A and 3773B were dated January 31, 2013, and requested payment of $2,129,889.14 (i.e., the application's amount less the $1,000 lease payment) and a monthly lease payment of $1,000, respectively.
On May 29, 2014, Fresno Unified and Contractor signed a certificate of occupancy stating Fresno Unified (1) had assumed full possession 10 days earlier and (2) accepted the work on phase 1 and 2 as substantially complete. On June 7, 2014, Fresno Unified opened the middle school for an open house and tours to the public. Since June 26, 2014, Fresno Unified has continuously occupied the entirety of the middle school. In August 2014, students started attending classes there.
On November 19, 2014, an amended notice of completion identifying the punch list work completed since May 19, 2014, was recorded. The amended notice stated the work on phase 1 of the Gaston Project had been completed on September 1, 2014. On December 4, 2014, a notice of completion for phase 2 of the Gaston Project was recorded. It stated the work on phase 2 had been completed on November 13, 2014.
The final lease payment was made by a release of $65,875.44 of escrowed funds to Contractor on March 24, 2016. This release of funds occurred approximately 16 months after the notice of completion for phase 2 was recorded. In total, Fresno Unified paid Contractor $36,051,375 in connection with phase 2 of the Gaston Project.
Parties
Contractor was founded in 1914 and, since that time, has engaged in the business of construction and construction management, predominately in central California. Contractor worked on a wide variety of construction projects in both the public and private sector, developing a proficiency in the areas of education, healthcare, and dairy and food processing. In 2006, Contractor undertook its first lease-leaseback school construction project when it managed the construction of a school for Kings Canyon School District. By 2016, Contractor had been awarded many lease-leaseback contracts for the construction of schools in the region.
The parties stipulated that Davis has standing as a taxpayer to bring this action pursuant to Code of Civil Procedure section 526a. He is the president, treasurer, chief executive officer, and the majority shareholder of Davis Moreno Construction, Inc., a Fresno-based contractor that has handled construction projects for school districts and sometimes is a direct competitor of Contractor. The trial court found Davis's primary motive for pursuing this lawsuit was his and his company's financial interests, rather than providing a public benefit. In particular, the court stated Davis's request for disgorgement of the $36 million paid to Contractor, plus interest, and the absence of a request that subcontractors or suppliers disgorge payments is “evidence of Davis's true motivation, to eliminate his competitor, [Contractor].”
Before this lawsuit was filed, Davis and his company were familiar with the lease-leaseback arrangement that uses a preliminary services agreement for certain preconstruction services before the same contractor enters into lease-leaseback agreements. In November 2006, his firm entered into a nine-page “Preliminary Services Agreement” with Kerman Unified School District (KUSD) for the design and construction of a new school. The preconstruction services provided were substantially similar to the preconstruction services provided by Contractor on the Gaston Project.
In April 2007, the related KUSD lease-leaseback agreements were signed. Specifically, Davis's firm and KUSD executed a 31-page lease-leaseback agreement, a “Site Lease,” and a “Sublease Agreement” for the turn-key construction of a four-classroom building with restroom facilities at the Liberty Intermediate School. The terms of these agreements were similar to the terms of the lease-leaseback arrangement challenged in this lawsuit. Davis's firm relied on this project and two others using a lease-leaseback arrangement to show its experience with the lease-leaseback delivery method in its response to Fresno Unified's RFQ No. 110327.
The appellate record's copy of Davis's firm's response to RFQ No. 110327 does not contain the certificate described in the last paragraph of section 4 of the RFQ. That paragraph stated: “Exceptions to this RFQ – The Response shall certify that the Respondent takes no exceptions to this RFQ or any addenda.”
Davis did not challenge the lease-leaseback arrangement used for phase 1 of the Gaston Project because he intended to have his construction firm bid to perform work as a subcontractor. On July 24, 2012, Davis's firm submitted bids to perform concrete work on the Gaston Project. Davis filed this lawsuit after his firm's bid to perform concrete work was not accepted.
From June 2016 (approximately one year after Davis I) through the trial in March 2024, Fresno Unified awarded contracts to Davis's firm totaling over $224 million under the design-bid-build delivery method. At the time of trial, approximately $9.4 million in change orders had been submitted on those projects, and Davis's active (i.e., pending) contracts had a value of approximately $114 million. In contrast, Contractor was not involved in any projects awarded by Fresno Unified during that period.
PROCEEDINGS
Davis filed this lawsuit in November 2012. The operative pleading is the first amended complaint filed in March 2013. The first appeal arose from a judgment entered after the trial court sustained demurrers of Fresno Unified and Contractor to that pleading. (Davis I, supra, 237 Cal.App.4th at p. 271.) In June 2015, we reversed the judgment, concluding the first, third, and fourth causes of action stated claims for (1) violations of California's competitive bidding laws and (2) conflicts of interest. (Ibid.)
The Supreme Court denied review and remittitur was issued. Fresno Unified and Contractor answered the first amended complaint in October 2015. (Davis II, supra, 57 Cal.App.5th at p. 923.) In 2016, Fresno Unified filed a motion for judgment on the pleadings and Davis filed a motion for summary adjudication of the conflict of interest claims against Contractor. (Ibid.) The trial court denied these motions.
In May 2019, Fresno Unified filed another motion for judgment on the pleadings asserting all the claims (1) were subject to California's validations statutes and (2) were moot because the challenged contracts had been fully performed. (Davis II, supra, 57 Cal.App.5th at p. 924.) The trial court granted the motion and filed a judgment dismissing the action and awarding costs to defendants. (Ibid.)
Davis filed a second appeal, and we reversed the judgment in November 2020. We concluded (1) the first amended complaint contained both a reverse validation action and a taxpayer's action, (2) the trial court's dismissal of the reverse validation portion of the lawsuit was proper, and (3) the dismissal of the taxpayer action portion of the lawsuit was improper because it stated viable claims. (Davis II, supra, 57 Cal.App.5th at p. 945.) Those claims stated were for violations of California's competitive bidding laws and for conflicts of interest prohibited by section 1090 and common law principles. (Davis II, supra, at p. 944.)
Defendants filed a petition for review, which the Supreme Court granted “to address a single question: ‘Is a lease-leaseback arrangement in which construction is financed through bond proceeds rather than by or through the builder a “contract” within the meaning of Government Code section 53511?’ ” (Davis III, supra, 14 Cal.5th at p. 678.) Had this question been answered “yes,” California's validation statutes would have applied to phase 2 of the Gaston Project and, as argued by defendants, the agreements would be deemed valid under the statutes because they had been fully performed. In April 2023, the Supreme Court answered the question in the negative, concluded California's validation statutes did not apply to the defendants' transaction, and the litigation could continue based on Davis's standing to bring a taxpayer action. As a result, the court affirmed Davis II and the matter was returned to the trial court for further proceedings. (Davis III, supra, at p. 700.)7
A six-day court trial was conducted in March and April 2024. The witnesses who testified included Davis; former Deputy Superintendent Quinto; Karin Temple, Fresno Unified's assistant superintendent for operational services in 2012; Doug Reitz, an employee of Contractor who worked on the project's preconstruction services; Michael Spencer, the president of Contractor at the time of trial and its director of business development during 2012 through 2015; Richard Spencer, Michael Spencer's father and a 50 percent owner of Contractor; and Ryan Diel, chief operating officer of Contractor at the time of trial. A week before the trial, the parties entered into a written stipulation of facts for all purposes in this case.
After the close of evidence, both sides filed written arguments along with supporting statements of facts. In August 2024, Davis filed his reply to defendants' closing argument.
In February 2025, the trial court filed a tentative statement of decision. Davis filed a request for a statement of decision, objections to the proposed statement of decision, and proposed additions. Contractor also submitted proposed additions and, 10 days later, Davis filed objections to Contractor's proposed additions.
In March 2025, the trial court issued its final statement of decision. The court determined Davis had failed to prove a violation of the competitive bidding statutes or a conflict of interest. On April 7, 2026, judgment was entered in favor of defendants. Davis timely appealed.
In May 2025, we issued an order directing the parties to address issues of statutory interpretation involving subdivision (d) of section 17406, which was added by Legislature in 2016 in response to Davis I. (See Stats. 2016, ch. 521, § 2 [Assem. Bill No. 2316].) Davis, in support of his supplemental brief, requested judicial notice of “documents obtained by the staff of Legislative Intent Service, Inc. on Assembly Bill 2316 of 2016.” We granted the unopposed request for judicial notice of the legislative history.
DISCUSSION
I. STANDARDS OF REVIEW
Context for our application of the various standards of review is established by the fundamental principles of appellate practice requiring appellate courts to presume the trial court's judgment is correct and requiring appellants to affirmatively demonstrate prejudicial error. (Denham v. Superior Court (1970) 2 Cal.3d 557, 564; Eagle Fire & Water Restoration, Inc. v. City of Dinuba (2024) 102 Cal.App.5th 448, 470.)
First, when an appellate court reviews the sufficiency of the evidence supporting a trial court's finding of fact, the fundamental question is “whether any reasonable trier of fact could have made the finding that is now challenged on appeal.” (Conservatorship of O.B. (2020) 9 Cal.5th 989, 1005.) In a civil appeal contesting the sufficiency of the evidence, “the power of an appellate court begins and ends with a determination as to whether there is any substantial evidence, contradicted or uncontradicted,” to support the challenged findings. (Crawford v. Southern Pacific Co. (1935) 3 Cal.2d 427, 429; Brewer v. Murphy (2008) 161 Cal.App.4th 928, 936 (Brewer).) Under the substantial evidence standard, appellate courts view the evidence in the light most favorable to the prevailing party, drawing every reasonable inference and resolving all conflicts in the evidence in support of the challenged findings. Evidence is “substantial” for purposes of this standard of review if it is of ponderable legal significance, reasonable in nature, credible, and of solid value. (Brewer, supra, at p. 935.)
Second, when an appellate court reviews how questions of law were resolved in the trial court's statement of decision, it conducts a de novo review. (Veiseh v Stapp (2019) 35 Cal.App.5th 1099, 1104; Brewer, supra, 161 Cal.App.4th at p. 936.) Questions of law include the proper interpretation of a statute “and the application of that interpretation to an established set of facts.” (Cleveland v. Taft Union High School District (2022) 76 Cal.App.5th 776, 803.) That set of facts includes undisputed facts and facts established by the rule, described above, that the appellate court must view the evidence in the light most favorable to the prevailing party. (Ibid.; Le Gault v. Erickson (1999) 70 Cal.App.4th 369, 372 [“ ‘It is well settled that the interpretation and application of a statutory scheme to an undisputed set of facts is a question of law ․ which is subject to de novo review on appeal.’ ”].)
Third, when reviewing a determination by the trial court that a party failed to carry its burden of proof, an appellate court must consider whether the evidence compels a finding in that party's favor as a matter of law. (Valero v. Board of Retirement of Tulare County Employees' Assn. (2012) 205 Cal.App.4th 960, 966.) In Valero, this court stated “ ‘it is misleading to characterize the failure-of-proof issue as whether substantial evidence supports the judgment.’ ” (Id. at p. 965.) Under the compelled-as-a-matter-of-law standard, the appellant's evidence must be (1) uncontradicted and unimpeached and (2) of such a character and weight as to leave no room for a judicial determination that it was insufficient to support a finding. (Ibid.; Jones v. Solgen Construction, LLC (2024) 99 Cal.App.5th 1178, 1196; Dreyer's Grand Ice Cream, Inc. v. County of Kern (2013) 218 Cal.App.4th 828, 838.)
II. CONFLICT OF INTEREST CLAIMS
Earlier in this litigation, we concluded Davis had alleged sufficient facts to state a cause of action for a violation of California's conflict of interest laws. (Davis I, supra, 237 Cal.App.4th at p. 301.) We also stated: “Ultimately, whether Davis will be able to prove Contractor violated the conflict of interest provision of ․ section 1090 will depend upon the facts established by the evidence.” (Ibid.) The trial court determined Davis has failed to prove Contractor was subject to the conflict of interest laws. We agree.
A. Statutory Text and Purpose
Section 1090, subdivision (a) provides that “state, county, district, ․ and city officers or employees shall not be financially interested in any contract made by them in their official capacity.” Section 1090 codified an established common law rule barring public officials from having a personal financial interest in the contracts they formed in their official capacities. (Davis I, supra, 237 Cal.App.4th at p. 298, citing Lexin v. Superior Court (2010) 47 Cal.4th 1050, 1072 (Lexin).) The rationale for the prohibition is that a person cannot serve two masters simultaneously. (Lexin, supra, at p. 1073.) “Where public and private interests diverge, the full and fair representation of the public interest is jeopardized.” (Ibid.)
In People v. Superior Court (Sahlolbei) (2017) 3 Cal.5th 230 (Sahlolbei), the Supreme Court stated the purpose of the common law rule and section 1090 was to protect “the actual and perceived integrity of the public fisc. As a result, liability ․ can accrue without ‘actual fraud, dishonesty, unfairness or loss to the governmental entity.’ ” (Sahlolbei, supra, at p. 239; Stigall v. City of Taft (1962) 58 Cal.2d 565, 569 (Stigall) [statute's goals include removing or limiting the possibility of any personal influence that might bear directly or indirectly on an official's decision].) This prophylactic purpose is the basis for the principle that “section 1090 should be construed broadly to ensure that the public has the official's ‘absolute loyalty and undivided allegiance.’ ” (Sahlolbei, supra, at p. 239.) When applying section 1090, courts evaluate the substance of the challenged transaction and disregard technical or formal aspects of the parties' relationship. In other words, they look behind any veil that may enshroud the parties' activities. (Sahlolbei, supra, at p. 239.)
B. Elements Establishing a Violation
The issues raised by the application of section 1090's text to Davis's conflict of interest claim include (1) whether Contractor or its personnel were government “officers or employees”; (2) whether Contractor “made” the challenged contracts in its “official capacity”; and (3) whether Contractor was “financially interested” in the contracts. (§ 1090, subd. (a); see Lexin, supra, 47 Cal.4th at p. 1074.)
The last of these elements is not disputed. The payment of over $36 million to Contractor under the leaseback contract establishes that Contractor was “financially interested in [the leaseback] contract” for purposes of section 1090, subdivision (a). (See Davis I, supra, 237 Cal.App.4th at p. 301 [allegation that Contractor agreed to build the Gaston Project for a guaranteed maximum price of $36.7 million adequately stated Contractor was financially interested in the lease-leaseback contracts].)
In addition, for purposes of this appeal, we assume without deciding that the lease-leaseback agreements were “made by” Contractor. (§ 1090, subd. (a).) In Stigall, the Supreme Court rejected a “narrow and technical interpretation of the word ‘made’ and construe[d] its statutory meaning to encompass the planning, preliminary discussions, compromises, drawing of plans and specifications and solicitation of bids, ․ which here were, in the broad sense, embodied in the making of the contract.” (Stigall, supra, 58 Cal.2d at p. 571.) Because the preconstruction services provided by Contractor impacted the project's plans and specifications and influenced the price agreed upon in the Facilities Lease, the assumption that Contractor participated in the making of the lease-leaseback agreements is reasonable.
As a result of this assumption, our analysis of the application of section 1090's text is limited to (1) whether Contractor was an “officer” or “employee” of Fresno Unified and (2) whether its participation in the making of the lease-leaseback agreements was “in [an] official capacity.”
1. Outside Advisors Can Be Officers or Employees
“Section 1090 does not define ‘officer’ or ‘employee.’ ” (Sahlolbei, supra, 3 Cal.5th at p. 234.) In Sahlolbei, the Supreme Court set forth standards for determining when outside advisors qualify as officers or employees after undertaking an historical analysis of revisions to section 1090 and related legislative materials. (Sahlolbei, supra, at pp. 236–237.) The court concluded “the Legislature understood section 1090's reference to ‘officers’ to apply to outside advisors with responsibilities for public contracting similar to those belonging to formal officers.” (Id. at p. 237.) The court also stated “that when the Legislature added the term ‘employees’ to section 1090, it similarly intended to include outside advisors with responsibilities for public contracting similar to those belonging to formal employees, notwithstanding the common law distinction between employees and independent contractors.” (Ibid.) The court also quoted with approval the Attorney General's conclusion that the Legislature, in amending section 1090 to include employees, intended to apply the conflicts of interest laws “ ‘to independent contractors who perform a public function and to require of those who serve the public temporarily the same fealty expected from permanent officers and employees.’ ” (Sahlolbei, supra, at p. 237, quoting 46 Ops.Cal.Atty.Gen. 74, 79 (1965).)
Based on its understanding of the Legislature's intent, the court rejected bright-line interpretations that would hold “all independent contractors are exempt from section 1090 liability” or, conversely, would hold “all independent contractors are covered by section 1090.” (Sahlolbei, supra, 3 Cal.5th at p. 240.) Rather, the court concluded section 1090 extended only to independent contractors who could be said to have been entrusted with transacting business on behalf of the governmental entity. (Sahlolbei, supra, at p. 240, citing Stigall, supra, 58 Cal.2d at p. 570.) The court rephrased this standard by stating that “independent contractors come within the scope of section 1090 when they have duties to engage in or advise on public contracting that they are expected to carry out on the government's behalf.” (Sahlolbei, supra, at p. 245, italics added.) The court refused “to adopt the ‘considerable influence’ standard when it comes to defining who is covered by section 1090 in the first instance.” (Ibid.)
2. The Trial Court's Decision
The statement of decision listed one of the issues presented at the trial as whether Contractor was an “officer” or “employee” of Fresno Unified and stated: “Short answer: no.” The part of the statement of decision addressing Davis's conflict of interest claim began by (1) setting forth the general requirements for establishing a violation of section 1090; (2) stating California Taxpayers Action Network v. Taber Construction, Inc. (2019) 42 Cal.App.5th 824 (Taber II) “directly addressed a contractor's 1090 conflict of interest claim”; and (3) concluding “[t]he facts in Taber II are on nearly ‘all fours’ to the instant matter.” Next, the court discussed Taber II, reiterated that “the relevant agreements are akin to those that existed in Taber II,” and found that “the evidence proved beyond a preponderance standard that there was no [section] 1090 violation in any of the actions taken or worked performed by [Contractor].” The court also referred to Davis's contention that Contractor “was an ‘officer’ or ‘employee’ of [Fresno Unified] at the time the lease-leaseback was entered into due to the preconstruction agreement[s]” and stated: “That argument was not supported by the evidence at trial.” More generally, the “CONCLUSION” of the statement of decision declared: “The Court finds that PLAINTIFFS [sic] failed in their [sic] proof burden and take nothing by way of their [sic] complaint.”
To identify the applicable standard of review, we must determine whether the trial court's rejection of the section 1090 claim should be characterized as a finding of fact or a determination that Davis failed to carry his burden of proof. Despite the trial court's statement that the evidence proved there was no section 1090 violation and its explicit finding “that the contract was negotiated at arms-length and in good faith,” we conclude the court's resolution of that claim is accurately characterized as a determination that Davis failed to carry his burden of proving Contractor was an “officer” or “employee” for purposes of section 1090. Accordingly, we review this particular failure-of-proof determination by asking whether the evidence compels a finding in Davis's favor as a matter of law. (Valero v. Board of Retirement of Tulare County Employees' Assn., supra, 205 Cal.App.4th at p. 966.) Under this standard, Davis's evidence must be (1) uncontradicted and unimpeached and (2) of such a character and weight as to leave no room for a judicial determination that it was insufficient to support a finding that Contractor was an officer or employee. (Ibid.)
3. Contractor Was Not an “Officer” or “Employee”
Our evaluation of whether the trial court erred in applying the legal standards set forth in Sahlolbei begins by considering whether the evidence compels a finding that Contractor had “duties to engage in ․ public contracting” on behalf of Fresno Unified. (Sahlolbei, supra, 3 Cal.5th at p. 245, italics added.) The parties stipulated that Contractor (1) had no authority to enter into contracts in the name of Fresno Unified; (2) had no authority to approve contracts in the name of Fresno Unified; (3) did not decide on behalf of Fresno Unified whether to enter into an agreement with Contractor to construct the Gaston Project; and (4) did not decide on behalf of Fresno Unified whether to enter into or approve the phase 2 Site Lease or Facilities Lease. These stipulated facts compel a finding that Contractor had no duty to engage in public contracting on Fresno Unified's behalf—that is, Contractor was not entrusted with transacting business on behalf of Fresno Unified. (Ibid.) To the extent Davis contends the finding-compelled-as-a-matter-of-law standard was met by the agreements Contractor made with subcontractors to complete the Gaston Project, we reject that contention because the subcontractors had contracts with and were paid by Contractor—that is, the subcontracts were made on Contractor's behalf, not on behalf of Fresno Unified.
Consequently, the question whether Contractor was an “officer” or “employee” for purposes of section 1090 is narrowed to whether Contractor had “duties to ․ advise on public contracting that [it was] expected to carry out on [Fresno Unified's] behalf.” (Sahlolbei, supra, 3 Cal.5th at p. 245, italics added.) In other words, whether Contractor was an “outside advisor[ ] with responsibilities for public contracting similar to those belonging to formal officers” or employees (Id. at p. 237) depends on whether it had a duty to act on behalf of Fresno Unified when advising on the contracts related to the Gaston Project.
Davis's appellate briefing emphasizes the advice Contractor gave Fresno Unified under the preconstruction services agreements. He refers to testimony of Assistant Superintendent Temple about recommendations from Contractor that influenced the price and timeline of the Gaston Project. Davis argues Contractor violated section 1090 “because, based on consulting and advice [Contractor] gave District pursuant to the ․ Preconstruction Services Agreements, [Contractor] participated in the making of the September 27, 2012 Lease Leaseback Agreements” for phase 2 of the Gaston Project. He also contends Contractor “was in a position to influence how much money District was going to pay [Contractor] to construct the Project since the Guaranteed Maximum Price for the construction of the Project was not set in the Lease Leaseback Agreements until they were awarded to [Contractor] by District on September 26, 2012, [citation] which was after [Contractor] performed its preconstruction services.” In Davis's view, the trial court misapplied section 1090 to the undisputed facts and, thus, we should conduct a de novo review and correct the error of law.
The weakness in Davis's appellate arguments is that they do not explicitly address all aspects of the standard for determining when an independent contractor or outside advisor is treated as an officer or employee subject to section 1090. In particular, Davis presents no arguments on the question whether Contractor was expected to act on behalf of Fresno Unified when it carried out its contractual duties to furnish preliminary design review services.
In comparison, the written closing argument defendants presented to the trial court referred to the preconstruction services provided on the project and explicitly asserted “there is no evidence that [Contractor] was transacting business on behalf of the District which the California Supreme Court requires.” Defendants then quoted the following discussion in Taber II of the school district's use of a lease-leaseback arrangement:
“In this case, however, it cannot reasonably be said that Taber was hired to engage in or advise on public contracting on behalf of the School District. The School District did not contract with Taber in the [preconstruction services agreements] for Taber to select a firm to complete the HVAC project. Rather, the School District contracted with Taber for Taber to provide preconstruction services in anticipation of Taber itself completing the HVAC project. Taber provided those services (including planning and setting specifications) in its capacity as the intended provider of construction services to the School District, not in a capacity as a de facto official of the School District.” (Taber II, 42 Cal.App.5th at p. 836.)
Accordingly, our review of the parties' arguments considers whether Davis has demonstrated Contractor's obligation or responsibilities under the preconstruction services agreements to provide advice and recommendations on constructability, value engineering, scheduling, and other matters was done on behalf of Fresno Unified rather than on behalf of itself as an independent contractor. Davis's failure to address the distinction between advising on behalf of Fresno Unified and advising on Contractor's own behalf, since the firm expected to be the construction manager and general contractor, is a reason why he has not carried the appellant's burden of demonstrating reversible error. Furthermore, the trial court made factual findings that support the determination that the advice given by Contractor was not rendered on behalf of Fresno Unified. In particular, the contract for the Gaston Project was negotiated at arm's length and in good faith and the expectation was that Contractor would negotiate a lease-leaseback arrangement for the construction of the middle school. Also, the condition that the lease-leaseback arrangement had to be approved by the board provided Fresno Unified with the options of not going forward with the project or proceeding with a different firm. That condition and the choices available to the board shows Fresno Unified was acting for itself and holding Contractor at arm's length in connection with the preconstruction services. Thus, Davis has not affirmatively demonstrated Contractor had duties or responsibilities for providing advice on the project “similar to those belonging to formal officers” or employees. (Sahlolbei, supra, 3 Cal.5th at p. 237.)
The specific arguments presented by Davis on appeal do not alter our conclusion. Those arguments do not address the principle that an outside advisor is an officer or employee only if its duty to provide advice is on behalf of the public entity. For instance, Davis contends that Contractor, “by way of the Pre-Constructions Services Agreements, was retained to and did advise District in a position by which [Contractor] could influence how District spent its money on the Lease Leaseback Agreements for the construction of the Gaston Project and that is enough to bring [Contractor] within California's conflict of interest prohibitions.” This contention fails because giving advice and having influence is not enough to satisfy the standard for being an officer or employee set forth in Sahlolbei. If giving advice were the only requirement to being an officer or employee for purposes of section 1090, all outside advisors would be deemed officers or employees. The Supreme Court has rejected such a broad interpretation of the statute. (Sahlolbei, supra, 3 Cal.5th at p. 240.)
Davis also asserts that Contractor's “ability to influence how District spent its money ․ is the trigger the Supreme Court identified as giving rise to a conflict of interest in [Sahlolbei, supra,] 3 Cal.5th 230.” Again, the ability to influence the terms of a contract does not, standing alone, establish a conflict of interest under section 1090 because (1) advice can be given and influence can be exercised at arm's length and (2) there are other aspects of the standard for being an officer or employee that must be established to trigger a violation of section 1090.
4. Official Capacity
Another reason why section 1090 does not apply to the lease-leaseback agreements is that the statute applies only if the defendant (1) participated in the making of the challenged contract (2) in the defendant's “official capacity”—that is, in his or her role as an “officer” or “employee” of the public entity. (Lexin, supra, 47 Cal.4th at p. 1074.) Here, because Contractor was not an officer or employee, it necessarily follows that Contractor's participation in the making of the lease-leaseback agreements was not “in [its] official capacity” within the meaning of section 1090.
In Sahlolbei, the high court stated the limitation of the statute's scope to contracts “made in the defendant's ‘official capacity’ [was not] an empty one. There may be instances where officials subject to section 1090 will be involved in the making of public contracts in which they benefit, but will not be liable because they were not acting in their official capacities.” (Sahlolbei, supra, 3 Cal.5th at p. 246.) As examples, the court referred to a case holding an outside attorney did not act in his official capacity when he directly renegotiated his own contract with the agency (Campagna v. City of Sanger (1996) 42 Cal.App.4th 533, 539–540) and an Attorney General's opinion concluding city firefighters who have developed a firefighting protective device could sell the device to the city's fire department without violating section 1090 if they contracted with the city solely in their private capacities. (Sahlolbei, supra, at p. 246.) In those situations, the attorney and firefighters were employed by a public entity and, thus, had an official capacity but did not make the contracts in that capacity.
Here, we have assumed Contractor participated in the making of the lease-leaseback agreements. That participation, however, was not in an “official capacity” because Contractor was not an officer or employee of Fresno Unified. Davis attempts to distinguish this case from Taber II because the contractor in that case was selected after a request for proposal and, in this case, Contractor was a firm prequalified pursuant to a request for qualifications and did not submit a request for proposal for the project. This factual distinction does not compel the finding that Contractor became an officer or employee of Fresno Unified when it entered into the preconstruction services agreements for the Gaston Project. The role of the firms in each case was similar because each firm was the contractor expected to complete the construction project and, in that capacity, the firm did not undertake duties for providing advice on the project “similar to those belonging to formal officers” or employees. (Sahlolbei, supra, 3 Cal.5th at p. 237.)
Lastly, Davis's arguments have not convinced us that Taber II was wrongly decided and that we should disagree with its analysis of section 1090. To summarize, the trial court did not err in concluding Davis failed to prove his conflict of interest claim.
III. SECTION 17406's EXCEPTION TO COMPETITIVE BIDDING
A. Historical Overview
A legal history of lease-leaseback arrangements for the construction of public works was provided by the Supreme Court in Davis III:
“The state Constitution imposes restrictions on local government debt. Specifically, such debt may not exceed the total annual income and revenues of the local entity in question without satisfying specified voter-approval requirements. (See Cal. Const., art. XVI, § 18, subd. (a).) This court held, however, in City of Los Angeles v. Offner (1942) 19 Cal.2d 483, that the cumulative amount payable under a multiyear lease is not a debt for purposes of the Constitution's debt limitation—provided, that is, that the local entity receives appropriate consideration in each year for the lease payments it makes during that year.
“In 1957, 15 years after our decision in City of Los Angeles v. Offner, supra, 19 Cal.2d 483, the Legislature enacted the provision of the Education Code that is at the heart of this proceeding, authorizing school districts to use lease-leaseback arrangements as a way of financing the construction of school facilities. (See Stats. 1957, ch. 2071, § 1, pp. 3682–3687.) The lease-leaseback provision is now codified in Education Code section 17406 ․ Under section 17406, a school district may lease its land to a builder (or some related entity) for $1 per year, and the builder then constructs a building or buildings on that land. Typically, the builder is compensated by leasing the land and the newly constructed school facilities back to the school district for a period of several years after construction is complete, receiving regular lease payments under that multiyear lease. (See Ed. Code, § 17417.) Finally, when both leases terminate, title to the land and the new facilities vests in the school district. (§ 17406.) In this way, the school district obtains costly improvements to its school facilities and pays for them over the course of many years, but it does so without entering into a debt obligation that would require voter approval. In essence, the school district shifts the financing of the construction project to the builder (or some related entity), who in order to secure that financing, is free to assign to a lender its right to receive lease payments from the school district. (See, e.g., City of Desert Hot Springs v. County of Riverside (1979) 91 Cal.App.3d 441, 444–445.) Thus, consistent with the provisions of section 17406, even though a school district may end up making payments directly to a lender, from the district's perspective, the payments are lease payments and not debt service.
“Significantly, section 17406 does not merely provide a method by which a school district can avoid the state Constitution's debt restrictions; it also allows a school district to avoid competitive bidding requirements otherwise mandated by state law. Moreover, some districts use lease-leaseback arrangements for the latter purpose alone. Under this approach, there is no multiyear leaseback of the completed project to the school district after construction is complete, and therefore there is no builder financing of the project. The lease payments by the school district compensate the builder for construction services performed during the period that the payment covers, and when the project is complete, the lease payments cease.
“The Courts of Appeal have reached conflicting decisions as to whether this manner of structuring a lease-leaseback arrangement is consistent with section 17406 (compare Davis I, supra, 237 Cal.App.4th 261, [§ 17406 applies only to builder-financed projects, not projects that are independently financed by the school district] with California Taxpayers Action Network v. Taber Construction, Inc. (2017) 12 Cal.App.5th 115 [rejecting that conclusion] and McGee v. Balfour Beatty Construction, LLC (2016) 247 Cal.App.4th 235 [same]), but that split of authority is not before us.” (Davis III, supra, 14 Cal.5th at pp. 682–684, fns. omitted, boldface added.)
With this background, we turn to section 17406's text and how it has been interpreted by the Court of Appeal.
B. Interpretation of Section 17406's Exception
The version of section 17406 in effect in 2012 8 when the phase 2 lease-leaseback agreements for the Gaston Project were signed provided:
“(a) Notwithstanding Section 17417, the governing board of a school district, without advertising for bids, may let, for a minimum rental of one dollar ($1) a year, to any person, firm, or corporation any real property that belongs to the district if the instrument by which such property is let requires the lessee therein to construct on the demised premises, or provide for the construction thereon of, a building or buildings for the use of the school district during the term thereof, and provides that title to that building shall vest in the school district at the expiration of that term. The instrument may provide for the means or methods by which that title shall vest in the school district prior to the expiration of that term, and shall contain such other terms and conditions as the governing board may deem to be in the best interest of the school district.
“(b) Any rental of property that complies with subdivision (a) shall be deemed to have thereby required the payment of adequate consideration for purposes of Section 6 of Article XVI of the California Constitution.”9
The First, Second and Fourth Districts have concluded the statute's plain language establishes “three requirements: ‘[1] the real property belong[s] to the school district, [2] the lease is for the purposes of construction, and [3] the title shall vest in the school district at the end of the lease term.’ ” (California Taxpayers Action Network v. Taber Construction, Inc., supra, 12 Cal.App.5th at p. 127 (Taber I), quoting McGee v. Balfour Beatty Construction, LLC, supra, 247 Cal.App.4th at p. 244; accord, Los Alamitos Unified School Dist. v. Howard Contracting, Inc. (2014) 229 Cal.App.4th 1222, 1227.) In contrast, our 2015 decision in Davis I disagreed with Los Alamitos's view of the statutory requirements and interpreted section 17406 as including three additional criteria. First, section 17406 required “a true lease, not simply a traditional construction contract designated as a lease by the parties.” (Davis I, supra, 237 Cal.App.4th at p. 284.) Second, based on “the primary statutory purpose of providing financing for school construction,” we concluded the lease-leaseback arrangement “must include a financing component.” (Id. at p. 285.) Third, we concluded the exception was available only if there was “a lease term during which the school district, as tenant, makes use of the newly built facilities.” (Id. at p. 289.) This requirement is based on the statutory text that refers to an “instrument” that “requires the lessee therein to construct ․ a building or buildings for the use of the school district during the term thereof,” that is, the term of the lease. (§ 17406, subd. (a), italics added.)
Applying the foregoing interpretations to Davis's first amended complaint, we concluded he adequately alleged the exception in section 17406 did not apply to the lease-leaseback arrangement on the grounds that (1) “the subject leaseback agreement was simply a traditional construction agreement and not a genuine lease,” (2) the arrangement “did not include a financing component for the construction of the project”; and (3) the arrangement did not provide for Fresno Unified to use the newly built facilities during the term of the lease. (Davis I, supra, 237 Cal.App.4th at p. 271.)
C. Law of the Case
An initial question of law is whether the statutory interpretation adopted in Davis I or the conflicting interpretation adopted in Taber I, McGee and Los Alamitos, applies in this appeal. At oral argument, counsel for Contractor asserted the trial court applied Davis I as law of the case, made the requisite findings on the three additional criteria recognized in Davis I, and argued those findings should be upheld in this appeal. We note the Supreme Court denied review in Davis I, subsequently acknowledged the split of authority on whether section 17406 “applies only to builder-financed projects, not projects that are independently financed by the school district,” and stated in Davis III the “split of authority is not before us.” (Davis III, supra, 14 Cal.5th at p. 684.) Thus, the high court has not altered the precedent established in Davis I. Consequently, we again conclude the “interpretation of ․ section 17406 adopted in Davis [I] is now law of the case” and, thus, is binding in this appeal. (Davis II, supra, 57 Cal.App.5th at p. 941, fn. 15.)
Because the law of the case doctrine applies, we need not repeat the rationale for the interpretation adopted in Davis I and explain why we continue to think Davis I was faithful to the Legislature's commands. (See generally, CRST Expedited, Inc. v. Superior Court (2025) 112 Cal.App.5th 872, 899–900 [the faithful agency doctrine of statutory interpretation]; Barrett, Substantive Canons and Faithful Agency (2010) 90 B.U. L. Rev. 109, 112 [view that federal courts function as the faithful agents of Congress].)
D. A Genuine Lease with a Financing Component
1. Trial Court's Decision
The trial court determined the lease-leaseback agreements complied with section 17406 and, as a result, were not subject to the competitive bidding statutes. The court referred to Davis I and its determination that the lease-leaseback arrangements “must include a financing component.” (Davis I, supra, 237 Cal.App.4th at p. 285.) The court noted “the Davis I decision provides no definition of the type, term, interest rate or other components of its financing condition” and found that Contractor had provided financing by acting like a bank for Fresno Unified. First, the court found that Contractor had been required to pay subcontractors numerous times before being paid by Fresno Unified and concluded that, by advancing these payments and waiting for reimbursement, Contractor provided “a form of financing.” Second, the court found that Contractor was not paid in full until it received the final lease payment on “March 24, 2016, almost two years after the District began using the school in May, 2014” and this waiting for final payment was an additional form of financing Contractor provided Fresno Unified. The court noted that in May 2014, Contractor was owed approximately $4 million; in August 2014, it was owed $2.9 million; and in November 2014, it still was owed $1.9 million.
2. The Financing Component
Here, we consider whether the phase 2 lease-leaseback arrangement entered into by Fresno Unified and Contractor included “a financing component” as required by the interpretation of section 17406 adopted in Davis I. An explicit definition of the word “financing” or the term “financing component” was not provided in Davis I.
Generally, the noun “financing” means either “[t]he act or process of raising or providing funds” or the “[f]unds that are raised or provided.” (Black's Law Dictionary (12th ed. 2024) p. 771.) Particular types of financing include “debt financing,” which is defined as “[t]he raising of funds by issuing bonds or notes or by borrowing from a financial institution,” and “equity financing,” which is “[t]he raising of funds by issuing capital securities (shares in the business) rather than [obtaining] loans or selling bonds.” (Id. at p. 772, italics added.) The broader term “outside financing” means “[t]he raising of funds by selling stocks (equity financing) or bonds (debt financing).” (Ibid.)
In Davis I, we did not set forth these basic definitions of “financing.” Rather, we described different methods for financing that school districts could use for new facilities. “The traditional method for financing new school facilities is for school districts to obtain voter approval for the issuance of general obligations bonds and then use the proceeds from the bonds to pay for the construction.” (Davis I, supra, 237 Cal.App.4th at p. 276.) We compared the “traditional method” to financing provided under a lease-leaseback arrangement in which “the builder finances the project (probably with assistance from a third party lender) and is paid over the term of the lease, which can last 40 years.” (Id. at p. 277.) We also stated:
“The leaseback, with its payment term of up to 40 years, allows a school to acquire facilities that it might not be able to pay for using other financing methods. As a result, the lease-leaseback method opened up a new source of financing for school construction—namely, private sector funding through the contractor and a third party lending money to the contractor.” (Davis I, supra, 237 Cal.App.4th at p. 279.)
Davis I proceeded to address a variation of the lease-leaseback arrangement in which “the school district pays for the construction (using local bond funds) as it progresses, with the final payment being made when construction is completed. As a result, the school district does not occupy and use the new facilities as a rent-paying tenant for a set length of time. Because the school district pays for the construction as it is completed, this alternate approach cannot be characterized as a method of financing the construction of new school facilities.” (Davis I, supra, 237 Cal.App.4th at pp. 280–281, italics added.) In other words, this variation of the lease-leaseback arrangement combines the traditional method of financing (i.e., funds raised by the sale of bonds) and the lease-leaseback method of delivery.
The foregoing variation of lease-leaseback arrangements was used for the Gaston Project. The funds that Fresno Unified used to make the progress payments were bond proceeds. Agenda item B-11 for the September 26, 2012 board meeting identified the guaranteed maximum price for phase 2 of the Gaston Project ($36,702,876) and addressed the fiscal impact of approval by stating: “Sufficient funds of $36,702,876 are available in the 2012/2013 Measure K and Measure Q budgets.” Similarly, when Deputy Superintendent Quinto was asked if Fresno Unified was using lease-leasebacks as a financing method for school construction, she testified: “Not in the traditional sense, no.” The exchange continued:
“Q. And what is the traditional sense?
“A. The traditional sense is that we were issuing bonds ․ on the open market and going to the capital market in order to indebt ourselves in the traditional manner by which school districts typically go out to the market to raise capital in order to construct school buildings.”
“Q. And so [Contractor] wasn't providing Fresno Unified any financing under phase 1 or phase 2?
“A. No, they were not.” (Boldface omitted.)
Quinto's description of her understanding of financing in the traditional sense is consistent with Davis I's description of the traditional method of financing school construction. (Davis I, supra, 237 Cal.App.4th at p. 276.)
The fact the Gaston Project was paid for with funds raised by selling bonds is further demonstrated by the one-page “Lease-Leaseback Projects OVERVEIW” prepared by Fresno Unified and referred to at trial as Exhibit 299. The overview that contains five columns: project description, contractor, board approval date, contract amount, and “Source.” Temple, Fresno Unified's assistant superintendent for operational services in 2012, testified the overview was “a list of all the lease[-]leaseback projects the District entered into, the contractor's name and the date of the board approval, the contract ․ amount and the funding source.” (Italics added.) The funding source for both phases of the Gaston Project was identified as “Measure K.” Further, Measure K or Measure Q were identified as the source for 23 of the 25 lease-leaseback projects listed in the overview. In comparison, the source for the $4.26 million Edison High School Aquatic Center was listed as “General Fund” and the source for the $1.86 million “Portable Relocation & Infrastructure 2014” project was listed as “School Facility Fees.”
We conclude that, as used in Davis I, the terms “financing” and “financing component” refer to the how the funds used to pay for the construction were raised by Fresno Unified. In particular, if Fresno Unified incurred debt to be able to pay for the construction, that debt would be regarded as the source of the project's financing.10 Applying this definition to the facts of this case, we conclude the lease-leaseback arrangement for phase 2 of the Gaston Project did not include a contractor-financing component because the construction was fully funded by proceeds raised by the sale of bonds. Because that lease-leaseback arrangement did not include a contractor-financing component, the arrangement did not meet the requirements of section 17406 and, thus, the contracts did not qualify for section 17406's exception to competitive bidding.
3. Delays in Payment Did Not Finance Part of the Project
We separately address defendants' contention that Contractor provided financing to Fresno Unified as a result of two types of delays in the payments owed to Contractor. As described in part III.D.1, ante, the trial court accepted the legal theory that delays in payment constituted “financing” and found Contractor had to wait for reimbursement of amounts paid to subcontractors and, further, Contractor was not paid in full until it received the final lease payment on March 24, 2016, almost two years after Fresno Unified began using the middle school. These findings about the timing of certain payments is supported by substantial evidence in the record. Consequently, the question considered here is not whether sufficient evidence supports the findings. Rather, the question is a legal one—whether delays in payment to Contractor constitute “financing” as that term was used in Davis I's interpretation of section 17406. We conclude they do not.
First, the delays in payment did not alter the source of the funds used to pay for the construction. The source—bond proceeds—was described by the Supreme Court's statement in Davis III that “the underlying project was fully funded by a prior sale of general obligation bonds, and payment of the debt service on the bonds was from ad valorem property taxes. Therefore, payment [of the bond indebtedness] did not depend on the lease-leaseback arrangement or even on completion of the project.” (Davis III, supra, 14 Cal.5th at p. 678, italics added.) Later, the court reiterated this point by stating:
“[T]he lease-leaseback arrangement at issue here did not involve a long-term lease that operated in practice as a financing mechanism. Rather, the cost of the District's new middle school was fully funded by the sale of general obligation bonds that preceded the lease-leaseback arrangement by nearly a year, and the lease-leaseback arrangement was to that extent analogous to an ordinary purchase contract for the acquisition of goods or services.” (Davis III, supra, 14 Cal.5th at p. 691, fn. omitted.)
In short, the funds used to pay for construction (i.e., the financing) were obtained through the sale of bonds and the delays in payment were not what caused Fresno Unified to be able to afford paying for the construction. Consequently, in the circumstances of this case, we conclude as a matter of law that the delays in payment did not constitute “financing.”
Second, that portion of the delayed payments involving the release of retainage from an escrow account did not provide any economic benefit to Fresno Unified and, thus, would not qualify as “financing” even under a broader definition of the term. “The withholding of ‘retainage’ until construction of the entire project is complete is a standard practice in the construction industry. Retainage is usually 5 or 10 percent of the amount otherwise due.” (Davis III, supra, 14 Cal.5th at p. 679, fn. 1.) Here, article 13 of the Construction Provisions was titled “PROGRESS PAYMENTS FOR CONSTRUCTION SERVICES” and set forth Fresno Unified monthly payment obligation: “Each Progress Payment shall comprise a sum equal to ninety-five percent (95%) of the value of the construction service work performed from the first through the last day of the previous month, less the aggregate of previous payment. The remaining five percent (5%) shall be withheld by the District, either in its own accounts or in accordance with the requirements of Article 15 of these Construction Provisions.” Article 15 addressed the formal acceptance of completion of the Gaston Project and also obligated Fresno Unified to “release any retention, less sums withheld pursuant to any good faith dispute relating to the Project, within thirty-five (35) days of recordation of the Notice of Completion. The release of the retention hereunder shall constitute the final Lease Payment, as provided for in the Facilities Lease.”11
Contractor elected to have the retainage held in an escrow account and, accordingly, the defendants established an escrow account—money market checking account 1413392—at United Security Bank. When Contractor submitted a monthly application for payment (accompanied by the architect's certificate verifying the progress of the work), it also presented Fresno Unified with a certificate for retention payment identifying the amount to be deposited into the escrow account at United Security Bank. Once Fresno Unified paid the retainage into an escrow account, it no longer had the benefit or the use of those funds. For instance, the interest that accrued on the escrow account was paid to Contractor. Alternatively, viewed from Contractor's perspective, Contractor did not assume the credit risk that Fresno Unified would be financially unable to make the retention payments because, as Diel testified during cross-examination, the money had been “put in a third party account for safekeeping.”
To summarize, the delays in payments experienced by Contractor on phase 2 of the Gaston Project did not provide a “financing component” as that term was used in Davis I. Therefore, the lease-leaseback arrangement for phase 2 did not qualify for section 17406's exception to competitive bidding. As a result, Davis proved the arrangement violated California's competitive bidding laws.
IV. REMEDY FOR THE COMPETITIVE BIDDING VIOLATION
A. Background
1. Disgorgement Under Prior Law
Ordinarily, statutory requirements for competitive bidding and advertising for bids before a public contract is awarded are mandatory and “a contract made without compliance with the statute is void and unenforceable as being in excess of the agency's power.” (Miller v. McKinnon (1942) 20 Cal.2d 83, 87–88.) “In general, under long-standing California law, if a public contract is declared void, a contractor may not be paid for work performed under that contract.” (Amelco Electric v. City of Thousand Oaks (2002) 27 Cal.4th 228, 234.) This harsh remedy deters violations of the competitive bidding and other requirements of public contracting statutes. Courts have justified its application by stating that “persons dealing with a public agency ‘are presumed to know the law with respect to the requirement of competitive bidding and act at their peril.’ ” (Marshall v. Pasadena Unified School Dist. (2004) 119 Cal.App.4th 1241, 1259, quoting Miller, supra, at p. 89.)
In 2003, the Legislature softened the no-payment remedy for certain situations involving competitively bid contracts by enacting Public Contract Code section 5110. (See Stats. 2003, ch. 678, § 2.) That statute provided:
“If the contract is later determined to be invalid due to a defect or defects in the competitive bidding process caused solely by the public entity, the contractor who entered into the contract with the public entity shall be entitled to be paid the reasonable cost, specifically excluding profit, of the labor, equipment, materials, and services furnished by the contractor prior to the date of the determination that the contract is invalid if all of the following conditions are met.” (Pub. Contract Code, § 5110, subd. (a), italics added.)12
The statutory conditions addressed the contractor's good faith belief the contract was valid, satisfactory performance of the work, the absence of contractor fraud in obtaining or performing the contract, and the absence of any other statutory or constitutional violation. (Pub. Contract Code, § 5110, subd. (a)(1)–(4).) “In adopting section 5110, the Legislature declared its intent that a contractor ‘may be paid the reasonable cost, specifically excluding profit, of labor, equipment, materials, and services that were rendered under a contract that was competitively bid, but subsequently determined to be invalid, in order to avoid unjust enrichment of the public entity and an unlawful taking of the contractor's property.’ (Stats. 2003, ch. 678, § 1.)” (Marshall v. Pasadena Unified School Dist., supra, 119 Cal.App.4th at p. 1260, fn. 14, italics added.) The term “unlawful taking” appears to refer to the constitutional requirement that private property may be taken for public use only when just compensation has been paid to the owner. (Cal. Const., art. I, § 19, subd. (a); see U.S. Const., 5th Amend. [“nor shall private property be taken for public use, without just compensation”].)
2. 2016 Amendment to Section 17406
Almost immediately after Davis I was final, various interested groups pursued legislation to overturn Davis I's interpretation of section 17406, as well as limiting the potential damage exposure (disgorgement of all monies received) from violating the statute. (Assem. Bill No. 975 (2015-2016 Reg. Sess.) §§ 1, 2 [as amended Aug. 18, 2015].) Eventually, in 2016, after Davis I (June 2015) and McGee (April 2016) were decided, the Legislature responded to these decisions' conflicting interpretations of section 17406 by amending section 17406. (Stats. 2016, ch. 521, § 2; see Sen. Rules Com., Off. of Sen. Floor Analyses, 3d reading analysis of Assem. Bill No. 2316 (2015–2016 Reg. Sess.) as amended Aug. 19, 2016, pp. 6–7 [discussion of court cases] (Senate Floor Analysis).) Assembly Bill No. 2316 was authored by Assemblymember Patrick O'Donnell, chair of the Assembly Education Committee.
The amendment modified and clarified the Education Code's “lease-leaseback provisions to remove the authority [from those provisions] to let such a contract without advertising for bids” and “require[d] that such a contract be awarded through a competitive process, as specified.” (Senate Floor Analysis, supra, p. 1.) Thus, the amendment did not implement one of the interpretations of section 17406 from the conflicting Court of Appeal decisions. Rather, the amendment changed the way lease-leaseback contracts could be awarded, thereby preventing further use of the controversial method employed in Los Alamitos, McGee, Taber I, and this case.
In addition, the amendment lessened the consequences of noncompliance with the former version of the statute by “provid[ing] that a contractor may be paid reasonable costs, as specified, if a court invalidates a lease-leaseback instrument entered into prior to July 1, 2015 for a school construction project, if specified conditions are met.” (Senate Floor Analysis, supra, p. 1.) Because the Site Lease and Facilities Lease were entered into in September 2012, this limitation on disgorgement was available to protect Contractor, if it met the statutory conditions.
The 2016 statutory text limiting disgorgement provided that when a court determines an instrument is invalid because it falls outside section 17406's exception to competitive bidding, “the contractor who entered into the instrument with the school district may be paid the reasonable cost, specifically excluding profit, of the labor, equipment, materials, and services furnished by the contractor before the date of the determination that the instrument is invalid,” provided that a court determined four conditions were met. (§ 17406, subd. (d)(1), italics added; cf. Pub. Con. Code, § 5110, subd. (a).) First, the contractor had to proceed with the construction based on a good faith belief the instrument was valid. (§ 17406, subd. (d)(1)(A).) Second, the school district had to determine the work performed was satisfactory and the district's determination had to be reasonable. (§ 17406, subd. (d)(1)(B).) Third, there could be no contractor fraud in obtaining or performing the work. (§ 17406, subd. (d)(1)(C).) Fourth, the instrument could “not otherwise violate state law related to the construction or leasing of public works of improvement.”13 (§ 17406, subd. (d)(1)(D).)
Subdivision (d)(2) of section 17406 places a mandatory ceiling on the payment allowed to contractors under instruments that fall outside section 17406's exception to competitive bidding:
“In no event shall payment to the contractor pursuant to this section exceed either of the following:
“(A) The contractor's costs as included in the instrument plus the cost of any approved change orders.
“(B) The lease payments made, less profit, at the point in time the instrument is determined to be invalid by a court of competent jurisdiction.” (Italics added.)
The statutory language at the center of the parties' dispute about the meaning and application of subdivision (d) of section 17406 are the terms “profit” and “reasonable cost”; the prepositional phrase “of the labor, equipment, materials, and services furnished by the contractor” that modifies or restricts the term “reasonable cost”; and the phrase “costs as included in the instrument.” (§ 17406, subd. (d)(1), (2).) These words and phrases are not defined in the article of the Education Code addressing lease-leasebacks, elsewhere in the Education Code,14 or in Public Contract Code section 5110, which was the model for section 17406's safe harbor provision. In addition, the parties have not cited any case law addressing their meaning as used in subdivision (d) of section 17406 or Public Contract Code section 5110. Consequently, this appeal presents issues of first impression regarding the proper interpretation of that statutory text.
3. The Trial Court's Decision
After the trial court issued its tentative decision, Contractor proposed adding three paragraphs addressing how the safe harbor in subdivision (d)(1) of section 17406 would have applied if Davis had established the lease-leaseback arrangement did not comply with section 17406. Davis objected to the proposed addition on the ground it was unnecessary surplusage because he was not the prevailing party in the tentative decision, Contractor was not subject to any disgorgement, and, as a result, there was no need to address the application of the section 17406's safe harbor.
The trial court rejected Davis's arguments, adopted Contractor's proposed paragraphs with minor changes, and included an introductory sentence stating that, although Davis had not met his burden of proof, the court would comment on the safe harbor provision “should the Appellate Court decide contrary to the trial court.” The court addressed the four conditions needed to qualify for the safe harbor's protection by finding Contractor met its burden of proving (1) Contractor proceeded with the good faith belief that the agreements were valid and enforceable; (2) Fresno Unified was satisfied with Contractor's performance; (3) there was no fraud by either Contractor or Fresno Unified in procuring or performing the challenged agreements; and (4) the agreements did not violate other state laws. Consequently, the court found “that the safe harbor elements were met, so that disgorgement would be limited to $236,129 in the event that” the lease-leaseback arrangement was deemed invalid because it fell outside section 17406's exception to competitive bidding. The court did not explicitly state how it interpreted subdivision (d) of section 17406 or how it arrived at the amount of $236,129.
4. Evidence of Overhead Expenses and Net Profit
The figure of $236,129 is derived from Chief Operating Officer Diel's testimony about his calculation of Contractor's net profit on phase 2 of the Gaston Project. Diel worked for Contractor as a project manager before becoming its chief operating officer in 2017. Diel testified Contractor's revenue from phase 2 of the Gaston Project was $36,051,375; its gross profit from that phase was $1,498,958; and, after deducting $1,262,829 in general and administrative expenses (i.e., indirect cost or overhead) allocated to the project, the net profit was $236,129. Diel's allocation of overhead expense to the Gaston Project used information from the parts of Contractor's redacted financial statements covering 2012, 2013 and 2014 admitted at trial as Exhibit 305.
The redacted financial statements included schedules of general and administrative expenses that listed 35 expense items or categories, eight of which had been redacted by Diel. Diel testified the redacted items might not be reasonably related to the Gaston Project and gave as examples expenses for travel, promotion, marketing, unassigned field staff, and maintenance of Contractor's self-perform equipment. The unredacted items (with the amounts) for 2013 included officers' payroll ($264,568), estimators' payroll ($395,998), office staff payroll ($420,850), payroll taxes for office employees ($148,931), employee benefits ($188,418), rent/facility ($441,048), facility maintenance ($47,375), maintenance of vehicles and office trailers ($92,810), utilities ($130,176), legal and accounting ($102,231), and computer costs ($180,540).
Contractor's general and administrative expenses for 2014 included “Bonuses” of $640,000, which Diel did not redact. When asked who received the bonuses, Diel answered: “My assumption, these were companywide bonuses. I don't know which individuals. If I was lucky, I may have received one.” When asked if everyone got the bonus and if it was shared proportionately, Diel replied: “Our bonuses have always been based on performance.”
Diel allocated a portion of Contractor's overhead expenses to the Gaston Project by performing calculations that appeared to be based on the Eichleay formula, which typically is used in federal litigation involving federal public works projects. (JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc. (2015) 243 Cal.App.4th 571, 584 (JMR Construction).) The Eichleay formula “ ‘is a method of allocating ․ home office overhead costs to a project that [has] been extended or delayed.’ ” (Ibid.) “ ‘Home office overhead costs are those that are expended for the benefit of the whole business, which by their nature cannot be attributed or charged to any particular contract.’ ” (Ibid.)
The steps in calculating the overhead expenses a contractor may recover under the Eichleay formula begin by identifying (1) the total overhead cost incurred by the firm during the contract period, (2) the billings from the delayed contract, and (3) total billings of the firm during the contract period. The total overhead cost figure is multiplied by the ratio of billings from the delayed contract to total billings of the firm during the contract. The result is the amount of overhead allocable to the contract. The underlying idea is that each dollar of the firm's revenue (i.e., billings) bears an equal portion of the overhead for the period in question. The next steps of the Eichleay formula (1) divide the overhead allocated to the contract by the days of contract performance to get to the daily contract overhead rate and (2) multiply the daily contract overhead rate times the days of government-caused delay—the result is the amount recoverable. (JMR Construction, supra, 243 Cal.App.4th at pp. 584–585, citing Wickham Contracting Co., Inc. v. Fischer (Fed.Cir. 1994) 12 F.3d 1574, 1577, fn. 3.)
Here, Diel determined the relevant contract period for phase 2 of the Gaston Project began with the issuance of the notice to proceed (Sept. 27, 2012) and ended when the work was completed (Nov. 13, 2014). As shown on Exhibit 306, he calculated Contractor's average per day revenue and average per day general and administrative expenses (i.e., overhead) for each year in the contract period—2012, 2013 and 2014—and then multiplied the number of days the contract was in effect during that year by the average daily revenue and average daily overhead expense for that year. For example, in 2012, the contract period for phase 2 of the Gaston Project covered 96 days (September 27th through December 31st) and Contractor's 2012 average daily revenue and average daily overhead were $186,932 and $8,893, respectively.15 These daily figures are multiplied by 96 days, resulting in $17,945,428 of Contractor's total revenue and $853,764 of its overhead for 2012 being allocated to the contract period.
The same calculations were performed for 2013 and 2014. When the calculations for each year were combined, Contractor's total revenue for the contract period was $217,321,223 and its total overhead for that period was $7,612,455. Because the payments on phase 2 of the Gaston Project were $36,051,375, that project generated 16.59 percent of Contractor's total revenue of $217,321,223 for the contract period. Based on the idea that each dollar of revenue should be allocated a proportionate share of the overhead expense, Diel allocated 16.59 percent of the $7,612,455 of overhead for the contract period (i.e., $1,262,829) to phase 2 of the Gaston Project. Diel subtracted the allocated overhead amount of $1,262,829 from gross profit of $1,498,958 to get a net profit of $236,129.
To summarize, in finding the appropriate disgorgement amount would be $236,129, the trial court resolved issues of law by impliedly interpreting the word “profit” used in subdivision (d)(1) of section 17406 to mean net profit, not gross profit, which is the equivalent of impliedly interpreting the phrase “reasonable cost ․ of the ․ services furnished by the contractor” to include a portion of Contractor's general and administrative expenses (i.e., overhead or indirect costs). The court resolved an issue of fact by impliedly finding that the reasonable amount of Contractor's overhead apportioned to phase 2 of the Gaston Project was $1,262,829, the amount calculated by Diel.
B. Interpreting Subdivision (d) of Section 17406
The interpretation of a statute presents questions of law subject to independent review on appeal. (See pt. I., ante.) Our role is to ascertain the intent of the Legislature so as to effectuate the purpose of the law. We begin with the statute's words and consider whether they have a plain meaning or, alternatively, are ambiguous—that is susceptible to more than one reasonable interpretation. When statutory language is ambiguous, courts select the interpretation most closely aligned with the apparent intent of the Legislature, with a view of promoting rather than defeating the general purpose of the statute and avoiding absurd consequences. (Merced Irrigation Dist. v. Superior Court (2017) 7 Cal.App.5th 916, 925.) Courts determine the apparent intent underlying ambiguous statutory language by considering that language in context and by evaluating a variety of extrinsic aids, including the ostensible objects to be achieved by the statute, the evils to be remedied, public policy, and the statute's legislative history. (Cisneros v. Department of Motor Vehicles (2024) 104 Cal.App.5th 381, 407–408.)
1. Statute's Ambiguity
On the threshold question of statutory interpretation, we conclude section 17406, subdivision (d)(1) unambiguously grants the trial court discretion in determining whether a contractor “may be paid” any of its costs, but is ambiguous about the scope of that discretion. For example, the exclusion of “profit” from the amount a contractor “may be paid” could mean either net profit or gross profit. (§ 17406, subd. (d)(1).) Similarly, the phrase “reasonable cost ․ of the labor, equipment, materials, and services furnished by the contractor” could be interpreted to encompass both direct and indirect costs or, like the interpretation requiring the disgorgement of gross profit, could permit only the payment of direct costs. (Ibid.)
2. Resolving the Ambiguity About Profit and Overhead
The legislative history for the 2016 amendment that added subdivision (d) to section 17406 does not explicitly state whether “profit” means net profit or gross profit; whether “reasonable cost” includes or excludes indirect costs (i.e., overhead); or whether “reasonable cost” is limited to direct costs. Davis notes the 19 uses of the term “any profit” in the judicially notice legislative materials. For example, staff comments in a report of the Senate Committee on Education refer to “reasonable costs (excluding any profit).” (Sen. Com. on Education, Rep. on Assem. Bill No. 2316 (2015–2016 Reg. Sess.) June 29, 2016, p. 3 (Education Committee Report).) Davis contends “any profit” encompasses gross profit and, thus, the statute precludes the payment of gross profit in all cases. Under this interpretation, the trial court would have no discretion to allow the contractor to be paid a portion of its overhead.
“Profit” means “[t]he excess of revenue over expenditures in a business transaction; GAIN.” (Black's Law Dict. (12th ed. 2024) p. 1465.) Below this general definition, Black's Law Dictionary sets forth several definitions for particular types of profit, including “gross profit” and “net profit.” Gross profit is defined as “[t]otal sales revenue less the cost of the goods sold, no adjustment being made for additional expenses and taxes.” Net profit is defined as “[t]otal sales revenue less the cost of the goods sold and all additional expenses.” (Ibid.) Here, Diel's use of “net profit” to mean “gross profit” minus general and administrative expenses (i.e., overhead or indirect costs) is consistent with these definitions.
Generally, the word “ ‘any’ ” means “ ‘of whatever kind’ ” or “ ‘without restriction.’ ” (Zabrucky v. McAdams (2005) 129 Cal.App.4th 618, 628.) “Any” is defined by Black's Law Dictionary to mean: “Some; one out of many; an indefinite number. One indiscriminately of whatever kind or quantity.” (Black's Law Dict. (6th ed. 1990) p. 94.) The dictionary acknowledges that “ ‘any’ has a diversity of meaning and may be employed to indicate ‘all’ or ‘every’ as well as ‘some’ or ‘one’ and its meaning in a given statute depends upon the context and the subject matter of the statute.” (Ibid.)
We conclude the use of “any profit” in the legislative materials provides some support for inferring “profit” should be interpreted broadly to mean gross profit because gross profit is a kind of profit. The inference would be stronger if the Legislature had included “any” or “all” in the statutory text or had explicitly resolved the question by referring to gross profit. Because the inference is not conclusive, the use of “any profit” in the legislative materials does not end our inquiry into legislative intent.
We also consider what the legislative materials said about the term “reasonable cost” or, more generally, about costs. An enrolled bill report addressed the legal impact of the 2016 amendment by stating: “This bill also specifies that contractors may recover their actual costs, in specified circumstances, if a court has invalidated a lease-leaseback contract entered into before July 1, 2015. This provision could apply to the contract invalidated in the Davis litigation.” (Enrolled Bill Rep. on Assem. Bill No. 2316 (2015–2016 Reg. Sess.), Sept. 9, 2016, p. 7, italics added.) The report also described Davis's attorney's opposition to the bill, stating that he “opposes the provision allowing contractors to recover their actually incurred reasonable costs in certain circumstances if a contract is invalidated, stating that contractors have violated conflict of interest laws and should not be given a free pass.”16 (Id. at p. 4, italics added.) Because overhead consists of expenses actually paid by a contractor, the use of the terms “actual costs” and “actually incurred reasonable costs” provides some support for the inference that the safe harbor allows contractors to be paid a portion of their overhead as part of the cost of the services furnished in performing the contract. However, like the use of “any profit,” the use of “actual costs” and “actually incurred” does not unequivocally demonstrate the Legislature intended to authorize the payment of a portion of the contractor's overhead.
Next, we consider Contractor's argument that the inquiry into legislative intent should examine statutes and judicial decisions that existed when section 17406 was amended in 2016. Contractor refers to Government Code section 16727, which restricts a public entity's use of proceeds from the sale of bonds to specified purposes including the costs of construction of capital assets. “Costs allowable under this section include costs incidentally but directly related to construction or acquisition, including, but not limited to, planning, engineering, construction management, architectural, and other design work, environmental impact reports and assessments, required mitigation expenses, appraisals, legal expenses, site acquisitions, and necessary easements.” (Gov. Code, § 16727, subd. (a).) This statute's reference to “costs incidentally but directly related to construction” does not provide a useful analogy for interpreting the text of section 17406 because the costs listed are not general and administrative expenses (i.e., indirect costs), but are “directly related to construction.” Thus, the discussion of administrative oversight work in San Lorenzo Valley Community Advocates for Responsible Education v. San Lorenzo Valley Unified School Dist. (2006) 139 Cal.App.4th 1356 and a 2004 Attorney General opinion does not address the public entity's overhead expenses, such as the cost of owning or renting its main office. Rather, the administrative costs discussed were for “ ‘monitoring contracts and project funding, overseeing construction progress, and performing overall project management and accounting that facilitates timely completion of the construction project’ ” (San Lorenzo Valley, supra, at p. 1401, quoting 87 Ops.Atty.Gen. 157, 160 (2004)), not general and administrative expenses that are regarded as indirect costs.
Contractor also refers to Government Code section 50054, which addresses the price a city or county may charge when it provides construction services or constructs public works for another agency:
“[T]he price charged for such services or construction shall be sufficient to reimburse the governmental body performing such services for the full cost thereof including labor, material, equipment costs or rentals and a reasonable allowance for overhead. In computing overhead, without limitation on other factors properly includable, there shall be allocated to the overhead cost its proportionate share of indirect labor and administrative costs.” (Italics added.)
This text shows the Legislature treated overhead as part of the cost that a governmental body may recover for construction services. The Legislature also referred to overhead in a provision of the Public Contract Code adopted in 1983 when the Legislature “created the California Uniform Construction Cost Accounting Commission.” (Pub. Contract Code, former § 21100; Stats. 1983, ch. 1054, § 1; see Stats. 1986, ch. 1019, § 40 [renumbered Pub. Contract Code § 22010].) One of the commission's duties is to recommend “uniform construction cost accounting procedures for implementation by public agencies in the performance of, or in contracting for, construction on public projects.” (Pub. Contract Code, § 22017, subd. (a).) The recommended cost accounting procedures must “be consistent with construction cost accounting procedures and reporting requirements utilized by state and federal agencies on public projects.” (Ibid.) Cities with a population under 75,000 that elect to utilize the procedures “shall assume an overhead rate equal to 20 percent of the total costs of a public project, including the costs of material, equipment, and labor.” (Pub. Contract Code, § 22017, subd. (b)(1), italics added.) Cities with a population over 75,000 “may either calculate an actual overhead rate or assume an overhead rate equal to 30 percent of the total costs of a public project.” (Id., subd. (b)(2), italics added.)
After the commission makes its recommendation, the State Controller evaluates it and either formally adopts or rejects the recommended accounting procedures. (Pub. Contract Code, § 22018.) After formal adoption, the State Controller must “promulgate the uniform procedure for all public agencies electing to participate, together with instructions for their adoption and implementation by any public agency.” (Pub. Contract Code, § 22019.) Because the accounting procedures are adopted pursuant to the Legislature's directions, we conclude those procedures provide some insight into how the Legislature views the treatment of overhead for accounting purposes.
The 2025 edition of the commission's Cost Accounting Policies and Procedures Manual (Cost Accounting Manual)17 identifies three methods that can be used when public entities elect to calculate their overhead rates. (Cost Accounting Manual, §§ 3.08, 7.01, pp. 48–49, 71.) Appendix A to the manual refers to the federal government's method of calculating overhead. Appendix B sets forth a method that allocates overhead costs as a percentage of direct labor costs. The third option is any method “satisfactory with the Commission, provided that acceptable accounting procedures are used and all administrative costs are included.” (Cost Accounting Manual, § 3.08, p. 49.) The manual describes the nature of overhead by stating: “Overhead costs cannot be identified with or charged to jobs or units of production unless some more or less arbitrary allocation basis is used.” (Ibid.; see 2 C.F.R. § 200.412 [“There is no universal rule for classifying certain costs as direct or indirect costs.”]; JMR Construction, supra, 243 Cal.App.4th at p. 584 [home office overhead costs “ ‘are expended for the benefit of the whole business [and] by their nature cannot be attributed or charged to any particular contract.’ ”].) The manual's Appendix B states:
“Overhead costs represent economic resources that are employed for common or joint purposes benefiting several end cost objectives and are not identifiable to an individual end cost objective. The challenge is to achieve an equitable allocation of overhead costs to these various end cost objectives of the public agency.” (Cost Accounting Manual, p. 79.)18
The Cost Accounting Manual also states that both the construction industry and public agencies recognize that the significant cost elements of any construction project include overhead and lists 13 overhead items, including the cost of processing payroll, data processing, facilities, and top management. (Cost Accounting Manual, § 3.08, p. 49.)
To summarize, Government Code section 50054, Public Contract Code section 22017, and the Cost Accounting Manual support the inference that the Legislature intended the reasonable cost of the services furnished on a construction project to include a reasonable portion of the contractor's overhead.
This inference is also supported by case law addressing the damages recoverable for breach of a construction contract. In Allen v. Gardner (1954) 126 Cal.App.2d 335, the general contractor on a school construction project sued a subcontractor who had agreed to furnish specially designed concrete but had delivered only a small portion of the agreed quantity. (Id. at p. 337–338.) The trial court found the subcontractor had breached the subcontract, found the replacement concrete cost the general contractor $43.02 a cubic yard, and awarded damages based on the difference between that cost and the price of $15.50 per cubic yard set in the subcontract. (Id. at p. 338.) The cost of $43.02 of each cubic yard of the replacement concrete included $5.69 for overhead, computed at 15.24 percent of the cost of the labor, equipment, cement and aggregate for each cubic yard. On appeal, the subcontractor argued there was no evidence supporting the award of overhead. (Id. at p. 344.) The court rejected this argument and concluded the method for estimating the overhead expense was appropriate. (Id. at p. 345.) Under that method, the overhead costs caused by the breach was estimated by determining “what proportion of the total business of [the general contractor] was represented by the concrete job, and [allocating] that proportion of the total overhead expenses as applicable to the concrete job.” (Ibid.) The court summarized by stating the case was “predominantly a fact case” and substantial evidence supported the fact of damage and the amount fixed in the award. (Id. at p. 346.)
Based on our consideration of the wording of subdivision (d) of section 17406, the legislative history of the bill enacting that subdivision, other statutes, the Cost Accounting Manual, and case law, we infer the Legislature did not intend to bar trial courts from allowing contractors to be paid for overhead costs allocated to the construction project. Restated using the statutory text, the Legislature intended the “reasonable cost ․ of ․ services furnished by the contractor” to include overhead. (§ 17406, subd. (d)(1).) Part of the rationale for this interpretation is that, as a practical matter, contractors could not furnish the “services” needed to complete a construction project without a home office supporting the personnel assigned to that project. Thus, it is reasonable for a portion of the contractor's overhead to be allocated to the project.
3. Scope of Discretion
Further issues of statutory interpretation involve the scope of the trial court's discretion and the types of decisions it makes in applying subdivision (d) of section 17406. First, the phrase “may be paid” and the legislative history clearly demonstrate the trial court has the discretionary authority to determine whether the contractor should be paid any of its reasonable costs of the labor, equipment, materials and services furnished. (See Education Committee Report, supra, p. 6 [recommendation that the court be given the discretion “to determine the appropriate remedy based upon the specific circumstances surrounding the [challenged] contract”].) If the court decides, in an exercise of that discretion, to allow the payment of some costs, it also has the discretion to determine which particular items of cost to include in the allowed payment.
Second, any allowance of payment under this discretionary authority is subject to the mandatory limits contained in subdivision (d)(2) of section 17406. (See Williams v. Superior Court (2017) 3 Cal.5th 531, 540 [scope of discretion always resides in the particular law being applied].) Thus, the amount the contractor is paid or allowed to retain must not exceed “[t]he contractor's costs as included in the instrument plus the cost of any approved change orders” or “[t]he lease payments made, less [net] profit” when the instrument is declared invalid by a court. (§ 17406, subd. (d)(2)(A), (B).) Here, the guaranteed maximum price for phase 2 of the Gaston Project included amounts to cover Contractor's overhead expenses and provide a profit. As a result, the limitation directly applicable in this case prohibits Contractor from retaining the profit portion of the $36 million in lease payments, which we have interpreted to mean net profit. (§ 17406, subd. (d)(2)(B).)
Third, once a trial court has, in an exercise of its discretion, decided to allow payment, its authority is limited by the modifier “reasonable” before the word cost and the prepositional phrase “of the labor, equipment, materials, and services furnished by the contractor” before the lease-leaseback arrangement is declared invalid. Stated another way, a trial court cannot allow payment of (1) an amount of a particular cost that is unreasonable or (2) a cost item that was not furnished in performing the construction. The application of the modifier “reasonable” and the prepositional phrase present the trial court with questions of fact. Accordingly, the trial court's findings of fact as to what was furnished and the reasonable value of that which was furnished are subject to review under the substantial evidence standard.
4. Method for Allocating Overhead
Another legal question presented is how to characterize the selection of a formula or method for allocating a portion of the contractor's overhead to the construction project in question. This characterization would establish the applicable standard of review. (See generally, Sierra Club v. County of Fresno (2018) 6 Cal.5th 502, 514 [under California Environmental Quality Act, an agency's choice of methodology for analyzing a potentially significant environmental impact “is amenable to substantial evidence review”].) We do not decide whether the selection of a method resolves a question of law, a question of fact, a mixed question of law and fact, or is committed to the trial court's discretion. Regardless of how the selection is characterized, we conclude the formula used by Diel and accepted by the trial court was reasonable as a matter of law, as a matter of fact, and was not arbitrary or capricious.
We agree with the statement in the Cost Accounting Manual that charging overhead costs to a job or unit of production requires the use of “some more or less arbitrary allocation basis.” (Cost Accounting Manual, § 3.08, p. 49.) The manual recognizes a variety of ways to perform that allocation. (Cost Accounting Manual, § 3.08, pp. 48–49.) Further, we have not located, and the parties have not cited, a California case adopting a particular method and rejecting all others. Thus, for purposes of section 17406, we conclude there is no single formula or method for allocating a contractor's overhead to a particular construction project.
Consequently, we consider whether the variation of the Eichleay formula used by Diel, which allocated a proportionate share of overhead expenses to each dollar of revenue from the contract period, was appropriate for this case. The Eichleay formula is generally accepted by federal courts when determining the recoverability of home office overhead as an element of damages for a government-caused delay. (See JMR Construction, supra, 243 Cal.App.4th at p. 587.) As described earlier, the foundation for determining the amount of overhead recoverable involves allocating part of the contractor's total overhead for the contract period to the contract in question. (Id. at p. 584.) That foundational amount is then converted to a daily amount and that daily amount is multiplied by the days of the government-caused delay to get the amount recoverable. (Ibid.) If this method is reasonable for determining the overhead that a project continued to incur after the contract period due to the delay, it logically follows that it also is a reasonable method for determining the foundational amount—that is, the amount of the contractor's total overhead for the contract period allocable to the contract in question. The method used by Diel also is supported by its similarities to the method used in Allen v. Gardner, supra, 126 Cal.App.2d 335 to estimate recoverable overhead. (Id. at p. 345.)
Our conclusion that the method was reasonable and appropriate in the circumstances of this case also is supported by Davis's failure to identify any alternate method of allocating overhead, much less a superior one. As a result, we conclude the trial court did not err in accepting the formula used by Diel, which allocated 16.59 percent of Contractor's general and administrative expenses for the contract period to phase 2 of the Gaston Project.
C. Application of Subdivision (d) of Section 17406
First, we consider whether the trial court abused its discretion in deciding to allow Contractor to retain all of the lease payments except its net profit. Because Contractor satisfied the four statutory conditions, that decision did not exceed to bounds of reason. (See Continental Baking Co. v. Katz (1968) 68 Cal.2d 512, 527.) Second, based on our interpretation of section 17406, subdivision (d), we conclude the trial court did not commit a legal error by limiting disgorgement to Contractor's net profit. Third, the court did not commit factual error by making findings that were not supported by substantial evidence. The testimony of Diel and the supporting exhibits qualify as substantial evidence that Contractor's net profit on phase 2 of the Gaston Project was $236,129.
D. Constitutional Prohibition of Gifts
Having resolved the issues of statutory interpretation, we turn to Davis's constitutional challenges to the safe harbor provision. Davis contends the entire $36 million paid to Contractor for phase 2 of the Gaston Project must be disgorged because section 17406's limitation of disgorgement to profit violates section 6 of article XVI of the California Constitution, which states in part:
“The Legislature shall have no power to ․ make any gift or authorize the making of any gift, of any public money or thing of value to any individual, municipal or other corporation[.]”
Courts addressing whether an appropriation of public funds constitutes a “gift” subject to this constitutional provision address “whether the funds are to be used for a ‘public’ or a ‘private’ purpose.” (County of Alameda v. Janssen (1940) 16 Cal.2d 276, 281; Paramount Unified School Dist. v. Teachers Assn. of Paramount (1994) 26 Cal.App.4th 1371, 1388.) Funds used for a “public purpose” are not a gift within the meaning of the California Constitution's gift clause. (Janssen, supra, at p. 281.) “The benefit to the state from an expenditure for a ‘public purpose’ is in the nature of consideration and the funds expended are therefore not a gift even though private persons are benefited therefrom.” (Ibid.; see Preston v. State Bd. of Equalization (2001) 25 Cal.4th 197, 225.) In the absence of a public purpose, the term “ ‘gift’ ” includes “ ‘ “all appropriations of public money for which there is no authority or enforceable claim,” ’ or which are grounded on mere moral or equitable obligations.” (West Contra Costa Unified School Dist. v. Superior Court (2024) 103 Cal.App.5th 1243, 1256.)
“The determination of what constitutes a public purpose is primarily a matter for the Legislature to determine, and its discretion will not be disturbed by the courts so long as that determination has a reasonable basis.” (County of Alameda v. Carleson (1971) 5 Cal.3d 730, 746.) “Where the Legislature makes findings, they are ‘given great weight and will be upheld unless they found to be unreasonable and arbitrary.’ [Citation.] But ‘[t]he failure to explicitly state a public purpose is not decisive. The courts may infer the public purpose from other legislation or the manner in which the legislation is enacted.’ ” (West Contra Costa Unified School Dist. v. Superior Court, supra, 103 Cal.App.5th at p. 1257.)
Here, the Legislature did not explicitly find that the payments allowed under the safe harbor created by subdivision (d)(1) of section 17406 were for a public purpose. (See Stats. 2016, ch. 521, §§ 1, 2.) However, because section 17406 addresses leases that “require[ ] the lessee therein to construct on the demised premises ․ a building or buildings for the use of the school district” (§ 17406, subd. (a)(1)), we infer the payments allowed by the safe harbor had a public purpose. Specifically, educating children provides a public benefit, when school districts provide that education they are serving a public purpose, and school districts need building to be able to perform the function of educating children. It follows that the construction of buildings for use by school districts serves a public purpose and payment for construction, which is allowed only if the school district reasonably determines the construction is satisfactory, is for the public purpose. Consequently, we conclude the safe harbor contained in subdivision (d)(1) of section 17406 is not unconstitutional, either on its face or as applied to the facts of this case.19 (See In re D.L. (2023) 93 Cal.App.5th 144, 156–157 [typically, the constitutionality of a statute may be challenged “in two ways: on its face or as applied”].)
V. COSTS
First, we address the costs incurred in this appeal. Second, we address the costs incurred in the trial court litigation.
A. Costs on Appeal
Code of Civil Procedure section 1034, subdivision (b) states: “The Judicial Council shall establish by rule allowable costs on appeal and the procedure for claiming those costs.” Generally, “the party prevailing in the Court of Appeal in a civil case ․ is entitled to costs on appeal.” (Cal Rules of Court, rule 8.278(a)(1).) When the Court of Appeal affirms a judgment without modification or reverses a judgment in its entirety, the prevailing party is clear. (Cal Rules of Court, rule 8.278(a)(2).) In contrast, where “the Court of Appeal reverses the judgment in part or modifies it, ․ the opinion must specify the award or denial of costs.” (Cal Rules of Court, rule 8.278(a)(3).) In fulfilling that mandate, the Court of Appeal may, in the interests of justice, “award or deny costs as it deems proper.” (Cal Rules of Court, rule 8.278(a)(5).) Under these provisions, this court has the discretion to determine which of the parties, if any, should be allowed to recover costs on appeal.
In exercising that discretion, we take into account defendants' success on the conflict of interest claims and the fact that the remedy on those claims would have been more extensive than just the disgorgement of net profit. (See § 17406, subd. (d)(1)(D).) Based on the partial success of this appeal, we deem it proper to award Davis 50 percent of the costs he incurred in this appeal and require him to bear the other 50 percent.
B. Costs Incurred Below
Code of Civil Procedure section 1032, subdivision (b) states: “Except as otherwise expressly provided by statute, a prevailing party is entitled as a matter of right to recover costs in any action or proceeding.” The term “prevailing party” is defined in subdivision (a)(4) of section 1032 of the Code of Civil Procedure and its first sentence states:
“ ‘Prevailing party’ includes the party with a net monetary recovery, a defendant in whose favor a dismissal is entered, a defendant where neither plaintiff nor defendant obtains any relief, and a defendant as against those plaintiffs who do not recover any relief against that defendant.” (§ 1032, subd. (a)(4), italics added.)
The four categories of litigants identified in this provision must be treated as a prevailing party for purposes of awarding costs and the superior court has no discretion to deny them prevailing party status. (Michell v. Olick (1996) 49 Cal.App.4th 1194, 1197; see Code Civ. Proc., § 1032, subd. (b) [recovery of costs as a matter of right].) In comparison, the second sentence of in subdivision (a)(4) of section 1032 of the Code of Civil Procedure states:
“If any party recovers other than monetary relief and in situations other than as specified, the ‘prevailing party’ shall be as determined by the court, and under those circumstances, the court, in its discretion, may allow costs or not and, if allowed, may apportion costs between the parties on the same or adverse sides pursuant to rules adopted under Section 1034.” (§ 1032, subd. (a)(4), italics added.)
Davis's opening brief requests that the judgment be reversed and the matter remanded back to the trial court for the entry of a judgment stating that he, “as the prevailing party, shall be awarded allowable costs pursuant to California Code of Civil Procedure section 1032.” His opening brief, however, does not address the question of whether the plaintiff in a taxpayer action who obtains a judgment requiring a defendant to disgorge (i.e., refund) money to a defendant public entity is “the party with a net monetary recovery” for purposes of the first sentence of subdivision (a)(4) of section 1032 of the Code of Civil Procedure. Stated another way, this issue is whether Davis, as a plaintiff who recovered nothing for himself, is the party with a net monetary recovery. (See Black's Law Dict. (12th ed. 2024) [“net” means “[t]he final amount remaining after all other amounts have been taken away”].) The respondent's brief also does not address the issue of how subdivision (a)(4) of section 1032 of the Code of Civil Procedure applies to these circumstances.
In the absence of reasoned argument by the parties supported by citation of authority (Cal. Rules of Court, rule 8.204(a)(1)(B)), we conclude the better course is for the trial court to decide the question of who, if anyone, is the prevailing party. This approach will give the parties an opportunity to address the application of the first and second sentences of subdivision (a)(4) of section 1032 of the Code of Civil Procedure to the facts of this case.
DISPOSITION
The judgment is reversed and the cause remanded to the trial court with directions to enter, no later than 10 days after the issuance of remittitur, a modified judgement that includes the following terms:
1. On Plaintiff's causes of action for noncompliance with Education Code section 17406 and violation of the competitive bidding statutes, judgment is entered against Defendants and in favor of Plaintiff such that Defendant Harris Construction Co., Inc. shall return $236,129 in profit to Defendant Fresno Unified School District.
2. Judgment on Plaintiff's remaining claims is entered against Plaintiff and in favor of Defendants.
The trial court also is directed to conduct further proceedings not inconsistent with this opinion, which proceedings are not necessarily limited to determining the prevailing party for purposes of an award of costs; the amount of costs awarded, if any; and the entitlement to and the amount of an award of attorney fees.
Appellant Davis shall recover 50 percent of his costs on appeal from respondents.
FOOTNOTES
1. As explained in part III.C. below, the Davis I interpretation applies in this appeal pursuant to the doctrine of law of the case, not the conflicting statutory interpretation adopted in decisions of other districts of the Court of Appeal. In Davis v. Fresno Unified School Dist. (2023) 14 Cal.5th 671 (Davis III), the Supreme Court stated, “that split of authority is not before us.” (Id. at p. 684.)
2. An overview of validation actions by public agencies and reverse validation actions is set forth in part I.C. of Davis v. Fresno Unified School Dist. (2020) 57 Cal.App.5th 911, 927–929 (Davis II). California has over 200 statutes, mostly in the Government Code and Water Code, that authorize validation proceedings. (Davis II, supra, at p. 929.) The statute at issue in Davis II and Davis III was Government Code section 53511, which authorizes local agencies to bring an action to determine the validity of its bonds, warrants, contracts, or obligations or evidence of indebtedness pursuant to the validation provisions in the Code of Civil Procedure.
3. A request for qualifications asks for information about how the responding firm is qualified to provide the requested services, which is more general than a request for proposals regarding a particular project.
4. In Davis I, we noted that “counsel for Fresno Unified stated during oral argument [on March 24, 2015,] that there was no preconstruction contract.” (Davis I, supra, 237 Cal.App.4th at p. 295, fn. 18.)
5. Davis I and Davis II were decided at the pleading stage, when we were not informed of the steps Fresno Unified had taken before the preconstruction services agreement was signed. Those steps included (1) the board's approval, in concept, of a new middle school located in southwest Fresno; (2) the board communications describing the three basic project delivery methods and the use of a Preliminary Services Agreement with the contractor; (3) RFQ No. 110327 and its description of the lease-leaseback method of project delivery; (4) the board's 2011 approval of the prequalification of 14 construction firms, including Contractor, pursuant to RFQ No. 110327; and (5) Fresno Unified's use of lease-leaseback arrangements for projects predating the Gaston Project. Why defendants did not seek judicial notice of this information, particularly RFQ No. 110327 and the board's 2011 prequalification of Contractor in connection with their pleading-stage challenges to Davis's claims, is unknown. Counsel for each party could offer no reason for these omissions at oral argument. That information would have significantly affected our analysis of Davis's conflict of interest claims.
6. The Site Lease is the “lease” in the lease-leaseback arrangement and the Facilities Lease is the “leaseback.” (Davis I, supra, 237 Cal.App.4th at pp. 271–272.)
7. Shortly after remittitur was issued in Davis III, Davis filed an application to set a trial date. Subtracting the time spent on the appeals, Davis calculated that the five-year period for bringing the case to trial would expire on October 16, 2023. (See Code Civ. Proc., § 583.310.) At the hearing on the application, the trial court, on its own motion, extended the five-year deadline to April 30, 2024, and set trial for March 18, 2024.
8. Section 17406 was amended in 2014, 2015, 2016, and 2021. (See Stats. 2014, ch. 408, § 1; Stats. 2015, ch. 214, § 1; Stats. 2016, ch. 521, § 2; Stats. 2021, ch. 666, § 5.) Section 17406's predecessor was former section 15705 of the Education Code. (See Stats. 1959, ch. 2, § 1; Davis I, supra, 237 Cal.App.4th 282.)
9. The italicized words “such” and “thereof” were changed to “this” and “of the lease,” respectively, by the 2014 amendment. (See Stats. 2014, ch. 408, § 1.)
10. The Facilities Lease stated the parties understood that Fresno Unified payment obligations were a current expense and “shall not in any way be construed to be a debt of [Fresno Unified.]” Thus, the Facilities Lease recognizes that the project's financing is not coming from Contractor.
11. In Davis II, 57 Cal.App.5th 911, we stated: “The existence of a standard 5 percent retention does not establish, as a matter of law, that Contractor provided a financing component to Fresno Unified under the [lease-leaseback c]ontracts.” (Id. at p. 941.)
12. The protections of this provision did not extend to contractors that performed work under lease-leaseback agreements that failed to comply with section 17406 because such agreements are not obtained through “the competitive bidding process.” (Pub. Contract Code, § 5110, subd. (a).)
13. This condition appears to prevent the safe harbor from extending to lease-leaseback arrangements that violate California's conflict of interest laws. Because we have upheld the trial court's determination that no conflict of interest had been proven, we need not address the various arguments raised by the parties about the safe harbor provision's impact on the remedies available when a lease-leaseback arrangement violates section 1090.
14. In contrast, the terms “shall” and “may” are defined by Education Code section 75: “ ‘Shall’ is mandatory and ‘may’ is permissive.”
15. Despite 2012 being a leap year, Diel divided the yearly totals by 365 days, rather than 366 days, which slightly overstated the 2012 daily averages. Had 366 days been used, they would have been $186,420.80 and $8,869.07, respectively. Davis has not raised this error. For that reason and its de minimis impact, we do not address that error further.
16. This argument is off point because the failure to comply with section 17046 is not necessarily a violation of California's conflict of interest laws and a contractor with a conflict of interest would not be able to satisfy the fourth condition to be eligible for the safe harbor's protection. (See § 17406, subd. (d)(1)(D).)
17. The Cost Accounting Manual is available online at the State Controller's website
18. In the context of this case, the “individual end cost objective” was phase 2 of the Gaston Project.
19. We note that Public Contract Code section 5110, the provision on which section 17406's safe harbor was modeled, has not been declared unconstitutional. (Senate Floor Analysis, supra, at p. 7 [safe harbor “modeled after Public Contract Code provisions that protect against disgorgement if the contract is invalidated because of a defect in the bidding process”].)
FRANSON, J.
WE CONCUR: DETJEN, Acting P. J. SNAUFFER, J.
Thank you for your feedback!
As the largest network of trusted legal brands, we help firms build authority across the platforms consumers and AI systems rely on most. Our network helps attorneys strengthen visibility, credibility, and preference where legal decisions begin.
Docket No: F089619
Decided: October 22, 2026
Court: Court of Appeal, Fifth District, California.
Search our directory by legal issue
Enter information in one or both fields (Required)
Harness the power of our directory with your own profile. Select the button below to sign up.
Learn more about FindLaw’s newsletters, including our terms of use and privacy policy.
Make It a Preferred Google Search Source
Add to GoogleGet help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)